Resolved
RESOLVED : i) That the reallocation of budget amounts to projects be approved. ii) That the Manager for Town Deal be authorised to submit project amendment forms to DLUHC. P Lyons
Bedford Town Deal Board approved this item on Tuesday 31 May 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED : i) That the reallocation of budget amounts to projects be approved. ii) That the Manager for Town Deal be authorised to submit project amendment forms to DLUHC. P Lyons
Agenda Item 7
Bedford Town Deal Board
Date - 31 May 2022
Report by - Manager for Town Deal
Subject - Amendments to Project Financial Profile Allocations
1. Town Deal Projects Financial Profile
1.1When Bedford was selected as a location to submit a Town Investment Plan for project proposals of up to £25m, the board approved schemes with a total cost estimate of £24.95m. Bedford was then awarded a Town Deal of £22.6m, 90% of the investment plan request.
1.2A project and programme confirmation was approved by the Town Deal Board at the 3 August 2021 meeting, and submitted to DLUHC on 30 August 2021, which allocated budget amounts to enable the selected projects to be progressed. Bedford Borough Council was subsequently paid a 5% advance of the total Town Deal award to commence design of the projects and undertake accurate cost estimating, and to enable preparation of Green Book appraisal business cases.
As the project schemes had not then been developed, these were still high-level project cost estimates when submitted to Government
2. Project Financial Profile Reallocation Proposals
2.1Following draft design of the projects, detailed survey work and engagement with statutory consultees, project scopes and opportunities have developed, and have enabled a more accurate project costing of the schemes to be produced.
7 (1) 2.2. At the Town Deal Board meeting on 17 March 2022 and an in person Board member session on 10 May 2022, the latest project designs were presented to the board for comment and consideration.
2.3The request is to progress all of the selected Town Deal projects originally proposed in the project confirmation submission in August 2021, and seek approval to reallocate budget allocation between the schemes.
3. Reasoning for Financial Profile Reallocation Request
3.1Following the design of a number of the proposed pedestrian and cycling schemes, which required adherence to a new government standard (LTN 120), which emerged after the original Town Investment Plan submission, it transpired that a number of the originally proposed cycling and pedestrian projects where unaffordable due to the increased capital cost estimates.
3.2For example, work to install segregated cycling infrastructure on London Road that adhered to LTN 120 had a project cost estimate of £4.5m for the 2.2km route. Allocating that capital amount to this project would not achieve the required outputs to make the Benefit Cost Ratio positive, and consequently the Green Book appraisal business case would not be viable.
3.3Additionally, the scope of the Transporting Bedford 2030 project at St. Paul’s Square and Greyfriars developed significantly, whereby the design would incorporate a much greater element of pedestrian and cycling infrastructure than was originally predicted so that it would adhere to LTN 120.
3.4The increased cycling and pedestrian infrastructure at these two important traffic intersections and locations will have a significant impact in improving the centre of Bedford’s environment and accessibility. This will subsequently contribute greater to the economic regeneration of Bedford and fundamental Town Deal objectives.
3.5In summary, whilst the profiled budget allocation for the general pedestrian and cycling project is therefore reduced, the total spend is maintained and reallocated to deliver pedestrian and cycling outcomes and objectives within other Town Deal projects, at Greyfriars and St. Pauls Square.
3.6The original scope of the Transporting Bedford 2030 projects was resurfacing, repaving and some highway improvements, but will now entail fundamental changes that greatly improve conditions for pedestrian and cycle users.
7 (2) 3.7. Finally, following detailed survey work for the Midland Road public realm project, and further consideration of its consequential impact on traffic congestion in the wider town centre, a refined scheme has reduced the original cost estimate significantly.
3.8The below table details the proposal for reallocation of the projects profiled budget:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Amendments to project budget allocationsReport | 4 pages | DownloadRead as text |
Follow Bedford Town Deal Board at Bedford and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Apr 2024 | Election of ChairThat Sam Laycock be elected as Chair. Chair | Decided | Open |
| 8 Apr 2024 | Appointment of Vice-ChairThat Mayor Tom Wootton be elected as Vice Chair. Chair | Decided | Open |
| 8 Apr 2024 | MinutesThat the of the meeting of the Board held on 29 November 2023 be approved. Chair | Approved | Open |
| 8 Apr 2024 | New Board Member InvitationRESOLVED That the Board agreed that the Manager of Town Deal could approach Patrick Harnan, of Harnan Real Estate, in... | Agreed | Open |
| 8 Apr 2024 | Marketing, Promotion and Engagement updateThat the update on the marketing, promotion and engagement, be received. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.