That planning application 20/0674 is refused for the following reasons: 1. The proposal does not constitute redevelopment to modern business/industrial facilities supporting the Blackpool Business Park/Enterprise Zone. As such it has a detrimental impact on the area’s potential to attract modern, hi-tech industries, due to noise and dust pollution generated on site. The proposal is thereby contrary to Policy CS24 of the Blackpool Local Plan Part 1: Core Strategy 2021-2027 and Policy DE2 of the Blackpool Local Plan 2001-2016. 2. The proposal would have a significant adverse impact on residential amenity in terms of noise (HGV engines, concrete crusher etc) air (dust, diesel fumes) particularly at unsociable times – late evening and early morning. As such the proposal would be contrary to Policy CS7 of the Blackpool Local Plan Part 1: Core Strategy 2012-2027 and Policy BH3 of the Blackpool Local Plan 2001-2016. 3. The proposal would result in off-site pollution of the water environment and ... view the full minutes text for item 9.
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Application ref: 20/0674 Ward: STANLEY Application type: FULL Location: LAND AT SQUIRES GATE INDUSTRIAL ESTATE, SQUIRES GATE LANE Proposal: Use of land as a contractors depot, incorporating land levelling, vehicle storage for up to 67 wagons, staff and customer parking, erection of workshop, concrete batching plant and aggregate bays.
Recommendation: REFUSE Case officer: Pippa Greenway Case officer contact: 01253 476222 Meeting date: 8 June 2021
1.0BLACKPOOL COUNCIL PLAN 2019-2024
1.1The Council Plan sets out two priorities. The first is ‘the economy: maximising growth and opportunity across Blackpool’, and the second is ‘communities: creating stronger communities and increasing resilience.
1.2This application accords with the first priority in that the applicant states that it supports 100+ jobs within the area and Fylde. However it conflicts with the second priority as the proposal impacts significantly on the residential amenities of the local community in terms of noise and disturbance, air pollution and flood risk.
2.0SUMMARY OF RECOMMENDATION
2.1The proposal would compromise the aims of the Enterprise Zone to attract new, modern, hi- tech companies and their staff into the area. It would also exacerbate water pollution and flooding within the area and cause significant issues for local residents with regard to dust/air pollution, continuous noise and disturbance throughout the day, with additional impacts early morning and late night, when the area is quieter. The adverse environmental and social impacts of the proposal are considered to outweigh the economic benefits. As such the proposal does not represent sustainable development and refusal of permission is recommended.
3.0INTRODUCTION
3.1This application is before Members because of the level of public objection and because it is a major scheme of general public interest that is recommended for refusal. 4.0 SITE DESCRIPTION
4.1The site comprises 2.6 hectares of land in the south east corner of Squires Gate Industrial Estate and is bounded by Squires Gate Industrial Estate and Sycamore Trading Estate to the north; the Business Park and Enterprise Zone to the west and south; and by a football ground (AFC Blackpool) and Common Edge playing fields to the east. On the opposite side of the football ground is a residential street – Oakwood Close.
4.2The site either is located within a Main Industrial/Business Area and an Industrial Improvement Zone.
5.0DETAILS OF PROPOSAL
5.1The proposal is use of land as a contractors depot. In the south east section would be a storage bays for aggregates, sand, gravel top soil etc. The aggregate bays are constructed of vertical universal beams (UB’s) set into the ground (max 4m high) with timber sleepers slotted into the webbing between each UB. A typical individual bay is 8m x 12m in size. To the west of this would be a section for the parking of 63 wagons; and occupying the area furthest west would be a crusher, screener and concrete batching plant. The batching plant consists of two silos (maximum height of 11.3m) and hoppers (max height 5.3m), a conveyor belt and a loading area for wagons. In the northern part of the site would be the workshop (20 m x 10 m with a ridge height of 8 m), drivers cabin/canteen, WC’s, site machinery storage area and staff/visitor parking. All access to the site is from the main estate access road at the traffic light controlled junction with Squires Gate Lane; and staff/visitor car parking is segregated from wagon access.
5.2The application has been supported by: Design and Access Statement Ecological Appraisal Arboricultural Constraints Appraisal Flood Risk Assessment Noise and Vibration Assessment Phase 1 Desk Study (contaminated land) Transport Statement External lighting details
6.0RELEVANT PLANNING HISTORY
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.