Resolved – That the decision of the of 29th January, under the heading ‘Local Government Reform – Cemetery Charges’, be amended to provide that a request be made to Lisburn and Castlereagh City Council to meet with an all-party deputation to discuss the Council’s concerns in respect of the proposed increase in burial charges at the Blaris Cemetery for former residents of Lisburn City Council who would be transferring to Belfast. Subject to the foregoing amendment, the minutes of the meetings of 9th and 29th January were approved and adopted.
Word for word from the decision Belfast published for this meeting.Source: minutes.belfastcity.gov.uk
Members present: Councillor Jones (Chairman); Councillors Carroll, Clarke, Corr Johnston, Craig, Dudgeon, Garrett, Graham, Hussey, Magennis and McDonough-Brown.
Also attended: Councillors Bradshaw, Convery, Rodgers and Spence.
In attendance: [name removed], Director of Property and Projects; [name removed], Project Sponsor; and [name removed], Democratic Services Officer.
Declarations of Interest
No declarations of interest were reported.
Belfast ‘Streets Ahead’ Project - Phase 3
The Committee was reminded that, at its meeting on 9th December, it had endorsed a draft response to the Department for Social Development's (DSD) consultation exercise on Phase 3 of the Belfast ‘Streets Ahead’ Project. In addition, the Committee had agreed to invite representatives of the DSD to attend a special meeting to outline in detail the proposals for that project. The Director of Property and Projects outlined the principal aspects of a revised corporate response to the consultation, which had been amended to reflect the comments which had been made at the Committee’s meeting in December. He then answered a range of Members’ questions.
The Chairman, on behalf of the Committee, welcomed to the meeting [name removed] and [name removed], representing the Department for Social Development, together with [name removed] from McAdam Design and [name removed] from Open Consultants. [name removed] provided a presentation which outlined in detail the plans which had been formulated for the project. In response to a query from the Chairman, he indicated that it was anticipated that work on the project would commence during 2016, with a view to it being completed by 2018.
The following comments and suggestions were made by Members in respect of the plans which had been presented:
• that consideration be given to enhancing the linkages between the York Street railway station and the Ulster University, specifically by addressing the needs of walkers and cyclists through the provision of adequate lighting and safety measures;
• that the type of materials to be used in the development, particularly with regard to the paving stones, should be easy to clean and maintain; and
• that the type of trees which would be used as part of the development would be in keeping with the local environment and aesthetics and that further consideration be given to their longer- term maintenance and upkeep.
In addition, in response to Members’ questions, the representatives of the DSD indicated:
• that public transport disruption would be kept to a minimum during the project and that a traffic management plan had been formulated to oversee any issues which might arise as a result of the work;
• that a range of social clauses had been included within the contract which would oblige the contractor to provide opportunities for the long-term unemployed, together with a requirement for the creation of a number of student placements;
• that consideration might be given at a later date to erecting tourist information boards within the area which would promote and celebrate local history and culture; and
• that the proposed statue to be erected by the Council to the late boxer John ‘Rinty’ Monaghan within the Council-owned Cathedral Gardens, known also as the Buoys’ Park, would not be impacted upon by the development and the Council’s prior consent would be sought should any work be necessary within the immediate vicinity of the statue.
The Committee endorsed the following response to the consultation, subject to it being amended to request that the DSD would agree to consult further with the Council regarding the type of trees to be used in the development:
“RESPONSE TO DSD PUBLIC CONSULTATION Streets Ahead Phase 3 Proposals
General Comments
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.