DECISION That the budget expenditure of £167,582 for the demolition of the former Depot at Warwick Road, Littlethorpe be approved. Reason: 1. To minimise health and safety risks once the site is vacated. 2. To prepare the site in readiness for future plans including improving the market value.
Word for word from the decision Blaby published for this meeting.Source: democracy.blaby.gov.uk
The former Depot site at Warwick Road, Littlethorpe is 0.86 hectares (2.14 acres) in size and is surrounded on three sides by residential properties towards the edge of the village. It has historically operated as Blaby District Council’s Waste Management and Maintenance Vehicle Depot and includes an office block, a large central garage, numerous warehouse buildings, vehicle storage bays and two underground fuel tanks. Due to the age of the structures there is extensive asbestos throughout the site and the buildings themselves are showing signs of extensive structural wear.
Assessment works have been undertaken by specialist consultants to establish the current condition and extent of asbestos within the Littlethorpe Depot which have indicated disproportionate cost for structural repair and a high level of licensable asbestos which carries a high risk to health if disturbed. Currently asbestos is monitored and inspected within the building as part of the general operation of the site but once the site is unoccupied the risk of intrusion and damage to the fabric of the building and the asbestos is increased.
Future plans for the Depot are under consideration and a full options appraisal will be undertaken to determine the best approach for disposal and to minimise the length of time the site remains vacant. No capital budget had previously been made as the intention was to net off potential demolition costs from a sale of the site.
The demolition of the building and clearance of asbestos will reduce risk to the public and the Authority and is intended to increase the development value of site. Additional security will be in place once the site is vacated.
4.2Proposal
It is recommended that authority be given for funding to undertake the demolition and asbestos removal works at the Depot site.
Should the recommendation be approved a planning application will be submitted for the demolition works. With this and the required procurement processes, it is anticipated that demolition works will commence in January/February 2017.
4.3Relevant Consultations
Senior Leadership Team, Health and Safety Advisor, Accountancy Services Manager.
4.4Significant Issues
None
5. What will it cost and are there opportunities for savings?
5.1The total assessed cost for the works is £167,582. This is comprised of a sum of £70,946 for general demolition works and preliminary overheads and £96,636 for safe removal of asbestos from site. This represents a worst case maximum budget for the Authority and we are advised that the market is currently very competitive and that we should secure significant savings through the procurement process. There will be some additional costs for increased security, NNDR business rates and utilities costs but we would look to use the remainder of the existing revenue budget to cover this. Current year 2017/18 Revenue 0 0 Capital 167,582 0
6. What are the risks and how can they be reduced?
6.1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Croft Conservation Area DesignationDECISION That the designation of a Conservation Area, as identified on the Croft Conservation Area, as identified on ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.