The Executive resolved as follows: To agree that Appendix 5a, to the Executive report, summary of offers received for Ryscar Way is not for publication by virtue of Paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972. To approve the disposal to Bidder A for land at Ryscar Way Blackpool and delegate contractual matters to the Director of Communication and Regeneration, subject to the completion of an appraisal as to the feasibility of the development of the land for social housing by one of the Council’s wholly owned companies. To delegate authority for the use of land at Bispham Road Blackpool to the Director of Communications and Regeneration, after consultation with the Cabinet Member for Business Enterprise and Job Creation and the Cabinet Member for Housing and Welfare reform and subject to the completion of an appraisal as to the feasibility of development of the land for social housing by one of the Council’s wholly owned companies. To delegate authority for the disposal of land at Blackpool Road, Poulton le Fylde to the Director of Communications and Regeneration, after consultation with the Cabinet Member for Business Enterprise and Job Creation. To delegate to the Director of Communications and Regeneration to make any payments as necessary to the developers or for infrastructure works from the ring fenced grant funding received from the One Public Estate programme for the use on these three sites only. To authorise the Head of Legal Services to prepare legal documentation and enter into appropriate documents as necessary to complete any transactions .
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Notice of: EXECUTIVE Decision Number: EX18/2020 Relevant Officer: Alan Cavill, Director of Communications and Regeneration Relevant Cabinet Member: Councillor Mark Smith, Cabinet Member for Business Enterprise and Job Creation Date of Meeting: 23 March 2020
RELEASE OF LAND FOR RESIDENTIAL DEVELOPMENT 1.0 Purpose of the report:
1.1To consider the disposal of land at Ryscar Way and Bispham Road in Blackpool and Blackpool Road in Poulton le Fylde.
2.0Recommendation(s):
2.1To approve the disposal to Bidder A for land at Ryscar Way Blackpool and delegate contractual matters to the Director of Communication and Regeneration.
2.2To delegate authority for the use of land at Bispham Road Blackpool to the Director of Communications and Regeneration, after consultation with the Cabinet Member for Business Enterprise and Job Creation and the Cabinet Member for Housing and Welfare reform.
2.3To delegate authority for the disposal of land at Blackpool Road, Poulton le Fylde to the Director of Communications and Regeneration, after consultation with the Cabinet Member for Business Enterprise and Job Creation.
2.4To delegate to the Director of Communications and Regeneration to make any payments as necessary to the developers or for infrastructure works from the ring fenced grant funding received from the One Public Estate programme for the use on these three sites only.
2.5To authorise the Head of Legal Services to prepare legal documentation and enter into appropriate documents as necessary to complete any transactions. 3.0 Reasons for recommendation(s):
3.1The sale of land to Bidder A follows a marketing exercise where the site was marketed on two separate occasions directly to house builders and their offer was the only unconditional offer and highest scoring, this is outlined in Appendix 5a, to the Executive report (exempt from publication).
The sites at Blackpool Road and Bispham Road have not yet achieved planning consent albeit this is in process and marketing has begun. As the One Public Estate programme is monitored and milestones need to be achieved as a condition of the grant funding, delegation will ensure those timescales are met. Originally all three sites had to be released by 31 March 2020 and an extension to this timescale has been agreed. The delegation provides added comfort to Ministry for Housing, Communities and Local Government, Cabinet Office and Local Government Association that the grant funding provided will be spent and the land to be released or use agreed for all sites by September 2020.
3.2a Is the recommendation contrary to a plan or strategy adopted or No approved by the Council?
3.2b Is the recommendation in accordance with the Council’s approved Yes budget?
3.3Other alternative options to be considered:
To approve the Ryscar Way disposal and not delegate the Bispham Road and Blackpool Road delegations although this could put at risk the grant funding received if the milestones are not met.
4.0Council Priority:
4.1The relevant Council Priority is: “The economy: Maximising growth and opportunity across Blackpool”.
5.0Background Information
5.1The Council applied for grant funding under the Land Release Fund One Public Estate Programme (LRFOPE) in October 2017 and submitted the three sites for consideration. In February 2018 the Ministry of Housing Communities and Local Government confirmed to the Council it had been successful in applying for £3.15m of grant funding to bring forward the three sites for new homes.
5.2Following receipt of the grant funding the Council’s Growth and Prosperity team has undertaken extensive surveys and drawings and submitted outline planning application for all three of the sites. Ryscar Way achieved outline planning consent in July 2019 and the sites at Bispham Road and Blackpool Road where the planning applications are still progressing.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.