Description of Decision That Full Council be recommended to approve the revised Capital Programme outlined at Appendix B of the report. Reason for Decision To enable the consideration of additions and variations to the Capital Programme. *Approval of recommendations to Full Council are not subject to call-in as the decision is one for Full Council. To enable the consideration of additions and variations to the Capital Programme. *Approval of recommendations to Full Council are not subject to call-in as the decision is one for Full Council. Cllr Headley/ACE(ES)
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To consider, and if satisfied, to recommend to Full Council, the Council’s Capital Programme for financial years 2020/2021 to 2023/2024 and future years.
Recommendations
The Executive is requested to consider the report and, if satisfied, to recommend to Full Council the revised Capital Programme outlined at Appendix B.
Reason for recommendations
To enable the Executive to consider additions and variations to the Capital Programme.
4. Key Implications
(a) Policy
The Council’s Capital Strategy sets the framework for the Capital Programme and incorporates Prudential Indicators that are set to ensure that capital investment is prudent, sustainable and affordable. It provides the overarching capital strategy and linkage of priorities from the Corporate Plan, Directorate Service Plans and the Corporate Asset Plan. The Capital Strategy requires the Council to undertake public consultation on proposed new scheme bids for inclusion in the Council’s Capital Programme. 13(1) Executive – 20 January 2021 Capital Programme (b) Legal Issues
The Local Government Act 2003 provides the legal basis for capital finance, namely a general power to borrow and a duty to set an affordable borrowing limit. The Local Authorities (Capital Finance and Accounting) Regulations 2003 provides operational detail and specifically states that Authorities must have regard to CIPFA’s Prudential Code when setting and reviewing borrowing limits.
(c) Resource Implications
The Capital Programme is funded from a number of sources including specific grants/external funding, capital receipts, revenue contributions, Community Infrastructure Levy (CIL), Section 106 and borrowing. Borrowing defrays the cost of the capital spending over a predetermined period of time and gives rise to the Minimum Revenue Provision (MRP) being the setting aside of Revenue Budget for the repayment of debt. The overall programme must be assessed in terms of estimated revenue implications of each scheme including their impact on Council Tax in terms of affordability.
(d) Risk Implications
In relation to Capital resources, the following risks should be taken into account when considering this report:
(1) New capital schemes can emerge at any time based on newly identified needs or changes in legislation which require funding to be identified; (2) The forecast cost/timing of existing schemes and the ability to undertake schemes may vary as implementation is undertaken; (3) Forecast capital receipts may not be achieved which will result in some schemes not proceeding until other sources of capital finance become available or unless further recourse is made to borrowing; (4) External contributions may not fully materialise and, as such, there is a risk that schemes relying on external funding may require alternative sources of funding to be identified.
(e) Environmental Implications
There are no environmental implications arising directly from the report. The environmental impacts of each capital scheme are considered as part of their implementation.
13(2) Executive – 20 January 2021 Capital Programme (f) Equality Impact
In preparing this report, due consideration has been given to the Borough Council’s statutory Equality Duty to eliminate unlawful discrimination, advance equality of opportunity and foster good relations, as set out in Section 149(1) of the Equality Act 2010. A relevance test for equality has been completed. The equality test determined that the content of the report has no relevance to Bedford Borough Council’s statutory equality duty to eliminate unlawful discrimination, advance equality of opportunity and foster good relation. An equality analysis is not needed. Individual capital bids may, however, have specific equality impacts that need to be considered and evaluated.
5. Details
Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Social Housing Allocations PolicyDescription of Decision (1) That the publication of the revised Bedford Borough (at Appendix A) on 1st September 2026...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.