The Committee: · noted the contents of the report bearing in mind that all costs are estimated and that no contractor had been appointed to formally survey the identified sites in the context of the changing IFA standard and the indicative costs presented had been informed by officers experienced in the operational management of the sites; and · agreed to await an update from the IFA before considering how it wished to proceed with the alignment of the 12 Belfast City Council pitches with the IFA’s proposed new criteria for intermediate football, in light of the estimated costs.
Word for word from the decision Belfast published for this meeting.Source: minutes.belfastcity.gov.uk
Subject: IFA Intermediate Football Restructure – Impact on Council Facilities
Date: 3rd March 2020
Reporting Officer: Ryan Black, Director of Neighbourhood Services
Contact Officer: Kelly Gilliland, Neighbourhood Services Manager (North)
Restricted Reports
Is this report restricted? Yes No X
If Yes, when will the report become unrestricted?
After Committee Decision After Council Decision Some time in the future Never
Call-in
Is the decision eligible for Call-in? Yes X No
1.0Purpose of Report or Summary of main Issues 1.1 To provide Members with an indication of potential costs involved in bringing current pitch stock to the new IFA standard and to facilitate members in further discussions with the IFA on this matter. 2.0 Recommendations 2.1 Members are asked to note the content of this report bearing in mind that all costs are estimated. No contractor has been appointed to formally survey the identified sites in the context of the changing IFA standard and the indicative costs presented here have been informed by officers experienced in the operational management of the sites.
2.2The Committee is further asked to consider how it wishes to proceed with the alignment of the 12 Belfast City Council pitches with the IFA’s proposed new criteria for intermediate football, in light of the estimated costs. 3.0 Main report 3.1 At the special meeting of People and Communities Committee that was held on 20th November, where the IFA had been invited in to update Members on their proposed new criteria for Intermediate Football, Members requested that an internal exercise was completed to get a better understanding of what the cost implications of adhering to the IFA’s new intermediate criteria might be for Council going forward (overall and on a site by site basis).
3.2In preparation for the meeting on the 20th November, Officers had already undertaken an initial desktop exercise to review the current status of relevant BCC pitches against the proposed new criteria – with12 sites/pitches across the city where intermediate football is currently played having been identified involving 13 clubs who most frequently use those sites/pitches.
3.3Officers with operational experience in the management of these 12 sites have considered the sites against the proposed standards and identified a number of criteria which the pitches will no longer satisfy. Project managers from Physical Programmes and officers of the Landscape Planning and development services have provided a set of indicative costs for major elements based on their experience of delivering the capital projects and the This has given rise to the following assumptions:
INSTALLATION REQUIRED INDICATIVE COST 3G SYNTHETIC PITCH £500,000 CHANGING PAVILLION £600,000 FLOODLIGHTING £150,000 PITCH FENCING FULL PERIMETER DISTANCE INC PEDESTRIAN AND VEHICLE GATES FOR MAINTENANCE £32,150 OFFICIALS FENCING TO MAXIMUM 2 X 55M LENGTHS @ £60per m ASSUMING CORRIDOR EFFECT IS REQUIRED £6,600
3.4Officers have no recent experience of installing covered hard standing on which to base cost estimates however in 2017 Suffolk FC requested permission to install a small covered spectator stand capable of holding up to 100 persons at the Carnanmore park pitch they held under an FMA. The cost at that time was £40,500, an allowance for 3 years of price increase has been made and a figure of £50,625 has been used as an indicative cost on all 12 sites. 3.5 No allowance has been made in these costings for criteria related to the presence of alternative pitch marking or goal posts as these are not considered to be of relevance to the identification of potential capital costings.
3.6In reviewing the sites a number of physical constraints have been identified and the options outlined assume that these constraints have the potential to be overcome, this may not be the case when the sites are formally surveyed by qualified consultants.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.