Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to the additional condition in the Update Report and an agreement under Section 106 of the Town & Country Planning Act 1990, relating to the payment of £398,950; plus a monitoring fee of £3950. Payments to be phased as follows: · £199,475 to be paid prior to commencement of the development (£197,500 for education and £1,975 monitoring fee); and · £199,475 to be paid within 12 months after commencement (£197,500 for education and £1,975 monitoring fee). Should the Section 106 agreement not be completed within 6 months of the date of the planning application being received, the Director of Growth and Development will have delegated powers to refuse the application.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
Proposed development: Full Planning Application (Regulation 4) for: Demolition of one substation building and the erection of 383 dwellings and associated works
Site address: Land to the North and South of Fishmoor Drive and Land to the East of Roman Road Blackburn
Applicant: Countryside Properties (UK) Ltd and Together Housing Group
Ward: Blackburn South East
Councillor: James Shorrock Councillor: Vicky Ellen McGurk Andy Kay M a r k a z u l U lo o m
Fishmoor Reser voir
HI G HER CRO FT
BLACKAMO O R 1.0 SUMMARY OF RECOMMENDATION
1.1APPROVE – Subject to a Section 106 Agreement relating to education provision and conditions, as set out in paragraph 4.1.
2.0KEY ISSUES/SUMMARY OF PLANNING BALANCE
2.1Detailed assessment of the application establishes that the proposed development corresponds with the Council’s overarching housing growth strategy, as set out in the Core Strategy and Local Plan Part 2. Delivery of a high quality housing development is assured, focussed on land that was previously developed to the north west and south east of Fishmoor Drive and to a previously developed site, primarily allocated for housing, to the east of Roman Road, Blackburn. Moreover, from a technical point of view, all issues have been addressed through the application or are capable of being controlled or mitigated through planning conditions and a Section 106 Agreement.
2.1.1 Approval of the application will secure a much anticipated and aspirational regeneration of the Fishmoor Area, offering highly significant economic, environmental and social benefits, including but not limited to quality mixed tenure housing (social rented, shared ownership and out right sale) which will widen the choice of family homes in the Borough, quality public open space and increased educational capacity for the community. The development will also boost the supply of family housing to meet the Council’s 5 Year Land Supply Target.
2.1.2 Submission of the application follows extensive pre-application consultation undertaken by the Applicants with the local community (including community groups), Council departments and elected Members. This is an approach advocated by The Framework and National Planning Policy Guidance, for schemes of this nature. The consultation included a pre-application meeting between the applicants and Council departments, and a public exhibition event at Roman Road Library, held in February last year. A Statement of Community Involvement submitted with the application sets out the applicants approach to community consultation and their response to the main issues raised. The final scheme responds proportionately to representations made during the pre-application process.
2.1.3 The scale of the proposed development directs the need for it to be screened in accordance with the Town and Country Planning (Environmental Impact Assessment) Regulations 2017 (the ‘EIA Regulations’) and supporting Planning Practice Guidance (PPG).
2.1.4 As an application for 383 dwellings, it falls to be screened under Schedule 2 of the EIA Regulations. Schedule 2 development requires an EIA if it would be likely to have significant effects on the environment. 2.1.5 The proposed development falls within category 10 of Schedule 2, ‘Infrastructure Projects’, sub-section (b) ‘Urban Development Projects’. The thresholds for residential developments as set out in Schedule 2 relate to developments that includes ‘more than 150 dwellings’. The proposed development is for 383 dwellings (above the threshold). It, therefore, requires further screening to determine whether there would likely be significant effects, either from the development in isolation or cumulatively when considered with other development in the vicinity. To achieve this, Schedule 3 of the EIA Regulations and the PPG need to be considered. Schedule 3 sets out the following selection criteria:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Highways Committee at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
Planning Items for DeterminationThat the committee considered the updated reports of the Strategic Director (Growth and Development) which detailed t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.