Bedford Town Deal Board, Thursday 23 March 2023 at 6.00pm

Approving Town Deal Balance Reallocation

Approved Committee 1 paper

Bedford Town Deal Board approved this item on Thursday 23 March 2023. Below is the council's own wording, with the papers it was decided on.

Item48

Resolved

RESOLVED a) That the reallocation of remaining Town Deal budget award across the town deal projects be approved. b) That further to the approval of the change request by DLUHC, the release of funding to commence delivery of the projects be approved. P Jones/P Lyons
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Bedford Town Deal Board, 3 pages

Agenda Item 6

Bedford Town Deal Board

Date – 23 March 2023

Report by – Manager for Town Deal

Subject – Approving Town Deal Budget Reallocation

1. Town Deal Project Budget Allocation

1.1In the development of the business cases for the Bedford Town Deal, the Station Quarter project was projected to be the last of seven-business case to be submitted to DLUHC. A sizeable allocation of the total Town Deal award, £5.4m, was apportioned to the Station Quarter project.

1.2Following initial concept designs and project scheme estimates, including contingencies and allowance for inflation, a total scheme cost of £4.13m is now projected. This estimate has subsequently created a surplus from the total award, allowing some reallocation.

1.3The current project cost budget allocation for town deal projects is:

Health & Digital Skills Centre £3,000,000 St. Pauls Square Public Realm £4,735,258 Transporting Bedford 2030 £2,136,305 Pedestrian & Cycling Infrastructure £2,822,395

6(1) Midland Road Regeneration – Public Realm £2,373,931 Midland Road Regeneration – Shopfront Enhancements £1,440,000 Station Quarter £4,139,190 Project Management £625,000 Total £21,272,079 Remaining from allocation £1,327,921

2. Proposed Town Deal Project Budget Reallocation

2.1Post business case submission for the St. Pauls Square Public Realm, Transporting Bedford 2030, Pedestrian & Cycling Infrastructure, Midland Road Regeneration – Public Realm and Midland Road Regeneration – Shopfront Improvements business cases, new emerging opportunities to expand those projects have been identified.

2.2The proposed project cost budget reallocation for town deal projects is:

St. Pauls Square Public Realm +£245,000 Transporting Bedford 2030 +£180,000 Pedestrian & Cycling Infrastructure +£300,000 Midland Road Regeneration – Public Realm +£205,000 Midland Road Regeneration – Shopfront Enhancements +£400,000 Total +£1,330,000

2.3St Paul’s Square Additional activities to be completed with the increased St. Pauls Square public realm budget include the St. Pauls Churchyard project element. This will include opening up this key site for pedestrians and town centre users, with established lighting, pathways and removal of the knee-high walls and railings in certain sections of the site, which will assist with movement between public open space at St. Pauls Square, Harpur Square and Riverside Square. Apparatus and instillations to assist with the facilitation of events on Harpur Square, a key objective of the project, is also proposed.

6(2) 2.4. Transporting Bedford Extra contingency for the wider project and budget to assist with the relocating and maintenance of the Italian Statue, currently located in the centre of Greyfriars roundabout is recommended. The statue will need relocating to a new permanent public location, and options are being explored on how to cast in a new, more durable material, to protect from damage.

2.5Pedestrian and Cycling Infrastructure The additional funding will be spent on new wayfinding signage for the town centre as well as a contribution to the emerging Dame Alice Street Cycling scheme, which will be funded in part by Bedford Borough Council funds, a separate active travel fund bid as well as Town Deal funding.

2.6Midland Road – Public Realm It is recommended to increase the allocation of funding to the Midland Road – Public Realm project, which will be utilised for additional CCTV and street lighting on part of a number of the side residential streets leading from Midland Road.

2.7Midland Road – Shopfront Enhancements Additional funding is proposed for the shopfronts scheme, so additional buildings can be targeted to join the scheme, as well as consider possibility for community buildings, not originally included in the project specification, to be included in the project.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approving Town Deal Balance ReallocationAgenda 3 pages DownloadRead as text

At this meeting

Whole meeting

More from Bedford Bedford Town Deal Board

All decisions
MeetingDecisionOutcome
8 Apr 2024 Election of ChairThat Sam Laycock be elected as Chair. Chair Decided Open
8 Apr 2024 Appointment of Vice-ChairThat Mayor Tom Wootton be elected as Vice Chair. Chair Decided Open
8 Apr 2024 MinutesThat the of the meeting of the Board held on 29 November 2023 be approved. Chair Approved Open
8 Apr 2024 New Board Member InvitationRESOLVED That the Board agreed that the Manager of Town Deal could approach Patrick Harnan, of Harnan Real Estate, in... Agreed Open
8 Apr 2024 Marketing, Promotion and Engagement updateThat the update on the marketing, promotion and engagement, be received. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies