Strategic Policy and Resources Committee, Tuesday 22 March 2016 at 9.30am

PEACE IV – Capital Update

Agreed Committee 1 paper

Strategic Policy and Resources Committee agreed this item on Tuesday 22 March 2016. Below is the council's own wording, with the papers it was decided on.

Item5d

Resolved

Agreed by SP&R Committee in June 2013. The proposal is to transform one of Belfast’s major arterial routes, creating a multi-faceted corridor of shared use around the themes of faith, heritage, culture, art and play. It would improve connectivity between neighbourhoods, reconnecting the area from Girdwood down to the City Centre, specifically to the Cathedral Quarter, the new Ulster University campus and the Library Quarter. The project would improve the physical environment through the uses of ‘shared by design’ features and preserving the built heritage in the area for future generations, including high profile public realm elements, the city centre up to Girdwood. Costs have not yet been worked up. This Project could potentially be combined with the EPOCH proposal below. 2.3 Cultural Hub - Belfast Story Creation of an experiential Cultural Hub in the city centre, creating a new iconic shared space featuring the Belfast Story through all eras from settlement to the industrial revolution through to Troubles and post Peace Process using range of art forms including digital, art, dance, exhibition film, theatre, etc. This was previously highlighted as a potential PEACE IV project. The City Growth and Regeneration Committee agreed in January that a business case to test the affordability, deliverability, feasibility and sustainability of the proposal is taken forward. This work is underway. Projects where detailed information is available/projects have been worked up 2.4 Shankill Women’s Centre (SWC) Development of a new build facility, cross community facility on Lanark Way. Feasibility and EA undertaken. Indicative costs are £3.5m. Lead applicant - The Shankill Women’s Centre. The Centre would like the Council to act as the lead partner for the project. 2.5 Blackmountain Shared Space The project will deliver a new youth / community facility at the Finlay’s Factory site at the foot of the Black Mountain in an interface area at Springfield / Ballygomartin Road. The Council recently acquired the land. Lead applicant – Black Mountain Shared Space Group. The Group has requested ... view the full minutes text for item 5d
Word for word from the decision Belfast published for this meeting. Source: minutes.belfastcity.gov.uk

Follow this further

Built from Belfast's papers

What the report saysPro

Report to Strategic Policy and Resources Committee

STRATEGIC POLICY & RESOURCES COMMITTEE

Subject: PEACE IV – Capital Update

Date: 22 March 2016

Reporting Officer: Gerry Millar, Director of Property and Projects

Contact Officer: Laura Leonard, European & International Relations Manager Sinead Grimes, Property & Projects Programme Manager

Is this report restricted? Yes No x

Is the decision eligible for Call-in? Yes x No

1.0Purpose of Report or Summary of main Issues 1.1 The purpose of this report is to update Members on the opportunities for capital funding within the new PEACE IV programme and emerging project ideas across the city, and seek a decision on the way forward with regards to Belfast City Council’s role in relation to this.

2.0Recommendations 2.1 The Committee is requested to:  Consider the project ideas outlined below for potential PEACE IV capital funding, and decide which, if any, Council will support, and/or lead. Members should note that the final decision about which projects to fund will rest with SEUPB. It is also recommended that should Members decide to support or lead any PEACE IV capital projects bids, that Officer working groups are immediately established to support the development of these in preparation for the June funding call.

The current emerging PEACE IV capital proposals are outlined below

Proposed Council projects 2.2 North Belfast Cultural Council’s current agreed PEACE IV capital proposal. Agreed Corridor by SP&R Committee in June 2013. The proposal is to transform one of Belfast’s major arterial routes, creating a multi-faceted corridor of shared use around the themes of faith, heritage, culture, art and play. It would improve connectivity between neighbourhoods, reconnecting the area from Girdwood down to the City Centre, specifically to the Cathedral Quarter, the new Ulster University campus and the Library Quarter. The project would improve the physical environment through the uses of “shared by design” features and preserving the built heritage in the area for future generations, including high profile public realm elements, the city centre up to Girdwood. Costs have not yet been worked up. This Project could 2.3 potentially be combined with the EPOCH proposal below. Cultural Hub - Belfast Creation of an experiential Cultural Hub in the city centre, Story creating a new iconic shared space featuring the Belfast Story through all eras from settlement to the industrial revolution through to Troubles and post Peace Process using range of art forms including digital, art, dance, exhibition film, theatre, etc. This was previously highlighted as a potential PEACE IV project.

The City Growth and Regeneration Committee agreed in January that a business case to test the affordability, deliverability, feasibility and sustainability of the proposal is taken forward. This work is underway.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
PEACE IV: Capital UpdateMinutes 118 KB DownloadRead as text

At this meeting

Whole meeting

More from Belfast Strategic Policy and Resources Committee

All decisions
MeetingDecisionOutcome
19 Jun 2026 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open
19 Jun 2026 Notice of Motions Quarterly UpdateAgreed to the closure of Notices of Motion 50, 176, 337, 393, 402, 420, 446; · Agreed that Motion 501 - Procedures of... Agreed Open
19 Jun 2026 Good Jobs Charter Initial Consultation - Draft ResponseAgreed the proposed response be submitted to the Department for Economy. Agreed Open
22 May 2026 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open
30 Apr 2026 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies