Agreed to apply Standing Order 55(a) Exceptions in relation to contracts by direction of the Council acting on recommendations of a Chief Officer – in that the exception was justified in special circumstances for the completion of capital works to space in the former Belfast Telegraph building on the basis that there was an extreme urgency brought about by events unforeseeable to the Council. Appendix 1 - Schedule of tenders for consideration Table 1 - New tenders Title of tender Senior Responsible Officer Proposed contract duration Sponsorship for Belfast Bikes Donal Durkin 3 years Provision of Dog Kennelling facilities and related services Nigel Grimshaw 1 year with the option to renew annually for a further 3 years
Word for word from the decision Belfast published for this meeting.Source: minutes.belfastcity.gov.uk
Report to Strategic Policy and Resources Committee
Purpose of report
1.1The purpose of this report is to: Seek approval from Members to the advancement and award of the tenders as outlined in Appendix 1, Table 1 in accordance with the Scheme of Delegation.
Recommendations
2.1The Committee is asked to:
1. Approve the public advertisement and acceptance of tenders as listed in Appendix 1, Table 1 through the Council’s electronic procurement system.
2. Grant delegated authority to the appropriate Director using pre-agreed criteria the most economically advantageous tender and allow month by month extensions where contracts are under review.
3. Agree to accede to Standing Orders 55(a) exceptions in relation to contracts by direction of the council acting on recommendations of a Chief officer that the exception is justified in special circumstances for the completion of capital works to space in the Belfast Telegraph on the basis that there is an extreme urgency brought about by events unforeseeable to the Council. 3.0 Main report Key Issues 3.1 Section 2.5 of the Council’s Scheme of Delegation outlines that under Standing Order 60(a) any contract that exceeds the statutory amount (currently £30,000) needs to be made under the Corporate Seal. Under Standing Order 51(b) the Corporate Seal can only be affixed when there is a resolution of the Council.
3.2The tenders submitted for approval in Appendix 1, Table 1, have been forwarded by Departments for approval. Departments have been required to provide assurance that provision for the expenditure has either been made within their departmental budgets or approval has been sought from the Director of Finance and Resources that this expenditure has been provided for within a corporate budget.
3.3Members should note that they are being asked to approve tenders in principal, after which the internal governance process demonstrating strategic alignment with the Belfast Agenda, will be applied.
3.4As part of this process, Departments have also provided assurance that appropriate resources are available within their departments in order to effectively administer and management any contract(s).
3.5In accordance with Standing Orders these tenders shall comply with the relevant requirements of national legislation and European directives and be overseen by Corporate Procurement Services.
3.6This report relates to corporate as well as departmental supplies and services only. The procurement of services and works contracts relating to the capital procurement is dealt with under the Capital Programme reports in accordance with the approved stage approval process.
3.7Direct Award Contracts The UK Government’s Digital Catapult (DCUK) has identified ‘immersive technology’ as a significant growth area for the national economy and wishes to establish three national ‘immersive technology’ hubs by November 2017. Locations have been already identified in Gateshead and Brighton and are due to open on this timescale. DCUK wish to establish a third in Belfast.
In August 2017 the NI Department for Economy (DfE) and Digital Catapult NI identified space within the Belfast Telegraph building as an ideal venue for the hub Officials from DfE are now engaging with the Bel Tel LLP to agree licensing terms and fees for this space for an initial 18 month period.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Strategic Policy and Resources Committee at Belfast and we tell you when its next papers are published, before the meeting rather than after it.
Notice of Motions Quarterly UpdateAgreed to the closure of Notices of Motion 50, 176, 337, 393, 402, 420, 446; · Agreed that Motion 501 - Procedures of...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.