Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to: Delegated authority is given to the Strategic Director of Place to approve planning permission, subject to an agreement under Section 106 of the Town & Country Planning Act 1990, relating to the payment of £1,219,272 including a monitoring fee of 12,072. Should the Section 106 agreement not be completed within 6 months of the date of the planning application being received, the Strategic Director of Place (Growth and Development) Department will have delegated powers to refuse the application.
Word for word from the decision Blackburn with Darwen published for this meeting.Source: democracy.blackburn.gov.uk
SUPPLEMENTAL REPORT OF THE STRATEGIC DIRECTOR Plan No: 10/21/1426
Proposed development: Hybrid planning application comprising - Full permission for the erection of 160 dwellings and 50 affordable, key hospital worker apartments in two blocks together with access roads and landscape treatment (Phase 1); and outline permission for the erection of 100 affordable, key hospital worker apartments in four blocks, with all matters reserved except for access (Phase 2).
Site address: Land Bounded by Haslingden Road and Fishmoor Reservoir Haslingden Road Blackburn
Applicant: Keepmoat Homes
Ward: Blackburn South East Councillor Tony Humphrys Councillor Vicky McGurk Councillor James Shorrock 1.0 SUMMARY OF RECOMMENDATION
1.1APPROVE – Subject to a Section 106 Agreement of £1,219,272, relating to additional secondary school places and highway works towards completion of the South East Major Transport Scheme; and conditions. Full details are set out at paragraph 4.1.
2.0KEY ISSUES/SUMMARY OF PLANNING BALANCE
2.1Members resolved to grant planning permission at the 21st April 2022 meeting of the Planning & Highways Committee. Members agreed with the recommendation that the proposal would deliver a high quality housing led development, on a site allocated for such, which widens the choice of family housing in the Borough, in support of the Council’s planning strategy for housing growth, as set out in the Core Strategy and Local Plan Part 2. The proposal was also deemed to be satisfactory from a technical point of view, with all issues having been addressed through the application, or capable of being controlled or mitigated through planning conditions and a Section 106 Agreement.
2.2The application has been returned to the Committee in order that a condition can be agreed, in addition to those already agreed, as set out at paragraph 4.1.
3.0DISCUSSION
3.1Since Committee’s resolution to grant planning permission at April’s Committee meeting, the formal decision is yet to be issued, pending completion of a Section 111 / 106 Agreement between the Council and the applicant to secure a financial contribution of £1,219,272. Since the Committee meeting, dialogue between the LPA, the applicant and United Utilities (UU) has established that the exact location of a water main, owned by UU, and an appropriate easement is yet to be formally agreed. This is contrary to the LPA’s understanding at the time of reporting the application to Committee Members.
3.2Since a formal decision notice is yet to be issued, this affords the opportunity to apply the following condition that UU have since recommended, to the full permission element of the subsequent decision – no. 31 in sequence. This is in order to safeguard UU’s asset water main from construction activity.
Asset Protection No development shall commence (including any earthworks) until details of the means of ensuring the water main that is laid within the site boundary is protected from damage as a result of the development have been submitted to and approved by the Local Planning Authority in writing. The details shall include a survey of the exact location of the water main and outline the potential impacts on the water main from construction activities and the impacts post completion of the development and identify mitigation measures to protect and prevent any damage to the water mains both during construction and post completion of the development. The details shall include a pre and post construction condition survey. Any mitigation measures shall be implemented in full in accordance with the approved details.
Reason: In the interest of public health and to ensure protection of the public water supply, in accordance with Policies 8 and 9 of the Blackburn with Darwen Borough Local Plan Part 2.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Highways Committee at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
Planning Items for DeterminationThat the committee considered the updated reports of the Strategic Director (Growth and Development) which detailed t...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.