Girdwood Hub - Update Report

Agreed Committee 1 paper

Strategic Policy and Resources Committee agreed this item on Friday 18 September 2015. Below is the council's own wording, with the papers it was decided on.

Item5c

Resolved

It was agreed last month that a detailed report on the progress of the Hub project would be brought back to Committee. This report outlines: · The current status of the Hub construction and wider development of the site · Proposals for the official opening · An update on future management arrangements · Programming of the Hub building 2.0 Recommendations Members are asked to note- · Current progress with regard to completion of Girdwood Community Hub · Current progress and developments with regard to the wider site, in particular the Indoor Sports Facility and Mixed Use Business Units · Current progress with programming for Girdwood Community Hub and pitch Members are asked to agree:- · to a site visit on Friday 25th September departing City Hall at 11am · that the official opening of Girdwood Community Hub and pitch takes place on Friday 15 January 2016 commencing at 12 noon and that a week long programme of events take place following the official opening. A letter of invitation to be issued to the Minister of Social Development and SEUPB’s representative. 3.0 Main report Key Issues 3.1 Members will recall that the Girdwood site had been a disputed space for many years and it was the political leadership shown by Belfast City Council through the Peace III intervention that has enabled movement on the site. Further political leadership was shown by the North Belfast MP/MLA group, including the former DSD Minister, in agreeing a Masterplan for the wider site which was required in order to secure the funding under Peace III. In 2014 the Council secured funding of £11.7m from Special EU Programmes Body (SEUPB) under Peace III for the construction of the Girdwood Hub and associated environmental works. Since this time the Council, together with the Department for Social Development (DSD), have been working closely to ensure the successful development of Girdwood Park. The construction of Girdwood Community Hub acted as the catalyst for the development of the remainder of the site. Girdwood Community Hub and Wider Site Development A number of construction projects are currently underway on the Girdwood Park site – 3.2 · Girdwood Hub – lead by Belfast City Council. Contractual completion of the Hub building is programmed for 30 September 2015 with a 6 week programme of commissioning and handover in advance of a soft opening late November/early December 2015 dependent upon systems testing. The Hub will include: · State or the art gym · Large multi-use hall · Multi-purpose rooms which can be used for community events and activities · Dedicated shared youth space · An outdoor piazza with seating · Classrooms for courses with Belfast Metropolitan College - BMC will be anchor tenants at the Girdwood Community Hub for an initial period of 5 ... view the full minutes text for item 5c
Word for word from the decision Belfast published for this meeting. Source: minutes.belfastcity.gov.uk

Follow this further

Built from Belfast's papers

What the report saysPro

Report to Strategic Policy and Resources Committee

STRATEGIC POLICY & RESOURCES COMMITTEE

Subject: Girdwood – Update Report

Date: 18 September 2015

Reporting Officer: Gerry Millar, Director of Property and Projects

Contact Officer: Kirsten Mullen, Project Sponsor

x Is this report restricted? Yes No x Is the decision eligible for Call-in? Yes No

1.0Purpose of Report or Summary of main Issues Members will be aware through regular updates on Council’s Capital Programme that the construction of Girdwood Community Hub is well underway with contractual construction completion scheduled for 30 September 2015. It was agreed last month that a detailed report on the progress of the Hub project would be brought back to Committee. This report outlines:

 The current status of the Hub construction and wider development of the site

 Proposals for the official opening

 An update on future management arrangements

 Programming of the Hub building

2.0Recommendations Members are asked to note-

 Current progress with regard to completion of Girdwood Community Hub

 Current progress and developments with regard to the wider site, in particular the Indoor Sports Facility and Mixed Use Business Units

 Current progress with programming for Girdwood Community Hub and pitch Members are asked to agree:-

 to a site visit on Friday 25th September departing City Hall at 11am  that the official opening of Girdwood Community Hub and pitch takes place on Friday 15 January 2016 commencing at 12 noon and that a week long programme of events take place following the official opening. A letter of invitation to be issued to the Minister of Social Development and SEUPB’s representative.

3.0Main report Key Issues 3.1 Members will recall that the Girdwood site had been a disputed space for many years and it was the political leadership shown by Belfast City Council through the Peace III intervention that has enabled movement on the site. Further political leadership was shown by the North Belfast MP/MLA group, including the former DSD Minister, in agreeing a Masterplan for the wider site which was required in order to secure the funding under Peace III. In 2014 the Council secured funding of £11.7m from Special EU Programmes Body (SEUPB) under Peace III for the construction of the Girdwood Hub and associated environmental works. Since this time the Council, together with the Department for Social Development (DSD), have been working closely to ensure the successful development of Girdwood Park. The construction of Girdwood Community Hub acted as the catalyst for the development of the remainder of the site. Girdwood Community Hub and Wider Site Development A number of construction projects are currently underway on the Girdwood Park site - 3.2  Girdwood Hub – lead by Belfast City Council. Contractual completion of the Hub building is programmed for 30 September 2015 with a 6 week programme of commissioning and handover in advance of a soft opening late November/early December 2015 dependent upon systems testing. The Hub will include:

 State or the art gym

 Large multi-use hall

 Multi-purpose rooms which can be used for community events and activities

 Dedicated shared youth space

 An outdoor piazza with seating

 Classrooms for courses with Belfast Metropolitan College - BMC will be anchor tenants at the Girdwood Community Hub for an initial period of 5 years with an opportunity for review and extension. Courses run will include essential skills, Prince’s Trust programme and IT classes

 Sport Pitch – The 4g multi-use sports pitch is contained within DSD’s wider infrastructure contract with contractual completion for the pitch and spine roads 19 December 2015. The associated infrastructure contract also includes arrangements for removal of the security fence at Cliftonpark Avenue which will be replaced by a temporary fence, at the community’s request together with the removal of security fencing along the rear of Brucevale and Kinnard Street. This work is planned for mid September 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Girdwood Hub: Update ReportMinutes 106 KB DownloadRead as text

At this meeting

Whole meeting
3aNotice of Motion - Provision of DefibrillatorsOn the agenda 3bNotice of Motion - Staff Volunteering PolicyOn the agenda 3cNotice of Motion - A Living WageOn the agenda 3dNotice of Motion - Special OlympicsOn the agenda 3eNotice of Motion - Procurement StrategyOn the agenda 3fNotice of Motion - Transgender EqualityOn the agenda 3gAsylum Refugee ForumOn the agenda 4aTimes of Future MeetingsOn the agenda 4bCity PositioningOn the agenda 4cProgress Report and Leading the City Delegation to MIPIM 2016On the agenda 4dCity Centre Development Team (CCDT)On the agenda 4eTransfer of DSD Urban Regeneration and Community Development PowersOn the agenda 5aCapital Programme UpdateOn the agenda 5bArea Working UpdateOn the agenda
5cGirdwood Hub - Update ReportThis decision
5dCity Hall UpdateOn the agenda 6aContracts for awardOn the agenda 6bFleet Management Unit OverspendOn the agenda 7aEquality Action Plan 2015-16: Feedback from Consultation on and Audit of Inequalities - Pre-ConsultationOn the agenda 7bMinutes of the Meeting of the Good Relations PartnershipOn the agenda 7cMinutes of the Meeting of the Diversity Working GroupOn the agenda 7dMinutes of the Meeting of the Budget and Transformation PanelOn the agenda 7eAudit and Risk PanelOn the agenda 7fRequests for the Use of the City Hall and the Provision of HospitalityOn the agenda 8aInternal Stress AuditOn the agenda 8bNothern Ireland Housing Executive Regional Services Coporate Plan 2015/16 -2017/2018On the agenda 8cIFA Request to Create Fanzone re Belfast Big ScreenOn the agenda

On this subject at Belfast

Search all
  1. Girdwood Hub - Update ReportThis decision
  2. Leisure Transformation Programme - Phase 1 Update: Olympia Regeneration; Andersonstown Regeneration; and Girdwood HubAgreed
  3. Girdwood Community Hub - UpdateAgreed
  4. Girdwood Community Hub - UpdateAgreed

More from Belfast Strategic Policy and Resources Committee

All decisions
MeetingDecisionOutcome
19 Jun 2026 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open
19 Jun 2026 Notice of Motions Quarterly UpdateAgreed to the closure of Notices of Motion 50, 176, 337, 393, 402, 420, 446; · Agreed that Motion 501 - Procedures of... Agreed Open
19 Jun 2026 Good Jobs Charter Initial Consultation - Draft ResponseAgreed the proposed response be submitted to the Department for Economy. Agreed Open
22 May 2026 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open
30 Apr 2026 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies