RESOLVED : That the report be received and that the Capital Virement of £1.820 million (£0.220 million 2018/2019 and £1.600 million 2019/2020) from the Property Investment & Development Fund to the Servicing Land at Fairhill Budget to meet the additional costs of infrastructure on the site, be approved.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
That the Capital Virement of £1.820 million (£0.220 million 2018/2019 and £1.600 million 2019/2020) from the Property Investment & Development Fund to the Servicing Land at Fairhill Budget to meet the additional costs of infrastructure on the site be approved.
Reason for recommendation
To advise Full Council of the increased infrastructure costs in relation to the Fairhill site. Undertaking the infrastructure work increases the value of the site and therefore the forecast capital receipts and as such meets the criteria of the Investment and Development Fund.
Details
Land at Fairhill totalling 16 acres has been allocated in the Local Plan for development as employment land (14 acres) and a hotel site (2 acres) subject to Policy AD18. As the employment land is too small for most major developers and too large for most end users, it was decided to enhance both the capital receipt and the appeal of the land to the market by obtaining outline planning consent and providing the infrastructure and services so that the site could be marketed as individual serviced plots.
The budget provision as set out in the current Capital Programme is £0.507 million in 2018/2019. The shortfall in budget will be vired from the Property Investment and Development Fund on the basis that the investment will achieve a financial return. The purpose of the Virement is therefore to reflect in the Capital Programme where the cost, leading to financial return, is being incurred.
12.1(1) There has been an increase from the initial estimate due to a number of factors:
a. Scope –utility routes and improvements to Fairhill are required to fully service the land which is higher than initially anticipated; b. Planning & Design fees are higher than anticipated; c. Utility connections – confirmed prices from utility companies are higher than originally budgeted; d. Asbestos has been found on site affecting a significant area of land; e. Japanese Knotweed was discovered to affect the eastern side of the site; f. To satisfy planning requirements additional surveys have been required once the presence of badgers on site was discovered, and to provide evidence that great crested newts are not present; g. Construction costs have increased since the initial estimate.
Construction of the infrastructure is ready to commence March 2019 with completion September 2019, subject to utility companies working to programme.
DAVE HODGSON Mayor
12.1(2)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Report of the mayor/executive membersThat the use of the Special Urgency Procedure be noted. (2) Membership of Executive and Changes to Executive Committe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.