Pre April-2015 Parks and Leisure Committee agreed this item on Thursday 9 June 2011. Below is the council's own wording, with the papers it was decided on.
It was agreed that final recommendations be made to the June meeting of the committee. 2 Key Issues Prioritisation – pitches Thirty-one council owned sites were considered for potential investment for new pitch provision. These were assessed using the revised prioritisation matrix also taking into account ... view the full minutes text for item 5.
Word for word from the decision Belfast published for this meeting.Source: minutes.belfastcity.gov.uk
Report to Pre April-2015 Parks and Leisure Committee
Appendix 1 Action Plans for the delivery of Playing Pitches Strategy Objectives
Objective 1 - Capital investment Actions Timescales
To invest in additional outdoor leisure facilities, Currently being delivered as part of the prioritisation Phase 1 will be addressing the shortfall in city supply and intensifying process delivered over the use period 2011-14
To invest in enhancing existing provision to intensify Currently being delivered as part of the prioritisation Phase 1 will be use and improve the quality of outdoor leisure process delivered over the provision period 2011-14
To invest in the quality of changing facilities at outdoor Currently being delivered as part of the prioritisation Phase 1 will be leisure provision, increasing provision for women and process delivered over the children period 2011-14
To begin discussions with Sport NI to develop Initial discussions have begun and a meeting will be Process has partnership arrangements for assets planning, organised with Sport NI to bring this forward commenced and management and secured community access ongoing
To work with education partners (schools, higher and Initial discussions have taken place with representatives Process has further education) to deliver increased access to their with BELB and CCMS re wider community use of commenced and outdoor leisure facilities, through secured community educational facilities. Further work is being under around ongoing access agreements and investment in ancillary this and reports will go to COMT and Committee in the facilities such as floodlighting coming months
To work with sports governing bodies, partners and Discussions are currently taking place with Process has other interested parties including sports clubs and the representatives from a range of sports governing bodies commenced and private sector to explore potential partnerships and to and other partners. Work is also ongoing through the ongoing deliver increased access to outdoor leisure facilities activities of the Leisure Development Unit Objective 1 - Capital investment Actions Timescales
To promote opportunities for shared space through Currently being delivered as part of the prioritisation Phase 1 will be multi-sport facilities process delivered over the period 2011-14 To create a repairs and renewals fund for the Process to be developed and implemented by To be established by refurbishment of playing pitches and a rolling departmental business support and parks operation staff March 2012 maintenance programme based on regular conditions surveys
To begin discussions with the Planning Service for Initial discussions have begun and a further meeting will Process has Northern Ireland be set up to bring this forward commenced and ongoing Objective 2 – Management Actions Timescales
To complete the review of existing Facility A review of FMAs has commenced and a report will be To be completed by Management Agreements (FMAs) brought to Committee in late 2011 March 2012
To develop a monitoring and evaluation framework for A framework will be developed by the Outdoor Leisure To be completed by all pitches which includes regular consultation with Unit in conjunction with the Policy and Business March 2012 pitch users to establish trend data in relation to Development Unit satisfaction, quality rating and common pitch issues To undertake a review of the current fees and charges A review will be undertaken by departmental business To be completed by support March 2012 To roll out a programme of ‘shared space’ training to A programme of training to be developed and delivered To be developed by all sports clubs across Belfast, firstly targeting clubs March 2012 with using our pitches and obtaining funding from us delivery thereafter
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Pre April-2015 Parks and Leisure Committee at Belfast and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.