Bedford Borough Council

Wixam Train Station

Agreed Scrutiny 1 paper

AI summaryBedford councillors told Wixams station project terminated and handed back to Urban and Civic, with Network Rail set to deliver a larger four platform station. Forecast final cost is £32.1m.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreed
Money£32.1mForecast overall final project cost, total spend since 2018
What happens nextLand transfer in around 4 weeksHeads of Terms being agreed with Urban and Civic
Who it affectsFuture rail passengers and the Council

What was decided

The committee received an update confirming that the site would be transferred back to Urban and Civic, with the construction licence ending on transfer of the land.

Members noted that Network Rail has been mandated by the Department for Transport to design and deliver a larger Wixams station, with the Council remaining a key stakeholder.

The committee noted the projected final cost of £32.1m, with the Council continuing to scrutinise claims from Network Rail, and that the Council is not incurring new costs on the project.

Why

Construction of the original two platform station began on site in September 2024, but the government's 9 April 2025 announcement of a Universal theme park nearby prompted a rethink of the project. Report 1.1, 1.2

The Department for Culture, Media and Sport wrote to the Council on 11 April 2025 recommending it negotiate with Network Rail to cease the project, while leaving the decision with the Council. Report 1.3

An executive decision on 25 July 2025 approved formal termination of the Implementation Agreement with Network Rail, with notice served on 5 August 2025 and site works concluded in November 2025. Report P5, P6, 1.6, 1.7

What happens next

The Council is in ongoing discussions with Urban and Civic to agree Heads of Terms for transfer of the land, which is anticipated to occur in the next four weeks. Report 1.8

Final accounts from Network Rail's suppliers are not expected for up to 12 months, and Grant Thornton is advising on asset classification to mitigate the risk that current expenditure is treated as revenue. Report 1.10, P12

Once the land is transferred, Network Rail will be under a licence to construct the larger station, with the Council owning and operating the car park and access road. Report 1.7

The money

  • £32.1m Forecast overall anticipated final project cost, total spend on the project since 2018, described as a forecasted worst case scenario Report 1.9

Implications

  • Financial: The Council is not incurring any new costs on the project but there are residual costs from works already completed, and no reimbursement of previous costs is expected. Report 1.7
  • Financial: Specialist accountancy advice from Grant Thornton on capitalisation of assets is progressing but a risk remains until the review is completed. Report P12
  • Risk: Final projected costs will not be known for up to 12 months because the contract is based on an emerging cost basis and there are lags in information from Network Rail. Report 1.10
  • Staffing: There will be some continuity with the same team members on the new larger station project.
  • Other: The site is currently boarded and gated with security locks, ready to be handed back, and hoardings remain pending commencement of the larger station. Report 1.7

Who and where

  • Future rail passengers, who will be served by a larger four platform Wixams station designed and delivered by Network Rail Report 1.7
  • Bedford Borough Council, which remains a key stakeholder, will own the access road and will own and operate the car park for the new station
  • Urban and Civic, as landowner of the station land and party to ongoing Heads of Terms discussions with the Council Report 1.8
  • Network Rail, mandated by the Department for Transport to deliver the larger station and to finalise supplier accounts Report 1.7, 1.9

Timeline

  • September 2024: Construction works for Wixams Station commenced on site Report 1.1
  • 9 April 2025: Government announced Universal Destinations & Experiences theme park and resort near Bedford Report 1.2
  • 11 April 2025: DCMS letter received by the Council's Chief Executive recommending negotiation to cease the station project Report 1.3
  • 25 July 2025: Executive decision 1813 approved formal termination of the Implementation Agreement with Network Rail Report P5, P6
  • 5 August 2025: Formal notice of termination served to Network Rail Report 1.6
  • 25 November 2025: Site visit with Network Rail, Urban and Civic, Council officers and consultants to inspect and agree transfer of completed assets Report 1.7
  • 15 January 2026: Environment and Sustainable Communities Overview and Scrutiny Committee received update
  • Next 4 weeks: Anticipated transfer of the station land from Urban and Civic to the Council and termination of the construction licence Report 1.8
  • Up to 12 months from now: Final projected costs expected once Network Rail completes final accounts with suppliers Report 1.10

Plain English for the jargon

  • Implementation Agreement: The contract between the Council and Network Rail for the original two platform station, which has been terminated
  • DCMS: Department for Culture, Media and Sport, which wrote to the Council about the Universal project
  • NR: Network Rail, now mandated by the Department for Transport to design and deliver the larger four platform station
  • DfT: Department for Transport, which has mandated Network Rail to build the larger station
  • HCPI&ST: Head of Capital Projects, Infrastructure and Sustainable Travel, the Council officer who answered questions at the meeting
  • Heads of Terms: The agreement being negotiated with Urban and Civic for transfer of the station land to the Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item58

Resolved

It was agreed that the site would be transferred back to Urban and Civic. · Network Rail have been mandated by the Department for Transport to design and deliver a larger Wixam station, with the Council remaining as a key stakeholder. · Discussions were ongoing with Urban and Civic regarding the land transfer, with the license being terminated on transfer of the land. It was anticipated that this should occur in the next 4 weeks. · The projected final costs for the project were £32.1M, with the Council continuing to scrutinise any claims from Network Rail. · Specialist advise was sought from Grant Thornton on the classification of this asset and risk mitigate. · The site was currently mothballed. In response to questions the HCPI&ST confirmed that: · The Council were not incurring any new costs on this project. There would still be some residual costs from works that had been completed. · The £32M was the total spend on the project since 2018, this was a forecasted worst-case scenario. · The remaining costs for the station sit with the Department for Transport. · A transport board for the project has been set up by the Department for Transport, the HCPI&ST attended these meetings. · The site was boarded and gated with security locks, ready to be handed back. · There would not be any reimbursement of previous costs. · The station would be bigger, the Council owned the access road and would own and operate the car park. · The rail quarterland sat on the boundary of Urban and Civic’s land. · There would be some consistency with the new project with the same team members. · Once the land was transferred, Network Rail would be under a licence to construct the station. · An experienced cost consultant had challenged and scrutinised the costs and would continue to check and verify any new receipts. · There was still an element of contingency included within the £32M. · The project was paused after the announcement in April and was terminated by the Executive decision in July. The formal termination would ensure that any risks were mitigated. · Legal advice was sought before making the decision to terminate. · The final cost report was not yet available. · The Council worked closely with Network Rail ... view the full minutes text for item 58. SDPRH&WM
Word for word from the decision Bedford published for this meeting. Source: councillorsupport.bedford.gov.uk

Follow this further

Built from Bedford's papers

What the report saysPro

Report to Environment and Sustainable Communities Overview and Scrutiny Committee

Summary

1.1Construction works for Wixams Station commenced on site in September 2024.

1.2Government announced, on 9 April 2025, that Universal Destinations & Experiences would proceed bringing a world-class theme park and resort to the former brickworks site just south of Bedford.

1.3A letter was received by the Council’s Chief Executive from the Department of Culture, Media and Sport (DCMS), on 11 April 2025, formally notifying Bedford Borough of the Universal project. The letter recommended that the Borough negotiate with Network Rail to cease the Council’s project at this time but also advised that any decision to pause or cancel the 2-platform project remained with the Council and warned that the letter did not form the basis of any guarantee against future costs if the Universal project did not proceed.

1.4Bedford Borough Council Officers subsequently entered into negotiation with Network Rail to terminate the Implementation Agreement contract working closely with Network Rail to complete work to bring the site to a safe operable state, complete and close out obligations of Network Rail sub-contracts and fulfil contractual obligations under the construction licence.

7(1) (Wixams Station / Environment Overview and Scrutiny / 15th January 2026) 1.5 An executive decision 1813 was confirmed on 25th July 2025 to:

• Approve serving Network Rail with a formal notice of termination of the Implementation Agreement. • Recommend a revision to the capital programme be submitted to Full Council for approval.

1.6BBC served notice of formal termination to NR on 5th August 2025 to ensure that matters were brought to a swift conclusion in line with the IA.

1.7Site works concluded in November 2025, culminating in a site visit with Network Rail, Urban and Civic, Bedford Borough Officers and consultants on 25th November 2025 to inspect and agree the formal transfer of all completed assets, and that all works necessary to conclude obligations under the licence had been satisfactorily completed. The site has now been vacated, though hoardings remain in place pending commencement of the larger 4-platform Wixams Station with completion of the car park, access road and public realm. Network Rail has been mandated by the Department for Transport to design and deliver the larger Wixams Station.

1.8The station land is owned by Urban and Civic, so access for construction works has been facilitated via a construction licence. Discussions are ongoing with Urban and Civic to agree Heads of Terms for transfer of the land to Bedford Borough Council which are progressing well. The licence will be terminated immediately on transfer of the land.

1.9Network Rail continues to provide updated forecast resource plans and financial forecasts. The Council’s appointed cost consultant continues to closely scrutinise and audit the payment applications from Network Rail along with the supporting financial information. The forecast overall anticipated final project cost is currently £32.1m, though until the NR commences final accounts with their suppliers, this will be subject to some assumptions. Project costs have reduced in the last month where Network Rail has reduced accruals for possession costs. BBC has challenged possessions costs, undertaken repeated sample audits with Network Rail and their supply chains and continues to meet NR’s commercial manager on a weekly basis with monthly forecast updates provided by NR.

1.10The contract is based on an emerging cost basis so it should be noted that there are lags in the timely provision of information from Network Rail, so the final projected costs will not be known for up to 12 months from now.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wixam Train StationReport 91 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
FZ
Councillor Fouzia Zamir AtiqChair, present
CR
Councillor Charles RoydenVice-Chair, present
JA
Councillor Jonathan AbbottCommittee Member, present
CA
Councillor Colleen AtkinsCommittee Member, apologies, sent representative
JG
Councillor Jon GamboldCommittee Member, apologies
DS
Councillor Dylan SimmonsCommittee Member, apologies, sent representative
SS
Councillor Sharan SiraCommittee Member, present
AS
Councillor Abu SultanCommittee Member, present
GC
Councillor Graeme CoombesCommittee Member, present

More from Bedford Environment and Sustainable Communities Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
16 Jul 2026 Previous MinutesRESOLVED That the Minutes of the meeting of the Committee held on the 18 June 2026 be confirmed. Chair Decided Open
16 Jul 2026 Local Plan 2050RESOLVED That the Committee noted the update. HCPI&ST Noted Open
16 Jul 2026 Executive DecisionsRESOLVED 1. The Committee noted that there were no meetings of Executive prior to the publication of the agenda, deci... Noted Open
16 Jul 2026 Notice of Forthcoming Decisions to be taken by the ExecutiveThat the Notice of Forthcoming Decisions for the period 1 August 2026 to 30 November 2026 be received. SDSO Decided Open
16 Jul 2026 Committee Work ProgrammeThat an item on Biddenham (Great Ouse Way) Country Park be added to the Committee’s Work Programme. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies