Planning Application 22/1006

Approved Planning 1 paper

Planning and Highways Committee approved this item on Thursday 16 February 2023. Below is the council's own wording, with the papers it was decided on.

Item71.5

Resolved

Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to the conditions highlighted in the Directors Report and the following amendments to various conditions: The following amendments to the suite of conditions itemised at paragraph 4.1 of the main report are agreed: Removal of the following condition – itemised as no. 8 in the main report: Prior to commencement of the development hereby approved, and notwithstanding the submitted details, a scheme for protecting the surrounding residential and commercial premises from noise, vibration and dust shall be submitted to and approved in writing by the Local Planning Authority. The approved scheme shall be implemented and adhered to throughout the period of demolition and construction. REASON: In order to safeguard neighbouring amenity, in accordance with Policy 8 of the Blackburn with Darwen Borough Local Plan Part 2. The requirements of the condition are instead included in the DCEMP condition, itemised as no. 15 in the main report. Amendment to condition itemised as no. 17 in the main report: Replace ‘Prior to commencement of development’ with Prior to above ground works. Amendment to condition itemised as no. 19 in the main report: Replace ‘Prior to commencement of development’ with Prior to above ground works. Removal of the following condition – itemised as no. 23 in the main report: Prior to occupation of the development hereby approved, and notwithstanding the submitted detail, a Landscape and Environmental Management and Maintenance Strategy shall be submitted to and approved in writing by the Local Planning Authority. The strategy shall cover all landscaped areas of public open space, subject to details approved under condition 20, and it shall detail a programme of works including scheduled frequencies of weeding and watering as well as monitoring of habitats for a period of 30 years. The strategy shall be implemented in accordance with the approved detail upon completion of the development. REASON: To ensure that there is a well maintained scheme of healthy trees and shrubs in the interests of amenity in accordance with Policies 9, 11 and 40 of the Blackburn with Darwen Borough Local Plan Part 2. Measures required by the condition are instead included in condition 26 (Landscape & Ecological Management Plan). Amendment to condition itemised as no. 24 in the main report: Removal of ‘as well as a maintenance programme to be implemented post completion of the development, for a specified period of time’. Instead the requirement will be included in the LEMP condition, itemised as no. 26 in the main report. Amendment to condition itemised as no. 26 in the main report: Removal of: - Persons responsible for implementing the works. - Details of initial aftercare and ... view the full minutes text for item 71.5
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Planning and Highways Committee

Background

3.1.1 The application is submitted following pre-application dialogue with the applicant (Suez Recycling & Recovery UK Ltd). The site currently benefits from an extant planning permission to create the new Darwen Energy Recovery Centre – EFW facility. The facility would process up to 500,000 tpa of residual municipal, commercial and industrial waste. Permission was granted in August 2019 by the Planning and Highways Committee, under application reference 10/19/0495. Permission was subject to a mutually agreed 4 year commencement period which expires on 15th August 2023. The current ADF proposal is submitted as an alternative form of waste management facility to the EFW which is unlikely to come forward, due to a significant shift in market forces, since approval of the facility.

3.1.2 The applicant does, however, wish to secure lawful commencement of the EFW permission, in order to retain the option of developing the site for that purpose, should market forces dictate a need. In order to facilitate this option and to ensure lawful commencement can be achieved, an application is anticipated to discharge pre-commencement conditions and / or to vary the wording of conditions, as may be necessary. Members should, however, be assured that only one development - either the ADF or EFW - will be implemented. Indeed the site cannot physically accommodate both. In order to formalise the position, the applicant and the Council have agreed that revocation of the EFW permission will be triggered upon commencement of the ADF, legally secured via either a clause inserted into the Section 106 Agreement or a Unilateral Undertaking. Discussions with the Council’s Legal team are ongoing in this regard and the final position will be represented in the Update Report.

3.2Site and Surroundings

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Planning Application 22/1006Report 1.8 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 21 attended
DS
Councillor David SmithChair, present
HA
Councillor Hussain AkhtarVice-Chair, apologies
JC
Councillor Jim CaseyCommittee Member, present
ZK
Councillor Zamir Khan MBECommittee Member, present
JS
Councillor Jacqueline SlaterCommittee Member, apologies, sent representative
PB
Councillor Paul BrowneCommittee Member, apologies
GP
Gavin PrescottOfficer, expected
MG
Michael GreenOfficer, present
RS
Rabia SaghirOfficer, expected
SA
Safina AlamOfficer, present
MK
Martin KellyOfficer, expected
SG
Shannon GardinerClerk, present

All 21 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Planning Application 22/1006This decision
  2. Planning Application 10/24/0728 - United Reformed Church, Ashleigh Street, DarwenApproved
  3. Planning Application 10/25/1150 - Vacant Land adjacent to former St. John Vianney RC Church, Livesey branch Road, BlackburnApproved
  4. Planning Application 10/25/1187 - Land at Bank Hey View, off Heys Lane, BlackburnApproved
  5. Planning Application 10/25/1257 - Land to the East of Buncer Lane, BlackburnDeferred
  6. Planning Application 10/26/0009 - Land adjacent to Newlands, 61 Manor Road, DarwenApproved

More from Blackburn with Darwen Planning and Highways Committee

All decisions
MeetingDecisionOutcome
20 Aug 2026 Minutes of meeting Thursday, 16 July 2026 of Planning and Highways CommitteeThat the minutes of the last meeting held Thursday, 16 July 2026 be agreed as a correct record and signed by the Chair. Agreed Open
20 Aug 2026 Material ConsiderationsThat the material considerations be noted. Noted Open
20 Aug 2026 Planning Items for DeterminationThat the committee considered the updated reports of the Strategic Director (Growth and Development) which detailed t... Decided Open
20 Aug 2026 10/25/1270 10/25/1274 - King George's Hall Northgate, Blackburn, BB2 1AAThat the planning permission be granted subject to the conditions detailed in Section 5 of the report. Decided Open
20 Aug 2026 10/25/1356 10/25/1357 - King George's Hall, Northgate, Blackburn BB2 1AAThat the planning permission be granted subject to the conditions detailed in Section 5 of the report. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies