Audit & Assurance - Progress & Outcomes to May 2026

Approved Finance 1 paper

AI summaryBlackburn with Darwen Audit & Governance Committee reviewed internal audit outcomes to 31 May 2026 and approved the proposed approach for an external assessment of Internal Audit against GIASUKPS standards.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedInternal audit outcomes discussed; external assessment approach approved
Money£65,591.48Total NFI 2024/25 errors, outcome, estimate and savings combined
What happens nextOngoing audits continueFifteen internal audit reviews in progress at period end
Who it affectsAll portfolios and wardsCouncil-wide internal audit and counter fraud activity

What was decided

Members discussed, reviewed and challenged the internal audit outcomes achieved to 31 March 2026 against the annual Audit and Assurance Plan 2025/26, approved by the Committee on 24 March 2026. Report P7

Members considered and approved the proposed approach for the external assessment of Internal Audit against the requirements of the Global Internal Audit Standards in the UK Public Sector (GIASUKPS). Report P7

Why

The Council is required under the Accounts and Audit (England) Regulations 2015 to undertake an effective internal audit, taking into account the GIASUKPS, and the Head of Internal Audit must communicate any significant governance, risk management or control issues to the Audit Committee during the year. Report P7

Internal audit work completed to date has not identified any significant governance, risk management or control issues to bring to the Committee's attention at this time. Report P7

What happens next

Fifteen internal audit reviews were ongoing at the period end, covering areas including Public Protection Inspection Arrangements, Equal Pay Arrangements, Highways Asset Management, Payroll Core System, Personalised Budgets and Creditors. Report P24

The Audit and Assurance team will continue to monitor the seven performance targets against its strategic aims, with attention to the two measures currently below target. Report P24, P25, P26

The money

  • 10,122.28 NFI 2024/25 total outcomes recovered or in process of recovery by departments Report P8
  • 55,469.20 NFI 2024/25 Cabinet Office estimated forward savings from errors identified Report P8
  • 65,591.48 NFI 2024/25 combined total of outcomes and estimated savings Report P8
  • 26,202.00 Estimated savings from Blue Badge and Parking Permit errors Report P8
  • 15,922.00 Estimated savings from Concessionary Travel Pass errors Report P8
  • 23,467.48 NFI 2024/25 outcomes and estimates for Housing Benefit matches Report P8
  • £794 Cabinet Office average loss from fraud or error per Blue Badge case Report P10
  • £38 Cabinet Office average loss from fraud or error per Concessionary Travel Pass case Report P10

Options considered

  • Chosen: Discuss, review and challenge internal audit outcomes to 31 May 2026 against the approved 2025/26 Plan. Statutory requirement to consider internal audit work and report any significant governance, risk or control issues to the Committee Report P7
  • Chosen: Approve the proposed approach for the external assessment of Internal Audit against GIASUKPS. GIASUKPS compliance requires an external assessment of the internal audit function Report P7

Implications

  • Financial: There are no financial implications arising as a result of this report. Report P27
  • Legal: There are no legal implications arising as a result of this report. Report P28
  • Staffing: Performance measure 2 (Planned Audits Completed Within Budget) was at 40% in Q4 2025/26 against a 90% target, partly linked to the issuing of one final report being delayed due to staff absence. Report P24, P25
  • Risk: Nine of 62 recommendations due in the period had not been implemented; two were categorised as 'Must' and related to a school audit, with one still being resolved with the software supplier and the other delayed by the timing of the relevant Governors meeting. Report P26
  • Equalities: There are no equality or health implications arising as a result of this report, and an equality analysis and impact assessment has been considered. Report P30, P31
  • Other: Five 'red' priority areas were reported by departments as at 31 March 2026: Tree Management; End to End Fostering (new); Budget and Demand Pressures in the Children's Services Portfolio; School Deficits; and High Needs Deficits. Three previously 'red' areas were downgraded to 'amber'. Report P13, P15, P16, P17, P18, P19, P20, P21

Who and where

  • All council portfolios and wards, as the internal audit function covers the whole authority Report P4, P5
  • Children & Education department, with multiple red-rated areas including fostering, school deficits, high needs deficits and ongoing budget pressures Report P15, P16, P17, P20, P21
  • Environment & Communities department, with Tree Management flagged as a continuing red priority Report P15
  • Council Tax payers and benefit claimants covered by the National Fraud Initiative data matching Report P8, P10
  • Salford City Council, which provided technical audit support for the IT software patch management review Report P23

Timeline

  • Early January 2025: NFI 2024/25 matches released to the Council by the Cabinet Office Report P7
  • 30 September 2025: Previous half-year review date used for comparison of red priorities Report P13
  • 28 February 2026 to 31 May 2026: Reporting period covered by this Progress and Outcomes report Report P7
  • 24 March 2026: Audit and Assurance Plan 2025/26 approved by the Audit & Governance Committee Report P7, P33
  • 31 March 2026: Date of the summary Director Exception/Dashboard Report and Assurance Statements used for the red priority review Report P12
  • 12 June 2026: Report dated by Colin Ferguson, Head of Audit & Assurance Report P33
  • 23 June 2026: Meeting date of the Audit & Governance Committee Report P3

Plain English for the jargon

  • GIASUKPS: Global Internal Audit Standards in the UK Public Sector, the standards the internal audit function must comply with.
  • NFI: National Fraud Initiative, a biannual data matching exercise run by the Cabinet Office to help prevent and detect fraud.
  • CO: Cabinet Office, which runs the National Fraud Initiative and provides estimated savings values for matched errors.
  • SPD: Single Person Discount, a Council Tax discount which is subject to NFI data matching.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That members discussed, reviewed and challenged the internal audit outcomes achieved to 31 March 2026 against the annual Audit and Assurance Plan 2025/26, as approved by the Committee on 24 March 2026. 2. That members considered and approved the proposed approach for the external assessment of Internal Audit against requirements of the Global Internal Audit Standards in the UK Public Sector (GIASUKPS).
Word for word from the decision Blackburn with Darwen published for this meeting. Source: democracy.blackburn.gov.uk

Follow this further

Built from Blackburn with Darwen's papers

What the report saysPro

Report to Audit & Governance Committee

TO: Audit & Governance Committee

FROM: Head of Audit & Assurance

DATE: 23 June 2026

PORTFOLIOS AFFECTED: All

WARDS AFFECTED: All

TITLE OF REPORT: Audit & Assurance - Progress and Outcomes to 31 May 2026

1. PURPOSE 1.1. To inform Committee Members of the achievements and progress made by Audit & Assurance in the period from 28 February 2026 to 31 May 2026. 2. RECOMMENDATIONS The Committee is asked to: • discuss, review and challenge the internal audit outcomes achieved to 31 May 2026 against the annual Audit & Assurance Plan 2025/26, as approved by the Committee on 24 March 2026. • consider and approve the proposed approach for the external assessment of Internal Audit against requirements of the Global Internal Audit Standards in the UK Public Sector (GIASUKPS). 3. BACKGROUND The internal audit function is required to comply with the GIASUKPS. The GIASUKPS require the Head of Internal Audit to communicate any significant governance, risk management and control issues identified to the Audit Committee during the year. This Progress and Outcomes report complies with these requirements by communicating any significant issues identified by the internal audit team during the year. 4. RATIONALE The Council is required under the Accounts and Audit (England) Regulations 2015 to undertake an effective internal audit to evaluate the effectiveness of risk management, control and governance processes, taking into account the GIASUKPS. The work undertaken throughout the year is intended to ensure that: • an objective and independent opinion can be provided at the year-end which meets the GIASUKPS and statutory governance requirements; • it demonstrates the effectiveness of the internal audit function; and • support is provided to Members, Directors and managers for their particular areas of responsibility throughout the year. The internal audit work completed to date has not identified any significant governance, risk management or control issues to bring to the Committee’s attention at this time. However, the Committee should consider the information provided in the following sections regarding the work carried out during the period. 5. KEY ISSUES Outcomes achieved in the year to 31 May 2026: Counter Fraud Activity National Fraud Initiative (NFI) 2024/25 The Council takes part in a biannual data matching exercise conducted by the Cabinet Office (CO) to assist in the prevention and detection of fraud. The exercise includes data provided by public and private sector organisations, including government departments. The 2024/25 matches were released to the Council in early January 2025. The table below details the categories of matches received and work undertaken on the 2024/25 matching process to date.

CO Total Matches Processed Errors Outcome Estimate Saving Housing Benefit 42 42 - - - - Council Tax Reduction 938 632 21 10,122.28 13,345.20 23,467.48 Payroll 115 92 - - - - Blue Badge PP's 186 186 33 - 26,202.00 26,202.00 Concessionary Travel Passes 491 491 419 - 15,922.00 15,922.00 Residential Permits 5 5 - - - - Creditors 5,123 4,956 - - - - Care Home Residents 18 18 - - - - Procurement 44 2 - - - - Waiting Lists 234 2 - - - - 7,196 6,426 473 10,122.28 55,469.20 65,591.48

The outcome value is the amount that has been recovered/is in process of being recovered by the relevant department. The Cabinet Office (CO) Estimate is the estimated forward savings made calculated as a result of the errors being identified and corrected as part of this matching process.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit & Assurance: Progress & Outcomes to May 2026Agenda 153 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

3 of 11 attended
JS
Jody Spencer-AnforthCouncil Staff, in attendance
CF
Colin FergusonOfficer, in attendance
DP
Denise ParkOfficer, expected
CF
Charlotte FrazerSecretary, expected
WH
Councillor Waqar HussainCommittee Member, present
MJ
Councillor Matthew JacksonCommittee Member, apologies
LJ
Councillor Liz JohnsonChair, present
AM
Councillor Andy MahonCommittee Member, apologies
MP
Councillor Mohmed PatelCommittee Member, present
AS
Councillor Anthony ShawCommittee Member, apologies
KK
Kaeleigh KnottOfficer, in attendance

On this subject at Blackburn with Darwen

Search all
  1. Audit & Assurance - Progress & Outcomes to May 2026This decision
  2. Audit & Assurance - Progress & Outcomes - 1st November 2025 to 31 January 2026Noted
  3. Audit & Assurance - Progress & Outcomes to May 2025Noted
  4. Audit & Assurance - Progress & Outcomes to February 2025Approved
  5. Audit & Assurance - Internal Audit Mandate and Charter, Internal Audit Strategy, Three Year Strategic Plan and 2025/26 PlanApproved
  6. Audit & Assurance - Progress & Outcomes to January 2025Noted

More from Blackburn with Darwen Audit & Governance Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 Minutes of previous meeting held on 24th March 2026That the minutes of the meeting held on Tuesday, 24 March 2026 be approved as a correct record and signed by the Chair. Approved Open
23 Jun 2026 Significant Partnerships Register 2025/26That the report be noted. 2. That committee reviewed the Significant Partnerships Register (SPR) Noted Open
23 Jun 2026 Annual Report on Health & Safety 2025/26That the report be deferred to the next meeting as the reporting Officer was not present at the committee meeting. Deferred Open
23 Jun 2026 Treasury Management Annual Report 2025/26That the report be noted. Noted Open
23 Jun 2026 Risk Management Annual Report 2025/26That members considered and reviewed the annual risk management report. 2. That members agreed the conclusion on the ... Agreed Open