(1) That the introduction of the new statutory pavement licencing regime be noted. (2) That it be agreed that the fees should be set at the maximum permitted level of £500 for first time applications and £350 for renewal applications and it be noted that the fees will be reviewed from time to time to ensure that the income received matches the costs incurred. (3) That the duration of the Licences will be two years, unless revoked.
Word for word from the decision Bedford published for this meeting.Source: councillorsupport.bedford.gov.uk
1.1On 31 March 2024, the Department for Levelling-Up, Housing & Communities commenced the pavement licensing provisions laid out in the Levelling Up and Regeneration Act 2023. The provisions introduce a permanent pavement licensing regime in England to replace the temporary provisions introduced by the Business and Planning Act 2020. This permanent regime retains the key features of the 2020 regime, intended to streamline processing and reduce costs, but also incorporates some changes, to ensure the long-term sustainability of the model.
There are several new pavement licensing provisions within the Levelling Up and Regeneration Act 2023 (LURA);
The fee cap for pavement licensing is increasing. The licence can now be granted for a maximum for two years. The 7 day consultation and determination period has been extended to 14 days for each. New enforcement powers
Permanent Pavement Licencing Regime General Licensing Committee – 25 April 2024 8(1) December 2023 2. RECOMMENDATION(S) 2.1 The Committee is requested to;
i. Note the introduction of the new statutory pavement licencing regime;
ii. Agree that the fees should be set at the maximum permitted level of £500 for first time applications and £350 for renewal applications and to note that the fees will be reviewed from time to time to ensure that the income received matches the costs incurred;
iii. Agree that the duration of the Licences will be two years, unless revoked.
3. REASONS FOR RECOMMENDATION i. To ensure that the Committee is aware of the change in legislation;
ii. To ensure that the cost of administering the licence applications is met from the income generated by fees charged;
iii. To minimise the administration and cost to both applicants and the Council within the scope of the legislation.
4. THE CURRENT POSITION 4.1 There have been temporary legislative provisions for a pavement licensing regime in England that were introduced by the Business and Planning Act 2020. At the present time there are five establishments in the Borough that have pavement licences under the previous arrangements, with one further application pending.
4.2The new statutory regime is not adoptive, local authorities are obliged to implement the scheme, although there are various discretionary aspects, including setting fees (up to a statutory cap) and setting the duration of the licence, up to a maximum of two years. The new cap on fees allows local authorities to recover the costs of processing, monitoring and enforcing licences.
4.3The previous cap did not cover the cost of processing the licences and the scheme was initially set up to support the economy to recover from the disruption caused by the COVID 19 outbreak in the UK.
Permanent Pavement Licencing Regime General Licensing Committee – 25 April 2024 8(2) December 2023 5. DETAILS 5.1 The fee cap for a pavement licence application is increasing. It will no longer be capped at £100 but instead be capped at £500 for first time applications and £350 for renewal applications, subject to each local authority deciding the level of fee up to the cap. The increase and fee cap intend to balance both local authority and business interests. This increase in fee cap is intended to allow local authorities to recover the costs of processing, monitoring and enforcing licences.
5.2Under this permanent regime, local authorities will now also be able to grant pavement licences for a length of their choosing up to a maximum of two years. As set out in the updated guidance, local authorities are encouraged to grant businesses the maximum two years unless there is a good reason to do otherwise. This will reduce the administration required by both the Council and applicants.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Review of Vehicle Testing ProcessAuthorised the Interim Strategic Director for Environment, or in their absence the Head of Regulation & Community Pro...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.