Treasury Management Strategy 2025/26

Approved Executive 2 papers

Executive Board approved this item on Thursday 13 March 2025. Below is the council's own wording, with the papers it was decided on.

Item102

Resolved

That the proposed Treasury Management Strategy for 2025/26, as detailed in Appendix 1 attached to the report, including the proposed Treasury management Indicators be approved.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Executive summary

1.1Treasury risk management is conducted within the framework of the Chartered Institute of Public Finance and Accountancy’s Treasury Management in the Public Services: Code of Practice 2021 Edition (the Treasury Management Code) which requires the Council to approve a Treasury Management Strategy before the start of each financial year. This report fulfils the Authority’s legal obligation under the Local Government Act 2003 to have regard to the CIPFA Code.

Recommendations

It is recommended that the Executive Board:

2.1Approves the proposed Treasury Management Strategy for 2025/26, detailed in Appendix 1, including the proposed Treasury Management Indicators.

Background

3.1Treasury management is the management of the Council’s cash flows, borrowing and investments, and the associated risks. The Council borrows and invests substantial sums of money and is therefore exposed to financial risks including the loss of invested funds and the revenue effect of changing interest rates. The successful identification, monitoring and control of financial risk are therefore central to the Council’s prudent financial management.

3.2Investments held for service purposes or for commercial profit are considered in the Capital Strategy report, approved by Finance Council in February 2025.

EBD: V1/16 Page 1 of 3 4. RATIONALE

The Council is required to approve a Treasury Management Strategy before the start of each financial year. It must also set Treasury and Prudential Indicators and a policy for determining a “prudent” level of Minimum Revenue Provision for repayment of debt, which is consistent with the Council’s Medium Term Financial Plan (MTFP).

5. KEY ISSUES

Working within the regulatory and professional frameworks, the Council considers and agrees an annual Treasury Management Strategy before the start of each year. This is followed up with a mid- year Strategy Review, considered alongside the Annual Outturn Report, summarising the position for the previous financial year. The key requirements for the Council are to maintain its two investment priorities, the security of capital and the liquidity of investments.

6. POLICY IMPLICATIONS

The policy implications arising from the Treasury Management Strategy are contained within the overall Budget Strategy of the Council.

Financial implications

The financial implications arising from the Treasury Management Strategy are also contained within the overall Budget Strategy of the Council.

Under the Local Government Act 2003, the Council is required to have regard to CIPFA’s Treasury Management in the Public Services: Code of Practice and Cross-Sectoral Guidance Notes.

9. RESOURCE IMPLICATIONS

None as a direct consequence of this report.

10. EQUALITY AND HEALTH IMPLICATIONS Please select one of the options below. Where appropriate please include the hyperlink to the EIA.

Option 1 Equality Impact Assessment (EIA) not required – the EIA checklist has been completed.

Option 2 In determining this matter the Executive Member needs to consider the EIA associated with this item in advance of making the decision.

Option 3 In determining this matter the Executive Board Members need to consider the EIA associated with this item in advance of making the decision. EBD: V1/16 Page 2 of 3 11. CONSULTATIONS

The issues raised in this report have been discussed previously with the Audit and Governance Committee and Treasury Management Group.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Treasury Management Strategy 2025/26Report 141 KB DownloadRead as text
PDF
Treasury Management Strategy 202526 AppendixAppendix 311 KB Download

At this meeting

Whole meeting

Who was there

9 of 15 attended
MD
Councillor Mustafa DesaiCommittee Member, present
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnCommittee Member, present
MH
Councillor Mahfooz HussainCommittee Member, present
MK
Martin KellyOfficer, expected
AL
Asad LaherOfficer, expected
DL
Dean LangtonOfficer, expected
QM
Councillor Quesir MahmoodCommittee Member, present
VE
Councillor Vicky Ellen McGurkCommittee Member, present
DP
Denise ParkOfficer, expected
PR
Councillor Phil RileyChair, present
SR
Simon RossOfficer, expected

All 15 on the meeting page

On this subject at Blackburn with Darwen

Search all
  1. Treasury Management Strategy 2025/26This decision
  2. EB Corporate Treasury Management Outturn Report 2025/26Noted
  3. Treasury Management Annual Report 2025/26Noted
  4. EB Treasury Management Strategy 2026/27Approved
  5. Treasury Management Report - 1st April to 31st December 2025Noted
  6. Treasury Management Annual Report 2024/25Noted

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies