CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Belfast City Council
Pre April-2015 Town Planning Committee, Thursday 7 February 2013 at 4.30pm

Major Planning Application under Article 31: Windsor Park

Agreed Planning 2 papers

Pre April-2015 Town Planning Committee agreed this item on Thursday 7 February 2013. Below is the council's own wording, with the papers it was decided on.

Item51

Resolved

Decision Notice. 3 Recommendation It is recommended that the Committee agrees that the Department of the Environment is requested to make every effort to expedite the application as a matter of urgency and to avoid any unnecessary delays.” After discussion, it was Resolved - That the Committee recognises the benefits which the proposed development at Windsor Park would ... view the full minutes text for item 51.
Word for word from the decision Belfast published for this meeting. Source: minutes.belfastcity.gov.uk

Follow this further

Built from Belfast's papers

What the report saysPro

Report to Pre April-2015 Town Planning Committee

Belfast City Council

Report to: Town Planning Committee Subject: Windsor Park – Major Planning Application Date: 7 February 2013 Reporting Officer: Andrew Hassard, Director of Parks and Leisure Contact Officer Caroline Wilson, Programme Manager

1.0Relevant Background Information 1.1 The Council has received correspondence from the Department of the Environment, advising of a major planning application under Article 31 for the re-development of Windsor Park. This is to provide an 18,000 seated national football stadium.

2.0Key Issues 2.1 The new stadium at Windsor represents a significant investment by the Department of Culture Arts and Leisure and the Irish Football Association. This contribution is recognised in the Council’s Investment Programme, and most significantly in relation to the transformation of the leisure estate. The physical improvement of the leisure estate is dependent on the Council’s agreed medium term financial strategy, and maximising value for money through strategic opportunities such as the Windsor and Casement developments. Both the Windsor and Casement stadia are on an aggressive timeline for delivery. Members have stressed the urgency of decisions in relation to these iconic investments, in order to realise the greatest potential socio-economic benefits and work towards an enhanced community provision. 2.2 Council officers from Environmental Health Services have worked closely with the applicant over the last 9 months, as part of a pre-application process, to resolve any issues prior to the application being submitted. A standard technical response in relation to environmental impacts is now being prepared by officers for submission to the Planning Service. The response will indicate that Council officers have considered all potential impacts and identified no issues in relation to the application and will be recommending to the Planning Service that the application is granted, subject to a number of conditions. 2.3 The major application is complementary to both the aims of the Council’s Investment Programme, as well as the principles underpinning the leisure estate transformation recently

1 agreed by SP&R Committee at its meeting (25 January 2013). The Council is committed to working with both stadia developers, in order to provide direct benefit to the city and its ratepayers in terms of the promotion of the city, as well as social and economic regeneration benefits. As part of the leisure transformation plan, Members have stressed the need to maximise the opportunities for partnership investments, and the emerging physical transformation plan includes the stadia developments as part of Phase 1, agreed by SP&R Committee. 2.4 It is therefore recommended that the Committee urges the Planning Service and the Department of the Environment to make all possible efforts to avoid potential and unnecessary delays and to make every effort to expedite the matter by avoiding the need for the holding of a public enquiry and to determine the application by way of issuing a Decision Notice.

3.0Recommendation It is recommended that the Committee agrees that the Department of the Environment is requested to make every effort to expedite the application as a matter of urgency and to avoid any unnecessary delays.

4.0Appendix Correspondence from the Department of the Environment to the Chief Executive – 21 December 2012

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Major Planning Application: Windsor ParkAppendix 1 1.2 MB Download
PDF
Major Planning Application under Article 31: Windsor ParkMinutes 79 KB DownloadRead as text

More from Belfast Pre April-2015 Town Planning Committee

All decisions
MeetingDecisionOutcome
9 Oct 2014 Chairing of MeetingResolved – That Alderman Rodgers take the Chair. (Alderman Rodgers in the Chair.) Decided Open
21 Mar 2013 Reconsidered Item- Application RejectedResolved – That the Committee agrees to reject the application on the grounds that such a development would be out of... Agreed Open
7 Feb 2013 Deputation from residents of the Malone Road area in relation to the Lennoxvale applicationResolved – That the Committee notes the concerns of the residents in respect of the proposals which have been submitt... Agreed Open
16 Feb 2012 327-329 Upper Newtownards Road and 1 Knockhill ParkResolved – That the opinion of the Divisional Planning Manager to approve the applications in respect of the erection... Approved Open
16 Feb 2012 Vacant Land adjacent to 42 Belmont Church RoadResolved – That the decision of the Divisional Planning Manager to refuse the application for the erection of a two-s... Refused Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies