Audit Committee, Tuesday 21 December 2010

Risk Management Report

Decided Finance 3 papers

Audit Committee decided this item on Tuesday 21 December 2010. Below is the council's own wording, with the papers it was decided on.

Item271

Resolved

DECISION That the Risk Management report be accepted. Reason: To enable the Audit Committee to monitor the management of risk within the Council.
Word for word from the decision Blaby published for this meeting. Source: democracy.blaby.gov.uk

Follow this further

Built from Blaby's papers

What the report saysPro

Report to Audit Committee

Purpose of report

1.1This report updates the Committee on the current position in relation to the risk issues identified in the Corporate Risk Register for the period ending December 2010.

Recommendation

2.1To accept the Risk Management report.

3. Reason for Decision Recommended

3.1To enable the Audit Committee to monitor the management of risk within the Council

4. Forward Plan

4.1Not applicable.

5. Key Decision

5.1Not applicable.

6. Matters for Consideration

6.1Introduction

The management of risk at all levels is a critical success factor for any organisation in achieving its objectives. The role of the Internal Audit service is to evaluate the effectiveness and give advice on the improvement of the risk management process within the council.

6.2Strategic/Corporate Risks

The Corporate Risk Group continues to meet on a quarterly basis to assess current risk and mitigating controls. This includes identifying new risks, putting mitigating controls in place and re-assessing the impact and likelihood of each risk. They also review high operational risks across the Council and monitor the management of risk by managers.

All corporate risks and significant risks across the Council continue to be effectively recorded and monitored on JCAD, our risk management system.

6.3Analysis of Risks

Risks are assessed as to their impact on the business of the Council and the likelihood of them occurring. Currently there are 51 corporate risks and their relative positions are demonstrated on the Risk Dashboard Report (appendix 1). The Dashboard allocates ‘high’ risks to the red area, ‘medium’ risks to the amber area and ‘low’ risks to the green area. A summary of the risk levels is as follows:

Red 15.69% Amber 39.22% Green 45.10%

It can be seen that there are 8 risks that have been identified as having potentially a ‘major’ impact or ‘major disaster’ on the Council’s business. These ‘high’ risks are detailed at the bottom of appendix 1. Controls put in place to mitigate these high risks have resulted in 7 of these being re- assessed as medium risk.

The remaining high risk relates to ‘Inadequate infrastructure around new housing developments to support sustainable communities’. The controls in place for this risk are: • S106 policy and implement • Influencing LEP • Deliver LDF/Core Strategy

Mitigating controls put in place for all the High Corporate Risks are detailed in the Corporate Risk Register which is attached at Appendix 2.

6.4Monitoring Service Risk Registers

Service Risk Registers are all held on JCAD and each Group Manager has a specific responsibility to:

• Identify, analyse and ensure that there are regular reviews of risk within their services • Escalate risks as appropriate to Corporate Risk Group

A review to ensure all risks have been identified and adequate mitigating controls are in place is currently being carried out by Performance and Audit with the relevant service managers.

6.5External review of risk management arrangements

Risk management arrangements within the Council are also reviewed by our external auditors, PriceWaterhouseCoopers, through the audit work that they carry out with us. 6.6 Conclusion

Corporate Risks within the Council are being managed and monitored regularly. JCAD software is providing accountability for monitoring and managing risks effectively as each individual risk and control measure is assigned to a specific Manager and Portfolio Holder. The management of risk within the Council continues to be developed and improved.

7. Other Relevant Considerations

7.1Risk Assessment & Business Continuity

• Risk & business continuity/resilience issues are considered within the Corporate Risk Register and Individual Service Risk Registers. Significant risks are reported to the Audit Committee for their consideration as part of this report.

7.2Equalities

i No EINA is required for this report. i Equalities is considered as part of the risk management process

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Management ReportReport 37 KB DownloadRead as text
PDF
Risk Report App 1 21Dec10Appendix 27 KB Download
PDF
Risk Report App 2: high risks 21Dec10Appendix 55 KB Download

At this meeting

Whole meeting

Who was there

5 of 12 attended
JH
Councillor J.O. HudsonChairman, present
DJ
Councillor D. JenningsVice-Chair, present
JB
Councillor J. BlackwellMember, apologies
DF
Councillor D. FreerMember, absent
JK
Councillor J. KenneyMember, present
BP
Councillor B.M. ParkinsMember, present
JS
Councillor J. SpringthorpeMember, present
JH
Mr J.L. HoldenOfficer, in attendance
SP
Sarah PennelliOfficer, in attendance
AM
Alison MoranOfficer, in attendance
MB
Mr M. BerryOfficer, in attendance
AB
Alison BreadonPublic, in attendance

On this subject at Blaby

Search all
  1. Risk Management ReportThis decision
  2. Risk Management StrategyApproved
  3. Risk Management Strategy 2023 - 2026Approved
  4. Risk Management Strategy 2019 - 2022Approved
  5. Risk Management Strategy 2015-18Approved
  6. Risk Management Update - March 2008 to June 2009Noted

More from Blaby Audit Committee

All decisions
MeetingDecisionOutcome
30 Jun 2011 Introduction to Audit and the Audit CommitteeIt was agreed that future dates for training for Members of the Audit Committee would be sought. Agreed Open
21 Dec 2010 Annual Audit LetterDECISION That the produced by PriceWaterhouseCooopers be acknowledged and its contents accepted. Reason: It is approp... Decided Open
21 Dec 2010 Use of ResourcesDECISION That the ‘’ assessment and the progress the Council has made be accepted. Reason: This assessment was carrie... Agreed Open
21 Dec 2010 Internal Audit Progress Report October - December 2010DECISION That the Internal Audit report for the third quarter of the 2010/2011 financial year be accepted. Reason: To... Decided Open
27 Sep 2010 Blaby District Council Results of 2009/10 Audit to Those Charged with Governance - Report from PWCDECISION That the report of the Deputy Chief Executive be accepted. That the Audit Committee confirm that the unadjus... Decided Open