Resolved
That the Executive Member: 1. Noted Darwen Resource Centre was confirmed surplus by the Asset Management Group in June 2024 following a review of Council assets in 2023/24 which was agreed by Finance Council in February 2024. 2. Noted a joint Council and NHS service currently operates from Darwen Resource Centre and following agreement with stakeholders will now relocate to Darwen Town Hall. 3. Noted the existing capital allocation of £150,000 for the project which was agreed by the Executive Member for Growth & Development in September 2024. 4. Approved an additional capital allocation of £200,000 to cover additional work now required following detailed design and approved the funds to be drawn down from the Development Investment Fund with all the capital expended over financial year 2025/26. 5. Approved the appointment of Thomas Kershaw Builders Limited, following a competitive tender, for the building refurbishment work with a tender sum of £269,701 (+VAT) and excluding contingency provision.