The Executive resolved as follows: To agree that Appendix 5a, to the Executive report, Financial estimates is not for publication by virtue of Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972 To agree to the further development of the Madame Tussauds by the creation of a Television Themed attraction in the identified underutilised space. To complete the delivery of the scheme as set out in this report, to include the completion of all due diligence associated with the project. To complete the project funding package through debt finance in the form of Prudential Borrowing, as detailed in Appendix 5a to this report. To agree in principle to the creation of an addendum to the existing Madame Tussauds operating agreement and that the Head of Legal be granted delegated authority to authorise the addendum and any other legal agreements on behalf of the Council.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
1.1To agree to the further development of the Madame Tussauds attraction as set out in this report and to seek authority allowing progress of the scheme to completion.
1.2To request authority to complete the project funding package through debt finance in the form of Prudential Borrowing as detailed in the financial appendices to this report.
2.0Recommendation(s):
2.1To agree to the further development of the Madame Tussauds by the creation of a Television Themed attraction in the identified underutilised space.
2.2To complete the delivery of the scheme as set out in this report, to include the completion of all due diligence associated with the project.
2.3To complete the project funding package through debt finance in the form of Prudential Borrowing, as detailed in Appendix 5a to this report.
2.4To agree in principle to the creation of an addendum to the existing Madame Tussauds operating agreement and that the Head of Legal be granted delegated authority to authorise the addendum and any other legal agreements on behalf of the Council.
3.0Reasons for recommendation(s):
3.1To enhance the Existing Madame Tussauds attraction and therefore further improve the economically important tourism sector, significantly contributing toward attaining the Council’s vision of Blackpool being the UK’s number one family resort with a thriving economy that supports a happy and healthy community who are proud of this unique town.
3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?
3.2b Is the recommendation in accordance with the Council’s approved Yes budget?
3.3Other alternative options to be considered:
Do nothing. The area of the building proposed for redevelopment does not currently align fully with the vision of the Council for Blackpool, of being the UK’s number one family resort with a thriving economy that supports a happy and healthy community who are proud of this unique town.
4.0Council Priority:
4.1The relevant Council Priority is: “The economy: Maximising growth and opportunity across Blackpool”.
5.0Background Information
5.1It has been identified that an area of underutilised space exists within the Council owned building occupied by the Madame Tussauds attraction.
5.2An analysis of the optimal use of this space has revealed the opportunity for a Television Themed attraction linked directly to the existing Madame Tussauds experience.
5.3Should authority to proceed be granted, the venture would be operated by Merlin Entertainments (Blackpool) Limited. The attraction will contain interactive elements including photograph opportunities and other activities along with merchandise, and follow the business model associated with the existing, highly successful, Madame Tussauds attraction.
5.4An addendum to the existing Madame Tussauds operating agreement would be put in place and this governance arrangement offers the benefit of sharing economies of scale with the existing attraction whilst providing assurance with regard to the quality of the product. 5.5 It is planned the new experience will open for the 2020/21 summer season with development work to the unit and attraction contents to commence in January 2020 should authority to proceed be provided. The timing of the investment is critical in order to allow the new attraction to open and trade for May 2020.
5.6The authority sought through this report will allow completion of the project as set out at 5.1 to 5.5 above, in addition to assembling the associated debt financing in the form of Prudential Borrowing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.