That the Food and Feed Service Plan 2021/2022 be approved. (b) 2020/2021 Revenue and Capital Budget Trends Councillor Headley moved, and the Mayor seconded, that the report be received and the recommendations be adopted. Councillor Headley advised that Council was required to approve changes to the Capital Programme that had arisen as a result of the costs for schemes being greater than anticipated following the respective tender processes. On the motion being put to the meeting, the Speaker declared it to be carried. RESOLVED : (1) That a virement from the Temporary Accommodation Budget to the Next Steps Accommodation Budget of £0.845 million reflecting an increase in project costs be approved. (2) That an increase in the Depot Enhancements Budget reflecting additional works required of £0.898 million funded from (i) £0.144 million from Highways (BBC funded) Budget, (ii) £0.025 million from Carbon Management Programme Budget and (iii) £0.729 million increase in the Capital Financing Requirement be approved. (c) Medium Term Financial Strategy Refresh Councillor Headley moved, and the Mayor seconded, that the report be received and the recommendation be approved. On the motion being put to the meeting, the Speaker declared it to be carried That the report be considered and the updated Financial Forecasts at Appendix A and the Medium Term Financial Strategy at Appendix C of the report be approved.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
To consider the latest trends in respect of the 2020/2021 revenue and capital budgets and emerging budget issues.
Recommendations
Full Council is requested to consider the report and, if satisfied, approve the following in relation to the Capital Programme for 2021/2022:
a) A virement from the Temporary Accommodation Budget to the Next Steps Accommodation Budget of £0.845 million reflecting an increase in project costs, and
b) An increase in the Depot Enhancements Budget reflecting additional works required of £0.898 million funded from (i) £0.144 million from Highways (BBC funded) Budget, (ii) £0.025 million from Carbon Management Programme Budget and (iii) £0.729 million increase in the Capital Financing Requirement.
Reason for recommendations
To consider the latest trends in respect of the 2020/2021 Revenue Budgets and emerging budget issues that impact on the Council’s Medium Term Financial Strategy and reflect cost pressures in relation to two capital schemes.
Revenue & Capital Budget Trends 12.2(1) 4. Key Implications
(a) Policy Issues
The Medium Term Financial Strategy (MTFS) states that, to ensure a continuously stable financial base for the provision of Council services and functions, the Council will ensure that annual ongoing General Fund revenue expenditure can be covered by annual income sources in each and every financial year. The MTFS requires regular reports to be submitted to the Executive in respect of budget trends and the report, therefore, provides an update on the latest budget position and also identifies a number of emerging budget issues that will need to be monitored during the remainder of 2020/2021.
The MTFS also requires that due regard is given to revenue budget forecasts and that any increase in the ongoing annual revenue budget will be subject to the expenditure being either legally unavoidable or considered affordable after taking into account:
(a) any forecast savings targets; (b) implications on Council Taxpayers in future years.
This is especially relevant this year with the implications of COVID-19.
(b) Legal Issues
The Council is required, by law, to set a balanced Revenue Budget each year which for 2020/2021 was approved by Full Council on 5 February 2020. The purpose of this report, in accordance with best financial management practice, is to advise the Executive of significant variations from that budget.
(c) Resource Implications
The Council’s approved 2020/2021 gross General Fund Revenue Budget reported to Full Council on 5 February 2020 totalled £365.137 million, this is reduced by income from specific grants, subsidies, fees, charges and rents which can be subject to variation as well as fixed income sources such as commuted sums, planned use of Reserves giving a net budget requirement of £132.047 million.
The net budget requirement is financed as follows:
Revenue & Capital Budget Trends 12.2(2) 2020/2021 Original Budget £million Net Budget Requirement 132.047
Financed by: Revenue Support Grant 5.861 Local Business Rates 30.343 Council Tax Yield 95.843
A review of forecast expenditure and income has highlighted that there are variations compared to the approved budget and, as such, these variations are set out in this report.
(d) Risk Implications
When the Council considers each revenue service and function budget it is important that endeavours are made to identify potential risks. Inevitably, during the course of the financial year risks occur and impact the budget by either requiring further expenditure or by reducing the Council’s budgeted income.
The budget is monitored on a monthly basis to identify risks and take action to mitigate risks when they arise. The Council holds a contingency with regard to budgetary risk in year, together with a range of Reserves to deal with specific issues and a General Fund Balance of £16.317 million.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Report of the mayor/executive membersThat the use of the Special Urgency Procedure be noted. (2) Membership of Executive and Changes to Executive Committe...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.