The infrastructure Funding Statement and the use of S106 monies

Noted Scrutiny 1 paper

Environment and Sustainable Communities Overview and Scrutiny Committee noted this item on Thursday 2 March 2023. Below is the council's own wording, with the papers it was decided on.

Item54

Resolved

RESOLVED That the report be noted. CORSC
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Environment and Sustainable Communities Overview and Scrutiny Committee, 20 pages

Executive summary

This report explains the regime for producing the Infrastructure Funding Statement (IFS) which the Council is obliged to produce each year, and the rules governing its use. This follows publication of the 2021/22 IFS in December 2022 (which is available here: https://www.bedford.gov.uk/media/5299/download?inline).

Details are also provided regarding the use of the Community Infrastructure Levy (CIL) and the section 106 contributions traditionally used to make otherwise unacceptable developments approvable.

Finally, the report refers to the specific case of the pedestrian bridge between Great Denham Country Park and Kempston as requested by Members of the Committee.

Recommendations

That the report is noted.

Reasons for recommendations

So that Members are familiarised with the IFS and the collection of monies as part of the planning process.

(The infrastructure Funding Statement) 5(1) 4. Key Implications

(a) Policy The council became a CIL charging authority in April 2014. The Local Plan 2030 sets out the level of growth expected within the Borough, and the use of CIL is one of the ways of mitigating its potentially adverse impacts.

(b) Legal Issues The relevant legislation is the Community Infrastructure Levy (Amendment) (England) (No. 2) Regulations 2019, which came into force on 1st September 2019.

(c) Resource Implications There are no resource implications as a result of this report. The administration of CIL and production of the IFS are funded from the 5% fee allowed for these purposes by law.

(d) Risk Implications If CIL receipts are not used in accordance with the regulations, then the authority would be open to challenge by the developers who have paid the levy.

(e) Environmental Implications and contribution to achieving a net zero carbon Council by 2030 None as a consequence of this report

(f) Equalities Impact None as a consequence of this report

Background

CIL and S106

5.1S106 contributions remain the primary means for the Council to ensure that developments pay for infrastructure that makes them acceptable in planning terms. These contributions are negotiated between with developers, and can pay for anything from new roads to serve the development to affordable housing.

(The infrastructure Funding Statement) 5(2) 5.2. Through the Planning Act 2008, local authorities are allowed, but not required, to introduce a CIL. CIL is levied on a much wider range of developments then those affected by s106 agreements, and is paid according to a published tariff schedule. This spreads the cost of funding infrastructure over more developers and provides certainty as to how much developers will have to pay. Bedford introduced CIL in 2014.

5.3CIL is intended to provide infrastructure to support a development, rather than make an application acceptable in planning terms. There may still, therefore, be some site-specific impact mitigation requirements without which a site won’t be granted planning permission. A s106 planning obligation may therefore be imposed to ensure that the consequences of a development can be mitigated; so some developments may attract both a CIL liability and s106 obligations.

5.4Local Authorities in receipt of CIL or s106 contributions must now produce an annual Infrastructure Funding Statement, as a result of recent changes to government legislation – the CIL (Amendment) (England) (No.2) Regulations 2019.

IFS 2021/22

5.5The IFS sets out details relating to CIL and s106 payments for the year 1st April 2021 to 31st March 2022. The key headlines from the statement are as follows:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The infrastructure Funding Statement and the use of S106 moniesReport 20 pages DownloadRead as text

At this meeting

Whole meeting

More from Bedford Environment and Sustainable Communities Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Previous MinutesRESOLVED That the Minutes of the meeting of the Committee held on the 18 June 2026 be confirmed. Chair Decided Open
16 Jul 2026 Local Plan 2050RESOLVED That the Committee noted the update. HCPI&ST Noted Open
16 Jul 2026 Executive DecisionsRESOLVED 1. The Committee noted that there were no meetings of Executive prior to the publication of the agenda, deci... Noted Open
16 Jul 2026 Notice of Forthcoming Decisions to be taken by the ExecutiveThat the Notice of Forthcoming Decisions for the period 1 August 2026 to 30 November 2026 be received. SDSO Decided Open
16 Jul 2026 Committee Work ProgrammeThat an item on Biddenham (Great Ouse Way) Country Park be added to the Committee’s Work Programme. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies