Description of Decision a) That progress regarding housing development schemes to be considered by Benedict Bedford Limited be noted. b) That progress against objectives set out in the Project Initiation Document agreed in May 2017 be noted. Reason for Decision To update members of the Housing Committee on activity to provide Benedict Bedford Limited with housing development opportunities.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1This report sets out the progress to date regarding housing development schemes to be considered by BBL, and reviews progress against objectives set out in the Project Initiation Document agreed in May 2017 when the housing company was being created.
Recommendations
2.1That the Committee notes (a) the progress regarding housing development schemes to be considered by BBL, and (b) progress against objectives set out in the Project Initiation Document agreed in May 2017.
Reasons for recommendations
3.1The purpose of the report is to update members of the Housing Committee on activity to provide BBL with housing development opportunities.
4. Key Implications
4.1The recommendation does not involve any key implications at this stage.
7(1) Legal Issues
4.2Members will recall the Company is a distinct legal entity from the Council and has Directors and a Company Secretary appointed to deal with its business.
4.3The Company’s business objectives are set out in an agreement between the Company and the Council and are informed by a confidential Remit Document which has been set by the Council as sole shareholder through the Shareholder Board.
Policy Issues
4.4All relevant Council Policies will be taken into consideration as this matter progresses.
Resource Implications
4.5Business Cases have been prepared to support the development of the Company in order to enable the commencement of trading and further strategies for investment in development opportunities are being drafted.
4.6The Company will be able to commence trading once its start-up loan has been received, anticipated to be by the end of April 2018
Risk implications
4.7Risk Management is being undertaken in accordance with the Council’s Risk Management Strategy.
Environmental Implications
4.8None.
Equalities Impact
4.9Section 149 of the Equalities Act 2010 will be considered where applicable during this process.
7(2) 5. Details
5.1The Officer Project Board has continued to meet on a regular basis. The last meeting took place on 13th March 2018 with the next meeting due 11th April 2018.
5.2The Council is working to supply the Company with a ‘pipeline’ of potential sites. Preparing the pipeline will require investment in officer time in obtaining pre-planning advice, which will be critical in discussions with the Company on any site purchases.
5.3The following table summarises potential development site pipeline activity:
Potential development Activity summary Target date Current Status schemes First development A full planning application is being prepared, Date for achieving Submission of the full scheme identified in the having regard to the advice received from planning permission for planning application is Remit Document Planning & Highways in pre-application the first site was set as expected by 30 April 2018 feedback. It has commissioned additional 31 December 2017 in and a decision received by supporting surveys. In its current design, the the original PID (dated mid-July. site is capable of providing 14 units. May 2017). The Council procured The Company has declared that in the first additional surveys and instance it intends to develop this first site as advice to assist with the a single project before taking on any future planning application developments, so that any lessons learnt (including pre-app advice) can be applied to future developments, which contributed to the minimising risk to the Company and Council. change in timescale.
Second site in remit Tender documentation is being prepared for Drawings to be received Tenders expected by end document provision of sketch schemes, which will be mid-June for of April 2018. used to consult local stakeholders. consultation with If there is general stakeholder support then stakeholders
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.