Resolved
Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to the conditions highlighted in the Director’s Report.
Planning and Highways Committee approved this item on Thursday 20 April 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to the conditions highlighted in the Director’s Report.
REPORT OF THE STRATEGIC DIRECTOR Plan No: 10/22/1152
Proposed Development: Erection of replacement 2m high fencing along the northeast and northwest site boundaries
Site Address: Land at Watery Lane (between Clough Street and Spring Vale Garden Village), Darwen
Applicant: [name removed]: Darwen South
Councillor Kevin Connor Councillor Matthew Jackson 21 Councillor Lilian Salton 33
5 12 29
AY 22
ET SEW 189.4m
STRE
4 CAU 28 1 13
2a 13 15 B EN 8 23 36 TL 16 EY ST R EE T 5
13 LB 62
4 187.5m
48 9a 1 NE 9 LA RY 8 14 TE Th 7 WA M e ew 54
5 s 5 3
SPRING 185.9m
VALE Riv Church
ET 6
er RE Darw ST ER 1 Weir en OCK C 5
(PH) Riv er D 1 arw en 70 20
70 77
Waste Disposal Centre 73
Car Park
Springvale Business Park 1 68
188.7m
C THE CL LO OU GH U y
G Bd
H ST ard
6 R W
EE T 6 Watery Lane 4
Industrial 1
Estate Ri ve Stone r Da rw 26
De en
f 1
5 38
193.0m 50
1 1.0 SUMMARY OF RECOMMENDATION
1.1The proposed development is recommended to be granted planning permission, subject to the conditions and informative note detailed in Section 5.
2.0KEY ISSUES/SUMMARY OF PLANNING BALANCE
2.1This application is presented to the Planning and Highways Committee, in accordance with the Council's Constitution, and given that a large number of objections have been received.
2.2The proposed development has been publicised through letters to residents and occupants of the nearest 14 adjacent properties on 12th December 2022. Those neighbours were renotified on 25th January 2023 and 08th February 2023 given the receipt of amended information. A site notice was also displayed at the site access point on 19th December 2022.
2.3Public comments have been received from 8 addresses objecting to the development. The objections received principally concern the temporary style of the fencing currently in place together with consequential visual impacts. Land ownership has also been cited as a concern. A summary of the objections received is detailed below in Section 7.6.
2.4The Council’s development plan supports new minor developments and associated works, provided they constitute sustainable development and accord with the development plan when taken as a whole.
2.5This application involves the erection of replacement fencing around the northeast and northwest site boundaries. Temporary metal ‘heras’ style fencing is currently in place, which would be replaced by green 2m high weld-mesh fencing. Suypplimentary landscaping would also be provided along Watery Lane.
2.6On balance, the proposals would be satisfactory from a technical point of view, with all issues having been addressed through the application process or capable of being controlled or mitigated through appropriately worded planning conditions.
2.7The key issues to be addressed in determining this application are follows;
Assessing any design and visual amenity impacts Safeguarded the residential amenities of the immediate neighbours Assessing any potential impacts on highway safety Ensuring flood risk is not increased
2 3.0 RATIONALE
3.1Site and Surroundings
3.1.1 The application site is a private carpark located within the settlement of Darwen. The site covers an area of circa 680 square meters. Dwellings and open landscaped areas surround to all sides. A culverted stretch of the River Darwen runs beneath parts of the site and the site is partly within Flood Zones 2 and 3 as a result.
Figure One – Satellite image of the site
3.1.2 The site has historically been used as a carpark yet it has been enclosed by fencing for around 2 years and a locked timber gate has been installed at the access point from Watery Lane. In addition to the temporary metal fencing, timber post and rail fencing of various heights define the site boundaries. A number of mature trees are also positioned adjacent.
Figure Two – Submitted Location Plan/Proposed Site Plan (amended)
3 3.2 Proposed Development
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Application 22/1152Report | 2.3 MB | DownloadRead as text |
Follow Planning and Highways Committee at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Aug 2026 | Minutes of meeting Thursday, 16 July 2026 of Planning and Highways CommitteeThat the minutes of the last meeting held Thursday, 16 July 2026 be agreed as a correct record and signed by the Chair. | Agreed | Open |
| 20 Aug 2026 | Material ConsiderationsThat the material considerations be noted. | Noted | Open |
| 20 Aug 2026 | Planning Items for DeterminationThat the committee considered the updated reports of the Strategic Director (Growth and Development) which detailed t... | Decided | Open |
| 20 Aug 2026 | 10/25/1270 10/25/1274 - King George's Hall Northgate, Blackburn, BB2 1AAThat the planning permission be granted subject to the conditions detailed in Section 5 of the report. | Decided | Open |
| 20 Aug 2026 | 10/25/1356 10/25/1357 - King George's Hall, Northgate, Blackburn BB2 1AAThat the planning permission be granted subject to the conditions detailed in Section 5 of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.