Transfer of Environment Agency Public Safety Control Measures to Bedford Borough Council

Approved Executive 1 paper

Executive approved this item on Wednesday 6 January 2021. Below is the council's own wording, with the papers it was decided on.

Item60

Resolved

Description of Decision That the transfer of the safety control measures (booms) at Duckmill and Newnham Weir from the Environment Agency to Bedford Borough Council be approved. Reason for Decision To protect river users from potential harms of a Council structure namely the weirs and sluice gate. Should the Council decide to not accept these control measures alternative arrangements would need to be made to protect the river users, which would be an additional expense and burden to the Council.
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Executive, 16 pages

Executive summary

Proposed transfer of the Environment Agency safety control measures (booms) at Duckmill and Newnham Weir to Bedford Borough Council. The report considers the impact this will have on the Council both financially, operationally and the effect for river users.

2. Recommendations That the Executive consider, and if satisfied, agree to support the approval of the transfer of the safety control measures (booms) at Duckmill and Newnham Weir from the Environment Agency to Bedford Borough Council.

Reasons for recommendations

It is recommended that Bedford Borough Council take control of these safety assets “booms” to protect river users from potential harms of a Council structure namely the weirs and sluice gate. Should the Council decide to not accept these control measures alternative arrangements would need to be made to protect the river users, which would be an additional expense and burden to the Council.

8(1) 4. Key Implications

(a) Policy

The Council’s Corporate Plan 2017-2021 focusses on priority areas, which will help ensure that Bedford Borough continues to be a place where people want to, live, work and spend their leisure time. One of the priorities is “Bedford Borough is seen as the place to grow and has a good quality local Environment”. By the Council taking ownership of these safety control measures it will protect users when they participate in leisure activities on the river.

(b) Legal Issues

Legal point of view, as the Council are the riparian landowners of the Newnham/Duckmill weir and sluice, we are obliged to maintain and operate the structures. The safety control measures (including the two booms), installed by the Environment Agency can be removed and the Council are not obliged to keep them. However, removal of these safety measures would give rise to safety concerns for river users.

(c) Resource Implications

There are no immediate resource implications identified which are not already being met from existing budgets to manage these Council structures. The booms are in place and have an expected life expectancy of 35 years. Visual inspections will continue to be carried out within existing resources.

The booms are designed to add protection to the Council assets/structures by helping stop any large debris damaging weirs, sluice gates and other structures. Whilst there is no foreseen immediate resource implications, there is always a risk of vandalism or other types of damage occurring to the booms and/or the assets that the booms are designed to protect (for example weirs, sluice gates etc.). However, in terms of maintenance costs, this risk is believed to be significantly lower than the risk of the booms being removed and the potential extensive cost likely if debris was to damage existing Council assets.

(d) Risk Implications

A weir can be dangerous to all river users, especially after heavy rain, an overflowing weir can become extremely dangerous due to the fast flowing volume of water flowing down it. It is therefore imperative that preventative measures such as water safety booms are in place upstream from the structures to ensure the safety of all our river users. Without

8(2) these safety control measures remaining in place there is nothing to stop serious injury or drowning or damage to the Council strictures from floating debris.

Currently, the safety booms are in front of the Council’s structures and the Environment Agency have asked that Bedford Borough Council takes ownership of these control measures (wire line buoys), otherwise the Agency will remove them and leave the structure (weir and sluice gate) unguarded which will become a risk to river users.

(e) Environmental Implications and contribution to achieving a net zero carbon Council by 2030

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Transfer of Environment Agency Public Safety Control Measures to Bedford Borough CouncilReport 16 pages DownloadRead as text

At this meeting

Whole meeting

More from Bedford Executive

All decisions
MeetingDecisionOutcome
15 Jul 2026 Minutes of Previous MeetingDescription of Decision That the Minutes of the meeting of the Executive held on 3 June 2026 be confirmed. Reason for... Decided Open
15 Jul 2026 Local Government and Social Care Ombudsman Annual Review Letter 2025/2026Description of Decision That the Local Government and Social Care Ombudsman’s Annual Review letter for 2025/2026 for ... Noted Open
15 Jul 2026 RIPA Annual ReportDescription of Decision (1) That it be noted that, in the period 1 April 2025 to 31 March 2026, there were no applica... Noted Open
15 Jul 2026 Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026... Approved Open
15 Jul 2026 Corporate Plan 2024-2028 Performance Report year-end 2025/2026Description of Decision That the latest performance as outlined within the Key Indictor Performance Report at Appendi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies