Resolved
Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to the conditions highlighted in the Director’s Report
Planning and Highways Committee approved this item on Thursday 25 May 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
Decision under Town and Country Planning Acts and Regulations – RESOLVED – Approved subject to the conditions highlighted in the Director’s Report
REPORT OF THE STRATEGIC DIRECTOR Plan No: 10/23/0030
Proposed development: Full Planning Application for Erection of 1no unit for vehicle showroom (sui generis) and associated landscaping
Site Address: Plot 4 Land off Millbank Road/Greenbank Terrace Lower Darwen
Applicant: Hippo Motor Group Ltd
Ward: Blackburn South & Lower Darwen Councillor John Slater Councillor Jacqueline Slater Councillor Denise Gee 1 SUMMARY OF RECOMMENDATION
1.1APPROVE – Subject to conditions; as set out in paragraph 4.1.
2. KEY ISSUES/SUMMARY OF PLANNING BALANCE
2.1There is a long and complicated planning history for this application site. The 10/18/1149 hybrid approval established full planning permission for a new link road and access points; and outline approval with all matters reserved (except for access) for a mixed use development comprising a maximum of the following: 100 dwellings (C3), 9,000m2 of employment use and careers hub (B1/B2/B8/D1), and associated ancillary works.
2.2Various Reserved Matters (RM) applications were subsequently submitted and approved, including RM approval for the provision of 35,000 sqft (3,251m²) internal floorspace of the approved employment use; in 4 separate Units known as Plots 1 - 4.
2.3RM approval for Plot 4 was approved under RM application 10/21/1328.
2.4This current application, which is submitted as a new, full planning application rather than an amended RM submission, is essentially a revised scheme to the RM previously approved for Plot 4 under ref 10/21/1328. However, as a full application, all matters need to be considered.
2.5Notwithstanding this, many of the fundamental matters have already been covered by the hybrid approval for the site, and the outline approval and subsequent RM approval are material considerations. Conditions in relation to the various outline and RM permissions for the wider site remain in place, and have either been discharged, or are awaiting discharge.
2.6Given the complexity of the site, for its wider context, the flowchart below shows the present situation of how all the applications link together. Figure 1: Flowchart
2.7The main difference between this new full application for Plot 4 and the previous RM approval for the Class B2 / B8 use of Plot 4 is the proposed vehicle showroom use, which is a Sui Generis use, and therefore requires planning permission in its own right. Had that not been the case, the physical changes proposed could have been assessed under a S73 variation of the previously approved RM plans. However, the previous outline and RM approvals remain material considerations.
2.8Aside from the difference in use, other differences to the previously approved scheme include a change to the large open internal layout to accommodate a showroom and customer sales area etc, and a considerable reduction in the overall internal floorspace from 3,251 sqm to 660sqm (ground floor), with an additional mezzanine floor space (staff facilities) of 325sqm (985sqm in total). There would also be a flat roof canopy on stilts, and a total of 321 fenced vehicle display spaces. The footprint of the proposed building and the canopy combined would be circa 67m x 35m, but the footprint of the building itself would only measure 31m x 21.5m. The height of the building would be similar to the previously approved building, at circa 8m, and would use similar materials.
2.9Essentially the proposal reflects the size, scale, design and appearance of other buildings in the area, and would meet the functional needs of a vehicle showroom. Assessment of this planning application finds that the proposal will deliver a high quality scheme that will assist in meeting the Council’s strategic aims and objectives, including economic growth, and regeneration benefits.
2.10All relevant issues have been addressed or can be controlled or mitigated through planning conditions. 3 RATIONALE
3.1Site and Surroundings
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Planning Application 23/0030Report | 3.1 MB | DownloadRead as text |
Follow Planning and Highways Committee at Blackburn with Darwen and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Aug 2026 | Minutes of meeting Thursday, 16 July 2026 of Planning and Highways CommitteeThat the minutes of the last meeting held Thursday, 16 July 2026 be agreed as a correct record and signed by the Chair. | Agreed | Open |
| 20 Aug 2026 | Material ConsiderationsThat the material considerations be noted. | Noted | Open |
| 20 Aug 2026 | Planning Items for DeterminationThat the committee considered the updated reports of the Strategic Director (Growth and Development) which detailed t... | Decided | Open |
| 20 Aug 2026 | 10/25/1270 10/25/1274 - King George's Hall Northgate, Blackburn, BB2 1AAThat the planning permission be granted subject to the conditions detailed in Section 5 of the report. | Decided | Open |
| 20 Aug 2026 | 10/25/1356 10/25/1357 - King George's Hall, Northgate, Blackburn BB2 1AAThat the planning permission be granted subject to the conditions detailed in Section 5 of the report. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.