TRAMWAY WORKS- PRUDENTIAL BORROWING

Agreed Executive 2 papers

Executive agreed this item on Monday 22 March 2021. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The Executive agreed the recommendation as outlined above namely: To approve Prudential Borrowing up to £900,000 to fund the capital works to the tramway, as outlined in paragraph 6.6, to be repayable up to five years.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive, 5 pages

Notice of: EXECUTIVE Decision Number: EX18/2021

Relevant Officer: John Blackledge, Director of Community and Environmental Services

Relevant Cabinet Member: Councillor Jim Hobson, Cabinet Member for Climate Change and Environment

Date of Meeting: 22 March 2021

TRAMWAY WORKS PRUDENTIAL BORROWING 1.0 Purpose of the report:

1.1To consider whether to fund essential tramway works through Prudential Borrowing.

2.0Recommendation(s):

2.1To approve Prudential Borrowing up to £900,000 to fund the capital works to the tramway, as outlined in paragraph 6.6, to be repayable up to five years.

3.0Reasons for recommendation(s):

3.1The tramway is a vital economic asset for Blackpool and Lancashire, which was used by 4.8 million passengers in 2019/20. Its state of the art Bombardier Flexi 2 trams are a plus for Blackpool and Lancashire County Council together with the heritage vehicles still in use and maintain the tramway as a Lancashire, Blackpool and Fylde Coast icon. In order to ensure that the tramway system continues to operate and to extend its operational life, works are required beyond that undertaken during day to day maintenance.

3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council?

3.3Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered:

4.1To not carry out the works could ultimately lead to the closure of the tramway. 5.0 Council priority:

5.1The relevant Council priority is: “The economy: Maximising growth and opportunity across Blackpool”.

6.0Background information

6.1The tramway service is a vital economic asset to Blackpool and Lancashire County Council who jointly have achieved significant investment not only in the line, but also in the trams themselves; Bombardier Flexi 2 Trams.

6.2The tramway is operated by Blackpool Transport Services along 11 miles of coastline from Squires Gate in Blackpool to Fleetwood. In 2019/20 financial year 4.8m residents and visitors to the Fylde Coast used the service.

6.3The track is maintained daily by Blackpool Council in conjunction and partnership with Lancashire County Council (LCC), jointly funding the maintenance requirement based on the percentage of track in Blackpool and Lancashire.

6.4A recent commissioned track survey highlighted a number of areas of work that need to be undertaken in the short to medium term to ensure the tramway can continue to operate to the required standards. Given the specialist nature of the works and the limited number of contractors able to undertake these works, the most cost effective way is to procure a suitable contractor(s) to undertake all the works one scheme to minimise track disruption and gain economies of scale in procuring the works. Following completion of the work, this would ensure the continued safe operation of the track and service.

6.5The works required which would add to the value of the asset and extend its life include rail replacement and installation of new under run protection, which is now required as a result of new health and safety guidelines at crossing points on the track by the Light Rail Safety Standards Board. This would be outdated by the Office of Rail and Road in the future to ensure compliance.

6.6The total cost of these works is £1.1m, which Blackpool and Lancashire County Council have identified an amount of additional annual funding over the next five years to pay for this. In terms of this, it would be used to pay back the works carried out in 2021/22.

The key areas of work are as follows:

1. Tramping Works £200k 2. Installation of rail and new under run £900k protection units Total £1.1m 6.7 Does the information submitted include any exempt information? No

7.0List of Appendices:

7.1None.

8.0Financial considerations:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
EX18 Tramway Agreement Prudential BorrowingReport 5 pages DownloadRead as text
PDF
TRAMWAY WORKS- PRUDENTIAL BORROWINGReport 5 pages Download

At this meeting

Whole meeting

Who was there

9 of 10 attended
LB
Lennox BeattieSecretary, expected
KB
Councillor Kath BensonCommittee Member, present
NB
Councillor Neal BrookesCommittee Member, present
GC
Councillor Gillian CampbellCommittee Member, present
JF
Councillor Jo FarrellCommittee Member, present
JH
Councillor Jim HobsonCommittee Member, present
MK
Councillor Maria KirklandCommittee Member, present
MS
Councillor Mark SmithCommittee Member, present
IT
Councillor Ivan TaylorVice Chair, present
LW
Councillor Lynn WilliamsChair, present

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies