Description of Decision That Full Council be recommended to approve the revised Capital Programme outlined at Appendix A having regard to the consultation responses received to date. * Reason for Decision To enable the consideration of additions and variations to the Capital Programme 2019/2020 to 2022/2023. *Approval of recommendations to Full Council are not subject to call-in as the decision is one for Full Council.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
The Council’s capital programme sets out how we invest money in schemes and projects to improve Bedford Borough. With reducing resources it is vital that we use the limited funds available for projects that offer a real benefit. We are consulting on this year’s capital programme, which includes:
Wixams Schools: a £29 million scheme, of which the Council is proposing to contribute £5.2 million, in order to meet the demand for additional school places in the area by increasing capacity. This is a joint project with Central Bedfordshire Council who are also contributing funding as are the developers in Wixams.
Riseley School: a £4.4 million scheme of which the Council is proposing to contribute £4 million. The scheme will involve demolishing the existing main block of the school following conversion to a Primary School and the building of a new main block. Allhallows Public Realm: this scheme will look to resurface the area around Allhallows to improve the built environment and encourage greater use of this area. The estimated cost is £2.5 million of which the Council is proposing to contribute £0.755 million.
Bedford Park Cricket Pavilion: at a cost of £0.341 million, with the Council proposing to contribute £0.118 million, we are looking to bring the building back into use for the community and enhance the facilities within the building including changing rooms and shower facilities.
CCTV in Norse Road cemetery: a £0.072 million scheme which the Council is proposing to fund entirely aims to extend the CCTV system to cover the cemetery extension area and improve security.
Methodology
We consulted on the proposed capital schemes from 13th December 2019 to 17th January 2020. Respondents could complete an online response form, send an email or write in with their comments. The consultation was promoted alongside the Budget Consultation in the following ways. • Dedicated page on the Council’s website • Included on the Consultations Database (www.bedford.gov.uk/yourvoice) • Email bulletins sent to the ‘Your Voice, Your Views’ e-bulletin (circa 7,500 subscribers)
2 • Email sent to all Town & Parish Councils • Email sent to the Bedford Borough Community Network (circa 220 members) • Included in the Community & Voluntary Sector (CVS) newsletter • Included in the ‘Bedford for Business’ e-bulletin • Hard copies placed in all Borough Libraries, Borough Hall and the Customer Contact Centre • Promoted via the Council’s Twitter (circa 11,500 followers) • Press releases to the local press, resulting in coverage in the Bedford Independent and the Times and Citizen
Response
Overall, we received 67 responses. 61 were received via the online response form and 6 were received via email. This included response from a range of individuals and the following organisations: • Midland Road Area Residents' Association • Oakley Parish Council • Riseley Community Centre & Children’s Hub Project • Riseley School
This report presents the responses received, and all comments are reproduced verbatim.
3 Wixams Schools: a £29 million scheme, of which the Council is proposing to contribute £5.2 million, in order to meet the demand for additional school places in the area by increasing capacity. This is a joint project with Central Bedfordshire Council who are also contributing funding as are the developers in the Wixams.
To what extent do you support or oppose this proposal?
Strongly support 5 Support 14 Neither support not oppose 8 Oppose 3 Strongly oppose 2 Don't know / no opinion 8
Please give any comments, ideas or alternative proposals you may have.
Housing developers should contribute more to the additional resources required for new builds. Individual
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.