Darwen Market and Civic Quarter Development - Appointment of Contractor

Noted Executive 1 paper

AI summaryBlackburn with Darwen Executive Board appoints Barnfield Construction as main contractor for the Darwen Market and Civic Quarter project, starting a six to eight month pre-construction phase within a £20M budget.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBarnfield Construction named main contractor on a two-stage basis
MoneyUp to £12.5M council co-investmentTotal project budget c.£20M, PCSA fee £104,025
What happens nextPre-construction services agreementJanuary 2026 for 6-8 months, then further Executive Board report
Who it affectsDarwen Market Hall and Civic QuarterIncludes Market Hall, car park, library and theatre upgrades

What was decided

The Executive Board appointed Barnfield Construction as the main contractor for the Darwen Market and Civic Quarter Project on a two-stage basis, following procurement via the Council's Growth and Development Framework. Report P5, 4.5

The Board noted that the appointment would initially proceed via a Pre-Construction Services Agreement (PCSA) to develop a RIBA 4 staged design within the £20M public funding envelope. Report P6

The Strategic Director of Growth and Development and the Acting Director of Finance and Resources were given delegated authority, with the Leader of the Council and the Executive Member for Finance and Governance, to develop the scheme and finalise funding contributions, subject to further Executive Board approval. Report P9

Why

Only one compliant bid was received after an 8-week tender process, from Barnfield Construction, which was assessed against quality and price criteria (60/40 split) and deemed compliant. Report 3.7, 4.2, 4.3

A two-stage contractual arrangement was adopted to mitigate cost and technical risks on this large, complex project, in line with industry standards for high-value schemes facing inflationary and global risks. Report 3.4, 7.4

The project supports the Council's Corporate Plan, Local Plan and Growth Strategy, and is central to delivering the Darwen Town Deal Investment Programme, where the Council is the lead partner and accountable body. Report 5.1, P43

What happens next

The PCSA period will begin in January 2026, lasting 6-8 months, with mobilisation and on-site works expected to start in Autumn 2026. Report 4.6

A further Executive Board report will be presented before mobilisation, seeking approval of the final development strategy and the drawdown of Town Deal and Council capital funding contributions, expected by Autumn 2026. Report 3.9, 6.4, 4.6

A social value delivery plan will be developed with the contractor during the PCSA period and reported to the Executive Board before construction commences. Report 4.4

The money

  • £104,025 Contractor's fee for the PCSA period, covering design development, further surveys and third-party fees Report 6.1
  • c.£20M Total project budget, inclusive of all design fees, further investigations and construction Report 6.2
  • up to £12.5M Council's committed capital funding co-investment in the Darwen Town Investment Plan Report 6.2

Options considered

  • Chosen: Two-stage contractual arrangement with a single compliant bidder (Barnfield Construction). Tenderers' feedback identified cost and technical risks; two-stage approach is the development industry standard for high-value, potentially high-risk projects under current economic conditions Report 3.4, 3.7, 7.4
  • Chosen: Soft market testing via the Council's Growth and Development Framework, earlier in 2025, with three interested main contractors. Feedback from this engagement informed the procurement strategy and the decision to adopt a two-stage approach Report 3.4

Implications

  • Financial: A final contract sum will be agreed during the PCSA period; a full financial assessment is not yet possible and VAT recovery implications are still being assessed through a Council VAT Planning Strategy. Report 6.1, 6.3
  • Legal: Procurement was run via mini-competition on the approved Growth and Development Framework, compliant with the Public Contracts Regulations 2015 and the Council's Contract and Procurement Procedures Rules; the contract will use JCT Standard Building Contract without Quantities, 2024 edition, with external construction law advice engaged. Report 7.1, 7.2, 7.3
  • Risk: Inflationary pressures, global risks, and the scale and complexity of the scheme informed the two-stage procurement approach to mitigate cost and technical risks. Report 3.4
  • Equalities: An Equality Impact Assessment checklist has been completed and the recommendations are stated to be compliant with equality legislation. Report P39, P45
  • Other: Market traders are being kept informed of emerging proposals and timelines, and additional expertise has been appointed to support market operations, including temporary relocation during works; a future operating model is also being developed. Report 3.8

Who and where

  • Market traders at Darwen Market, who will experience temporary relocation when works are underway Report 3.8
  • Users of Darwen Library and Darwen Library Theatre, which are subject to major upgrades Report 3.2
  • Residents, communities and businesses in Darwen, identified as beneficiaries of the Town Centre improvements Report P43
  • The Council in its role as Accountable Body for the Darwen Town Deal, providing strategic, programme and financial management Report P8

Timeline

  • 1st October 2025: Tender documents issued via the Chest e-tendering portal to the Growth and Development Framework Report 4.1
  • 26th November 2025: One tender returned by Barnfield Construction, assessed and deemed compliant Report 4.3
  • January 2026: PCSA period begins, lasting 6-8 months Report 4.6
  • By Autumn 2026: Further Executive Board report expected before mobilisation, covering final financial implications, delivery strategy and funding drawdown Report 6.4, 4.6
  • Autumn 2026: Mobilisation and on-site works planned to begin Report 4.6
  • 8 January 2026: Executive Board decision to appoint Barnfield Construction as main contractor

Plain English for the jargon

  • PCSA (Pre-Construction Services Agreement): An initial contract under which the contractor works with the design team on surveys, design development and cost advice before main construction works are agreed.
  • RIBA 4: Stage 4 of the Royal Institute of British Architects' Plan of Work, covering technical design, before detailed design and construction.
  • Growth and Development Framework: The Council's approved procurement framework used to run a mini-competition for this main contractor appointment.
  • JCT Standard Building Contract without Quantities, 2024 edition: A standard form of building contract published by the Joint Contracts Tribunal, used for construction projects where a bill of quantities is not provided.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item145

Resolved

RESOLVED (1) That the progress made on delivering the Darwen Town Deal Investment Programme and the Darwen Town Board’s role in overseeing progress of its delivery be noted. (2) That following a robust procurement process undertaken via the Council’s Growth and Development Framework, the appointment of Barnfield Construction as the main contractor on the Darwen Market and Civic Quarter Project on a two-stage basis be agreed, as set out in the report. (3) That it be noted that the procurement process would initially be via a Pre-Construction Services Agreement (PCSA) which sets out expectations on working with the Council’s procured Principle Designer and design team to develop the Pre-Construction Information needed to deliver a RIBA 4 staged designed scheme within the available public funding envelope of £20M. (4) That it be noted that, once the Darwen Market and Civic Quarter scheme details were finalised and prior to mobilisation and start on site, a further Executive Board report would be submitted to consider and approve the delivery strategy and to seek approval to draw down funding from the Town Deal Investment Programme, and the Council’s agreed capital funding contribution. (5) That the role of the Council, as an Accountable Body for the Darwen Town Deal; the Council’s commitment to co-invest up to £12.5M in capital funding support for the Town Deal Investment Programme; and the key role the Council performs, as an Accountable Body, and in continuing to provide strategic advice, and programme and financial management to support the Board and the delivery of the Investment Programme, be noted. (6) That the Strategic Director of Growth and Development and the Acting Director of Finance and Resources be granted delegated authority, in conjunction with the Leader of the Council and the Executive Member for Finance and Governance, to develop this scheme and finalise the capital funding contribution from the Darwen Town Deal and Council, subject to further Executive Board approval.
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Executive Board

Executive summary

The report provides an update on the Darwen Town Deal Investment Programme, including the transformational Market Hall and Civic Quarter development project. The Council is the lead partner, co-investor, and accountable body for the Darwen Town Deal. The primary purpose of this report is to seek Council approval to progress the procurement of a main contractor to deliver this strategic development scheme.

The report also sets out the Council’s procurement approach, including the 2-stage contractual arrangements, and details of the successful bidder, selected via the Council’s approved Growth and Developer Framework. To this end, the report seeks approval to appoint the proposed main contractor, Barnfield Construction, and progress the scheme design and delivery, as set out in this report, in what is a major milestone for the Darwen Town Deal Investment Programme.

Recommendations

The Executive Board is asked to:

1. Note the progress made on delivering the Darwen Town Deal Investment Programme and the Darwen Town Board’s role in overseeing progress of its delivery.

2. Following a robust procurement process via the Council’s Growth and Development Framework, agree to appoint Barnfield Construction as the main contractor on the Darwen Market and Civic Quarter Project on a two-stage basis, as set out in this report.

3. Note that initially this would be via a Pre-Construction Services Agreement (PCSA), which sets out expectations on working with the Council’s procured Principal Designer and design team to develop the Pre-Construction Information needed to deliver a deliverable RIBA 4 staged designed scheme within the available public funding envelope of £20M.

4. Note that once the Darwen Market and Civic Quarter scheme details are finalised, prior to mobilisation and start on site, a further Executive Board report will be submitted to consider and EBD: V3/23 Page 1 of 6 approve the delivery strategy and to seek approval to drawdown funding from the Town Deal Investment Programme, and the Council’s agreed capital funding contribution.

5. Note the role of the Council, as accountable body for the Darwen Town Deal; the Council’s commitment to co-invest up to £12.5M in capital funding support for the Town Deal Investment Programme; and the key role the Council performs, as accountable body, and in continuing to provide strategic advice, and programme and financial management to support to the Board and the delivery of the Investment Programme.

6. Delegate responsibility to the Strategic Director of Growth & Development and the Acting Director of Finance and Resources, in conjunction with the Leader of the Council and the Executive Member for Finance and Governance, to develop this scheme and finalise the capital funding contribution from the Darwen Town Deal and Council, subject to further Executive Board approval.

Background

3.1Following the Darwen Town Deal Update in February 2025 to Executive Board on progress with all projects within the agreed Investment Programme, there has been a strong focus on developing the design, procurement and delivery strategy of the Darwen Market & Civic Quarter Development.

3.2This project is the largest and most complex Town Deal project with its key focus on the re- development of the Market Hall, and replacement of the Market car park, linked to major upgrades of Darwen Library and Theatre (and both have Planning and Listed Building consent). Works will also improve connected public realm and key gateways as available funding allows.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Darwen Market and Civic Quarter Development: Appointment of ContractorReport 154 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

17 of 19 attended
MD
Councillor Mustafa DesaiCommittee Member, present
JF
Councillor Jackie FloydCommittee Member, present
JL
Councillor Julie Louise GunnOfficer, present
SH
Councillor Shaukat HussainCommittee Member, present
MK
Martin KellyOfficer, present
AL
Asad LaherOfficer, present
DL
Dean LangtonOfficer, expected
QM
Councillor Quesir MahmoodCommittee Member, present
NM
Nafisha MasterSecretary, present
VE
Councillor Vicky Ellen McGurkCommittee Member, present
ZM
Zahra MusaSecretary, present
DP
Denise ParkOfficer, present

All 19 on the meeting page

More from Blackburn with Darwen Executive Board

All decisions
MeetingDecisionOutcome
10 Sep 2026 Minutes of the Previous MeetingRESOLVED That the minutes of the last meeting held on Thursday, 13 August 2026 be agreed as a correct record for sign... Agreed Open
10 Sep 2026 Corporate Plan Performance, Quarter 1 2026/271) That the Quarter 1 performance against the delivery of the Council’s Corporate Plan Missions, as attached as Appen... Noted Open
10 Sep 2026 Children and Young People's Plan 2026 - 20281) That the Children and Young People’s Plan 2026-2028, which had been formally signed off by the Children’s Partners... Noted Open
10 Sep 2026 Variation to existing schools capital programme - Newfield Satellite Site1) That the requirement for a significant increase in the capital budget for the proposed Newfield School satellite s... Noted Open
10 Sep 2026 Enhancement of the Free Bulky Waste Collection Service1) That that introduction of a newly developed online access system to facilitate a full end to end self-serve option... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies