Resolved
RESOLVED That the contents of the report be noted. COE
Environment and Sustainable Communities Overview and Scrutiny Committee noted this item on Thursday 22 April 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED That the contents of the report be noted. COE
This report follows previous reports / presentations made to the Committee in November 2017, November 2018, July 2019 and March 2020; and summarises work undertaken to date on the Transporting Bedford project.
That the report is noted.
For the Committee to fully consider the development and implementation of the Transporting Bedford project.
4. Key Implications
(a) Policy The Transporting Bedford project seeks to deliver parts of the Council’s policy framework in respect of: Local Transport Plan Sustainable Community Strategy
7(1) Environment Committee / 22 April 2021 / Transporting Bedford (b) Legal Issues Grant funding provided by SEMLEP is covered by a legal agreement.
Legal agreements to transfer land for highway use have been completed with both the Harpur Trust and the Bedford Hospital Trust to enable construction of elements of the scheme.
(c) Resource Implications The Transporting Bedford project is jointly funded from the DfT’s Local Growth Fund (administered by SEMLEP), the DfT‘s National Productivity Infrastructure Fund and the Council’s capital programme (as agreed by Council in January 2018). The table below shows the total project budget allocations.
Funding Source Funding
Local Growth Fund 2 £11,000,000 Local Growth Fund 3 £4,500,000 National Productivity Infrastructure Fund £3,500,000 Total External Funding £19,000,000
Section 106 contributions £358,012 Community Infrastructure Levy £1,350,000 BBC Structural Maintenance Programme £2,987,000 Total Internal Funding £4,695,012
Total Funding £23,695,012
(d) Risk Implications A Quantified Risk Register has been developed for the project. Identified “High Risks” as at January 2021 include: Scheme budget pressures The ability to quantify scheme benefits in light of changes to transport and travel patterns arising because of Covid
7(2) Environment Committee / 22 April 2021 / Transporting Bedford (e) Environmental Implications Part of the technology elements of the project includes installing further air quality monitoring equipment. Data outputs from that equipment can be used to drive traffic management strategies in real time.
Key outputs from the project include a reduction in vehicle km within the core urban area and stabilisation of journey times (i.e. linked to less traffic congestion)
(f) Equalities Impact None arising from this report. Detailed design of individual elements of the project respects the Council’s equality impact duty and policies.
5. Details
5.1Between 2014 and 2017 the Borough Council undertook a Transport Strategy development process to support enhancements to the town centre, as well as to integrate with wider issues, such as the Local Plan process, the One Public Estate programme, the Oxford to Cambridge Corridor (including the Expressway and East West Rail) and enhancements to the Midland Mainline. A wide range of transport policy, strategy and scheme options were considered for Bedford town centre through this process.
5.2The strategy development process identified a number of preferred scheme options for developing the town centre as a whole and identified a set of measures focussed upon enhancing accessibility to and within the core town centre, and extending out to the former A6 corridors to the north and south of the town.
5.3These measures are broadly categorised within the following three themes: Theme 1: Town Centre Public Realm Theme 2: Alleviating Pinch-points Theme 3: Urban Traffic Management Control (UTMC) & Technology measures
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Transporting BedfordReport | 6 pages | DownloadRead as text |
Follow Environment and Sustainable Communities Overview and Scrutiny Committee at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Previous MinutesRESOLVED That the Minutes of the meeting of the Committee held on the 18 June 2026 be confirmed. Chair | Decided | Open |
| 16 Jul 2026 | Local Plan 2050RESOLVED That the Committee noted the update. HCPI&ST | Noted | Open |
| 16 Jul 2026 | Executive DecisionsRESOLVED 1. The Committee noted that there were no meetings of Executive prior to the publication of the agenda, deci... | Noted | Open |
| 16 Jul 2026 | Notice of Forthcoming Decisions to be taken by the ExecutiveThat the Notice of Forthcoming Decisions for the period 1 August 2026 to 30 November 2026 be received. SDSO | Decided | Open |
| 16 Jul 2026 | Committee Work ProgrammeThat an item on Biddenham (Great Ouse Way) Country Park be added to the Committee’s Work Programme. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.