LA04/2020/2200/F & LA04/2020/2201/DCA - Demolition of Nos. 27 to 37 Linenhall Street and Nos. 8-10 Clarence Street and erection of seven storey office building at 8-10 Clarence Street 27-37 Linenhall Street and existing car park at the corner of Linenhall Street and Clarence Street

Agreed Planning 1 paper

Planning Committee agreed this item on Tuesday 20 April 2021. Below is the council's own wording, with the papers it was decided on.

Item9e

Resolved

Resolved - That the Committee agrees to defer consideration of the application to allow the developer to submit further information in respect of viability and improvements to public realm. The Committee noted, as the application had not been presented, that all Members’ present at the next meeting, would be able to take part in the debate and vote on this item.
Word for word from the decision Belfast published for this meeting. Source: minutes.belfastcity.gov.uk

Follow this further

Built from Belfast's papers

What the report saysPro

Report to Planning Committee

Executive summary

Applications seeking demolition of Nos. 27 to 37 Linenhall Street and Nos. 8-10 Clarence Street and erection of seven storey office building (circa 6000 sqm floor space).

The key issues in the assessment of the proposed development include:  Principle of a building on the site  Demolition within the Linen Conservation Area  Impact on Built Heritage  Impact on character and appearance of the Linen Conservation Area  Design  Acceptability of Office Use at this location  Traffic and Parking  Impact on Amenity  Impact on Historic Monuments  Drainage and Flooding  Pre-application Community Consultation  Air Quality  Waste Water Treatment  Developer Contributions

1. The principle of the proposed office use is acceptable in this city centre location. 2. 3. However, the scale, height, massing, alignment and form of the building will have a detrimental impact upon the setting of a number of listed buildings, including the Ulster Hall. HED objects to the proposal on grounds of harm to the setting of listed buildings, contrary to Policy BH11 of Planning Policy Statement 6. Application ID: LA04/2020/2200/F

4. The proposal includes the demolition of two buildings, one on Clarence Street and one on Linenhall Street. The principle of demolition of the building on Linenhall Street, which makes a positive contribution to the character of the Linen Conservation Area, is not acceptable and the proposed redevelopment scheme does not enhance the character and appearance of the area as it is of a scale and massing which is unsympathetic to the adjoining buildings and the characteristic built form of the area. Both the Conservation Officer and Urban Design Officer object to the proposal. 5. The Council has a duty to adopt a precautionary principle and when considering demolition of a building which makes a positive contribution (to the character of a conservation area): there should be clear and convincing evidence that all reasonable efforts have been made to sustain existing uses or find viable new uses, and that these efforts have failed. The onus therefore is on the applicant to provide detailed evidence in support of such claims.

In the absence of such evidence (as is the case here), the determining factor in assessing demolition of these buildings will therefore be the merits of the alternative proposals. For the reasons stated above, and amplified in the main body of the report, the proposed redevelopment scheme is deemed to be unacceptable. It would have a detrimental impact on the setting of Listed Buildings and harmful to the character and appearance of the Conservation Area.

6. DAERA and NI Water have advised that at present the waste water treatment infrastructure does not have sufficient capacity to serve the proposed development and no acceptable, alternative solution has been proposed. However, for the reasons set out in the main report, it is considered that this issue could be addressed by a suitably worded planning condition and a refusal reason on this issue is not considered appropriate.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
LA04/2020/2200/F & LA04/2020/2201/DCA: Demolition of Nos. 27 to 37 Linenhall Street and Nos. 8-10 Clarence Street and erection of seven storey office building at 8-10 Clarence Street 27-37 Linenhall Street and existing car park at the corner of Linenhall Street and Clarence StreetMinutes 910 KB DownloadRead as text

At this meeting

Whole meeting
2MinutesOn the agenda 4Committee Site VisitsOn the agenda 5Planning Appeals NotifiedOn the agenda 6Planning Decisions IssuedOn the agenda 7AbandonmentsOn the agenda 8aConfirmation of ListingsOn the agenda 9a(Reconsidered item) LA04/2019/1540/F - Centralised Anaerobic Digestion (CAD) plant to include a bunded tank farm, (6no.On the agenda 9bLA04/2020/0426/F - Reconstruction of petrol station and ancillary retail unit including the replacement of fuel tanks, pumps and canopy alterations. Hot food takeaway unit, ATM, compactor and provision of an EV charging facility at 228 -232 Stewartstown RoadOn the agenda 9c(Reconsidered item) LA04/2019/1833/F - New dwelling to replace previous dwelling on site at 11 Ashley Park, DunmurryOn the agenda 9d(Reconsidered item) LA04/2020/0857/F - Demolition of existing hostel building and redevelopment to provide four-storey building comprising 15 No. residential units, office space and ancillary development at Ormeau Centre, 5-11 Verner StreetAgreed
9eLA04/2020/2200/F & LA04/2020/2201/DCA - Demolition of Nos. 27 to 37 Linenhall Street and Nos. 8-10 Clarence Street and erection of seven storey office building at 8-10 Clarence Street 27-37 Linenhall Street and existing car park at the corner of Linenhall Street and Clarence StreetThis decision
9fLA04/2021/0024/F & LA04/2021/0025/DCA - Retrospective single storey extension to front of existing single storey garage/ Minor demolition works to front garage at 10 Broomhill ParkOn the agenda 9gLA04/2021/0320/F - Variation of Condition 3 (agreement of proposed materials prior to commencement) of planning permission LA04/2015/0264/F to enable a change to the proposed materials to be agreed prior to occupation of the development (cuOn the agenda 9hLA04/2020/1783/F - Change of use and refurbishment of the ground floor and part of the first floor of a three storey building in the Conway Mill Complex to a new training gym with elevation changes at St John Bosco ABC, Conway Mill, 5-7 Conway StreetOn the agenda 9iLA04/2020/2093/F - Change of use from retail furniture showroom to fitness/exercise training centre and leisure at 71 Ballysillan RoadOn the agenda 9jLA04/2020/2469/F - Pedestrianised public space to include cafe/bar/storage container/canopy areas, performance stage, outdoor seating and associated works (temporary permission) on Brunswick Street.On the agenda 10LA04/2019/2653/F - Demolition of existing property and erection of a 9 storey building (overall height 37m) comprising a ground floor retail unit together with cycle parking and plant areas: and 8 floors of grade A office accommodation at Chancery House 88 Victoria StreetAgreed

On this subject at Belfast

Search all
  1. LA04/2020/2200/F & LA04/2020/2201/DCA - Demolition of Nos. 27 to 37 Linenhall Street and Nos. 8-10 Clarence Street and erection of seven storey office building at 8-10 Clarence Street 27-37 Linenhall Street and existing car park at the corner of Linenhall Street and Clarence StreetThis decision
  2. LA04/2019/1819/F & LA04/2019/1820/DCA - Demolition of existing dwelling and erection of 3 storey (and basement) detached dwelling with garage and landscaping to front and rear at 28 Malone ParkAgreed
  3. LA04/2020/0847/F & LA04/2020/1208/DCA - Partial demolition and redevelopment of existing buildings to provide 16 apartments, communal bin store and landscaped communal garden at 25-29 University RoadAgreed
  4. LA04/2019/0110/F & LA04/2019/0111/DCA - Demolition of single dwelling and erection of 2 semi-detached dwellings at 47a Derryvolgie AvenueApproved

More from Belfast Planning Committee

All decisions
MeetingDecisionOutcome
10 Mar 2026 Restricted ItemResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open
9 Feb 2026 Restricted ItemsResolved – That the Committee agrees to exclude the Members of the Press and public from the Committee meeting during... Agreed Open
9 Dec 2025 Restricted ItemsResolved – That the Committee agrees to exclude the members of the press and public from the meeting during discussio... Agreed Open
14 Oct 2025 LA04/2022/1819/F - Demolition of existing buildings and erection of 32 apartments in 3No. blocks (7@ 1no. bedroom and 25@ 2no. bedrooms) (6no. wheelchair adaptable) and associated site works. - 39 Upper Dunmurry Lane, DunmurryResolved – “That the Committee writes to the Northern Ireland Federation of Housing Associations to invite them to at... Agreed Open
12 Aug 2025 LA04/2024/1654/F - Change of use from a 7-bedroom dwelling house (C1) to a 7 bed/ 9 person House of Multiple Occupancy (Sui Generis) - 432 Falls RoadResolved – “That the Committee refuses to grant planning permission on the basis of the lack of parking provision whi... Refused Open