i) That the progress being made against the 2022/2023 Annual Governance Statement Action Plan, be acknowledged. ii) That the Chief Executive be requested to review the format of the action plan to ensure that it was clearer to Members whether actions were, or were not, on target as well as include specific actions. iii) That the Chief Executive be requested to provide a written answer to Members of the Committee in regard to Freedom of Information requests and how the Council’s performance compared to that of other local authorities. EY
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
This report considers the progress being made against the action plan and milestones identified in the Annual Governance Statement for 2022/2023 to ensure that effective systems of internal control are maintained as a critical part of the Council’s Corporate Governance arrangements.
Recommendation
That the Committee is invited to consider, seek clarification and, if satisfied, acknowledge the progress being made against the 2022/2023 Annual Governance Statement Action Plan.
Reasons for recommendation
To enable the Committee to review progress against the key actions identified in the Annual Governance Statement and the sources of assurance to support the statement. To maintain and reinforce the Council’s adherence to strong corporate governance.
4. THE CURRENT POSITION
The Annual Governance Statement for 2022/23 was presented to the June 2023 committee, and a progress report is now due. An updated action plan is detailed at Appendix A.
Audit Committee – 12 March 2024 Annual Governance Statement 2022/23 Action Plan follow-up 13(1) 5. DETAILS
5.1The Council is responsible for ensuring that its business is conducted in accordance with the law and proper standards, and that public money is safeguarded and properly accounted for and used economically, efficiently and effectively. The established corporate governance arrangements are critical and provide the systems and processes for the direction and control of the organisation and its activities through which it accounts to, engages with and leads the community.
5.2The system of internal control is a significant part of the corporate governance framework and is designed to manage risk to a reasonable level. It is based on an ongoing process designed to identify and prioritise the risks to the achievement of the Council’s policies, aims and objectives, to evaluate the likelihood of those risks being realised and the impact should they be realised and to manage them efficiently, effectively and economically.
5.3The Council has responsibility for conducting, at least annually, a review of the effectiveness of the governance framework including the system of internal control. The annual review is informed by the work of senior officers responsible for the development and maintenance of governance arrangements (Corporate Governance Working Group), the Annual Internal Audit report and assessments made by external audit and other review agencies and inspectorates.
5.4The draft Annual Governance Statement for 2022/2023, including the position on Corporate Governance arrangements as at 31 March 2023, was reported to the Audit Committee at its meeting on 28 June 2023. The report outlined the outcome of the review of the effectiveness of the Council’s Corporate Governance framework, and its system of internal control with the sources of assurance included within the Statement.
5.5It should be noted that the final Annual Governance Statement for 2022/2023 not yet been approved and published within the Council’s accounting statements for 2022/2023, as the external audit has not been concluded. The draft AGS has been published alongside the unaudited financial statement for 2022/2023, on the Council’s website.
5.7This report, therefore, seeks to provide an update on the progress made since the 2022/2023 AGS was presented to the committee in June 2023. The progress made to date is reported at Appendix A and the Committee is invited to consider the progress made against the key actions and milestones.
6. ALTERNATIVES CONSIDERED AND REJECTED
6.1This section is not applicable.
Audit Committee – 12 March 2024 Annual Governance Statement 2022/23 Action Plan follow-up 13(2) 7. KEY IMPLICATIONS
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Internal Audit Plan Update 2026/27RESOLVED That the Committee considered the report and was satisfied to acknowledge the progress made to date against ...
Report on Fraud and Corruption 2025/26RESOLVED That the Committee considered the report, sought clarification, and noted, (a) The Council’s performance in ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.