Licence between BCC and Transport NI to permit Transport NI to carry out works at Corporation Square off street car park
AgreedCommittee2 papers
City Growth and Regeneration Committee agreed this item on Wednesday 11 November 2015. Below is the council's own wording, with the papers it was decided on.
It was agreed at BCC’s Shadow Strategic Policy & Resources Committee Meeting on 20 March 2015 that BCC would continue to work with DRD and other partners through the Strategic Advisory Forum to assess the regeneration opportunities of surplus land parcels resulting from the proposed development at an early stage to maximise the potential benefit for the city. As part of the proposed York Street Interchange Road Scheme TNI has identified the need to construct a reception shaft underneath BCC lands at Corporation Square. TNI engineers have undertaken extensive feasibility and site option assessment works in respect of the proposed shaft location and have confirmed that this is the only suitable location for the reception shaft. 3.4 In order to complete the construction works it will be necessary to close off 48 car parking ... view the full minutes text for item 8.
Word for word from the decision Belfast published for this meeting.Source: minutes.belfastcity.gov.uk
2.1Members are asked to agree to entering into a temporary licence between BCC and TNI to facilitate the construction of a reception shaft as part of the Advanced Works for the proposed York Street Interchange Scheme. The licence agreement will be subject to detailed terms to be agreed between the Estates Manager, BCC Legal Services and TNI. Members are also asked to note that there will be a temporary loss of 48 car parking spaces.
3.0Main report
3.1Key Issues
The off street car park that is located at Corporation Square was transferred to BCC from DRD as part of the Transfer Scheme of Off Street car parking on 1 April 2015. It currently provides a total of 193 car parking spaces.
3.2The Westlink, M2 and M3 Motorways are currently connected through a complex arrangement of traffic signals at York Street. This bottleneck causes significant congestion and delays for traffic travelling at peak times. TNI has developed proposals to provide a grade separated junction at York Street that will greatly improve access between these roads and these proposals are known as the York Street Interchange Road Scheme.
The York Street Interchange Scheme is highlighted in BCC’s City Centre Regeneration Strategy & Investment Plan as a significant project for the city. It was agreed at BCC’s Shadow Strategic Policy & Resources Committee Meeting on 20 March 2015 that BCC would continue to work with DRD and other partners through the Strategic Advisory Forum to assess the regeneration opportunities of surplus land parcels resulting from the proposed development at an early stage to maximise the potential benefit for the city.
3.3As part of the proposed York Street Interchange Road Scheme TNI has identified the need to construct a reception shaft underneath BCC lands at Corporation Square. A map showing the proposed location of the reception shaft is attached as Appendix 1. TNI engineers have undertaken extensive feasibility and site option assessment works in respect of the proposed shaft location and have confirmed that this is the only suitable location for the reception shaft.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.