Resolved
That the Minutes of the meeting of the Partnership Board held on 21 January 2022 be approved. Chair
Bedford High Street Heritage Action Zone approved this item on Friday 22 April 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Minutes of the meeting of the Partnership Board held on 21 January 2022 be approved. Chair
AT A MEETING
of the
BEDFORD HIGH STREET HERITAGE ACTION ZONE PARTNERSHIP BOARD
held on Friday, 21 January 2022 at 10am
PRESENT: Councillor Henry Vann (Chair) Hilary Chipping, SEMLEP - South East Midlands Local Enterprise Partnership Will Fletcher, Historic England - Development Advice Team Leader - East Region Ian Johnson, Manager for Heritage & Planning Compliance - Bedford Borough Council Tom Perrett, Manager for Libraries & Culture – Bedford Borough Council Christina Rowe, Love Bedford (Bedford BID) Jon Shortland, Chief Officer for Planning, Infrastructure and Economic Growth – Bedford Borough Council
Also present:
Councillor Doug McMurdo (Observer) Eleanor Karklas, Manager for Economic Growth and Development - Bedford Borough Council Jessica Mittler, High Street Heritage Action Zone - Project Manager - Bedford Borough Council
Apologies for absence were received from:
Elaine Midgley, Bedford Creative Arts, Chris Morris, Manager for SEND Programme – Bedford Borough Council, Joe Warburton, Historic England - HSHAZ- Project Officer - East of England, and David Wilkins, Bedford College - Construction & Building Service.
1 38. MINUTES AND MATTERS ARISING
There were no matters arising reported.
RESOLVED:
That the Minutes of the meeting of the Partnership Board held on 22 October 2021 be approved.
39. DISCLOSURES OF LOCAL AND/OR DISCLOSABLE PECUNIARY INTERESTS
There were no disclosures of local and/or disclosable pecuniary interests reported.
40. PROGRESS UPDATE LETTER / 6 TH DEC. 2021
i) Outcome grant increase No. 58 a/b/c
The High Street Heritage Action Zone - Project Manager advised that the grant had to be increased as the tender had come back much higher than first anticipated. The approval to increase the grant had enabled the project to go live. A forum of works was currently being awaited and a site visit had taken place to progress further with this. Another meeting was to take place to discuss the compound arrangements, as the building was located within a prominent space on the High Street. Furthermore, the scaffold ing banners were in the process of being produced as were banners for the harris fencing which were to tell the story of the building.
ii) Outcome grant increase No. 43
The High Street Heritage Action Zone - Project Manager reported that a grant increase had been requested as the tender had come back extremely high. The grant was to be increased to £200,000, in the hope that the project could have commenced immediately. However, there were still planning related issues which had needed to be addressed before the project started. This had included a missing noise report, which had still not been received. It was additionally outlined that the project was anticipated to
2 start during 2021/2022 financial year. However, was likely to carry on over into 2022/2023, with the main proportion of the bud get also being spent during this year.
The Chair highlighted that in terms of spending the funding, this was considered to be very important and he did not want to see any clawback. Furthermore, the Historic England - Development Advice Team Leader stated that Historic England were supporting the increase of grants and it had been recognised that the cost of materials had gone up considerably since the original proj ect estimates were completed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes and Matters ArisingMinutes | 9 pages | DownloadRead as text |
Follow Bedford High Street Heritage Action Zone at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 21 Apr 2023 | Minutes and Matters ArisingThat the Minutes of the meeting of the Partnership Board held on 27 January 2023 be approved [Note: the Minutes were ... | Approved | Open |
| 21 Apr 2023 | Progress Update - Community EngagementThat the progress update on Community Engagement be noted. T. Perrett | Noted | Open |
| 21 Apr 2023 | Cultural Consortium UpdateRESOLVED : That the Cultural Consortium ... view the full minutes text for item 25. Chair | Decided | Open |
| 21 Apr 2023 | Future Meeting DateRESOLVED : That the next meeting to be confirmed to be fixed in 3 months’ time. | Decided | Open |
| 27 Jan 2023 | Minutes and Matters Arisingi) That the Minutes of the meeting of the Partnership Board held on 22 July 2022 be approved. ii) That the Informal M... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.