Flood Alleviation in Belfast

Agreed Committee 2 papers

Pre April-2015 Strategic Policy and Resources Committee agreed this item on Friday 23 January 2015. Below is the council's own wording, with the papers it was decided on.

Item15a

Resolved

It was agreed that this work would be undertaken by the Council in conjunction with the three main drainage agencies; DRD Roads Service (now Transport NI), Northern Ireland Water and DARD Rivers Agency. 1.2 There has been considerable progress in addressing flood alleviation in the city since June 2012 and the purpose of this report to Committee is to highlight some of the main improvements (including those which are planned but not yet completed) and the outstanding issues mentioned in the research report, including the lack of progress in establishing a scheme for individual property protection. 1.3 Members will recall that Rivers Agency drafted a business case for such a scheme almost a year ago and the Chair of this Committee wrote to both DARD and DFP in February 2014 seeking clarification on the proposals, finance, timeframes and administrative arrangements for the scheme and welcoming early discussions on the implications of the proposed scheme for councils. The scheme is still under consideration by the Department of Finance and Personnel. 2 Key Issues 2.1 Flood Alleviation Measures The number of government departments and agencies with responsibilities for flood alleviation makes it difficult to establish a single process that covers all the issues involved in improving the flood resilience of the city. However since the URS Report and a number of other reports published following the June 2012 flooding there has been considerable investment and much work done to alleviate flooding in Belfast. For example, phase one of the Connswater Community Greenway project and the flood defences at Victoria Park have been completed. This ensured that the Orangefield and Sandhill areas did not flood during recent flooding events. Phase two of the project is underway and will provide additional protection around the other culverts feeding into the Connswater and Loop rivers. A number of other significant schemes for Finaghy , Greystown and the Upper Malone area have also been launched and are due to commence next spring. These schemes will use a number of the mechanisms suggested in the report to deliver integrated solutions to flooding. 2.2 Coastal flood plans are well progressed and NIE, BT and NIW have taken action to protect their infrastructure in flood risk areas. In particular there has been considerable work to improve the resilience of the NIW pumping station at Sydenham. There is also a proposal to upgrade this pumping station to increase its capacity; and a further proposal to rebuild it in a new ... view the full minutes text for item 15a
Word for word from the decision Belfast published for this meeting. Source: minutes.belfastcity.gov.uk

Follow this further

Built from Belfast's papers

What the report saysPro

Report to Pre April-2015 Strategic Policy and Resources Committee

Belfast Flood Alleviation Improvement Works Significant Issues Report

May 2014

Prepared for:

Belfast City Council

UNITED KINGDOM & IRELAND Belfast City Council – Belfast Flood Alleviation Improvement Works

Rev Date Details Prepared by Checked by Approved by

Strategic Report into Flooding Claire McCann John Armstrong David McKillen 1 6 Dec 2013 in Belfast Civil Engineer Associate Technical Director

nd Claire McCann John Armstrong David McKillen 2 31 Jan 2014 2 Draft Civil Engineer Associate Technical Director

rd Claire McCann John Armstrong David McKillen 3 4 April 2014 3 Draft Civil Engineer Associate Technical Director

17 April th Claire McCann John Armstrong David McKillen 4 4 Draft 2014 Civil Engineer Associate Technical Director

Claire McCann John Armstrong David McKillen 5 20 May 2014 Final Report Civil Engineer Associate Technical Director

Beechill House Beechill Road Belfast BT8 7RP

Telephone: +44(0)28 9070 5111 Fax: +44(0)28 9079 5651

SIGNIFICANT ISSUES REPORT, 47069440 May 2014 i Belfast City Council – Belfast Flood Alleviation Improvement Works

Limitations

URS Infrastructure & Environment UK Limited (“URS”) has prepared this Report for the sole use of Belfast City Council (“Client”) in accordance with the Agreement under which our services were performed [47069440]. No other warranty, expressed or implied, is made as to the professional advice included in this Report or any other services provided by URS.

The conclusions and recommendations contained in this Report are based upon information provided by others and upon the assumption that all relevant information has been provided by those parties from whom it has been requested and that such information is accurate. Information obtained by URS has not been independently verified by URS, unless otherwise stated in the Report.

The methodology adopted and the sources of information used by URS in providing its services are outlined in this Report. The work described in this Report was undertaken between July and December 2013 and is based on the conditions encountered and the information available during the said period of time. The scope of this Report and the services are accordingly factually limited by these circumstances.

Where assessments of works or costs identified in this Report are made, such assessments are based upon the information available at the time and where appropriate are subject to further investigations or information which may become available.

URS disclaim any undertaking or obligation to advise any person of any change in any matter affecting the Report, which may come or be brought to URS’ attention after the date of the Report.

Certain statements made in the Report that are not historical facts may constitute estimates, projections or other forward- looking statements and even though they are based on reasonable assumptions as of the date of the Report, such forward-looking statements by their nature involve risks and uncertainties that could cause actual results to differ materially from the results predicted. URS specifically does not guarantee or warrant any estimate or projections contained in this Report.

Unless otherwise stated in this Report, the assessments made assume that the sites and facilities will continue to be used for their current purpose without significant changes.

Copyright

© This Report is the copyright of URS Infrastructure & Environment UK Limited. Any unauthorised reproduction or usage by any person other than the addressee is strictly prohibited.

SIGNIFICANT ISSUES REPORT, 47069440 May 2014 ii Belfast City Council – Belfast Flood Alleviation Improvement Works

TABLE OF CONTENTS NON-TECHNICAL SUMMARY.............................................................. I

1. INTRODUCTION................................................................ 1

2. BACKGROUND TO FLOODING IN BELFAST .................. 2

2.1Sources of Available Information ....................................... 5

3. DATA COLLECTION PROCESS ....................................... 6

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Alleviation Significant IssuesMinutes 4.7 MB DownloadRead as text
PDF
Flood Alleviation in BelfastMinutes 84 KB Download

More from Belfast Pre April-2015 Strategic Policy and Resources Committee

All decisions
MeetingDecisionOutcome
19 Sep 2014 Request to Participate in Cinemagic InitiativeResolved – That the Committee agrees to approve expenditure of £6,500 for the aforementioned event under Section 37 o... Agreed Open
22 Aug 2014 Working GroupsIt was agreed also to review the number and role of the existing working groups to take account of the dual governanc... Agreed Open
22 Aug 2014 NI Street League FundingResolved - That the Committee agrees that expenditure of £4,400 in respect of the aforementioned event be approved un... Agreed Open
19 Jun 2014 Request for Funding – Common Purpose BelfastResolved – That expenditure in the sum of £6,000 be approved for the aforementioned Programme under Section 37 of the... Approved Open
19 Jun 2014 City Hall Car ParkingIt was agreed also that a wider, corporate review of car parking be undertaken and a report thereon be submitted to t... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies