The Executive agreed the recommendations as outlined above namely: To delegate authority to the Director of Communications and Regeneration, to appropriate for planning purposes the Subject Land under section 122 of the LGA 1972 and conditional on the grant of planning permission subsequently invoke section 203 and section 204 of the Housing and Planning Act 2016. To delegate authority to the Director of Communications and Regeneration to negotiate and enter into legal agreements with third parties in order to secure the modification or release of rights or covenants (and the grant of new rights) (“the Rights) which may otherwise be an impediment to the ‘Enabling Phase’ of the Blackpool Central Site. In the absence of legal agreements being entered into to release the Rights, to delegate authority to the Director of Communications and Regeneration to deal with the settlement of any claims for compensation made pursuant to section 204 of the Housing and Planning Act 2016 that may arise by virtue of the operation of the overriding power contained in Section 203 of the Housing and Planning Act 2016. To authorise the Head of Legal Services to enter into any such documentation as may be necessary to give effect to or flowing from the appropriation for planning purposes of the Subject Land. *
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Relevant Officer: Alan Cavill, Director of Communications and Regeneration Councillor Lynn Williams Leader of the Council and Relevant Cabinet Members: Councillor Ivan Taylor Deputy Leader of the Council
Date of Meeting: 12 July 2021
PROPOSED APPROPRIATION AND DISPOSAL OF LAND AT BLACKPOOL CENTRAL 1.0 Purpose of the report:
1.1To seek approval to appropriate for planning purposes, a parcel of land to the rear of the Former King Edward Apartments within the Blackpool Central Site as shown edged blue and coloured green on the attached plan 1 (“the Subject Land”), pursuant to Section 122 of the Local Government Act 1972 (“LGA 1972”) and conditional upon the grant of the hybrid planning permission with application number 21/0517 to enable the building of a Multi-Storey car park which is the ‘Enabling Phase’ (as illustrated edged green on plan 2) of the Blackpool Central development invoke section 203 and section 204 of the Housing and Planning Act 2016 (“HPA 2016”) .
2.0Recommendation(s):
2.1To delegate authority to the Director of Communications and Regeneration, to appropriate for planning purposes the Subject Land under section 122 of the LGA 1972 and conditional on the grant of planning permission subsequently invoke section 203 and section 204 of the Housing and Planning Act 2016.
2.2To delegate authority to the Director of Communications and Regeneration to negotiate and enter into legal agreements with third parties in order to secure the modification or release of rights or covenants (and the grant of new rights) (“the Rights) which may otherwise be an impediment to the ‘Enabling Phase’ of the Blackpool Central Site.
2.3In the absence of legal agreements being entered into to release the Rights, to delegate authority to the Director of Communications and Regeneration to deal with the settlement of any claims for compensation made pursuant to section 204 of the Housing and Planning Act 2016 that may arise by virtue of the operation of the overriding power contained in Section 203 of the Housing and Planning Act 2016.
2.4To authorise the Head of Legal Services to enter into any such documentation as may be necessary to give effect to or flowing from the appropriation for planning purposes of the Subject Land.
3.0Reasons for recommendation(s):
3.1i) To facilitate the commencement of the major leisure development by removing the Rights over the Subject Land to allow the ‘Enabling Phase’ of the development to commence with the building of the Multi-Storey car park.
ii) The appropriation for planning purposes of the Subject Land is necessary as the programme of works for the ‘Enabling Phase’ means that the Developer requires a safe working space around the ‘Enabling Phase’ prior to the anticipated date of confirmation of the Compulsory Purchase Order (The Blackpool Borough Council (Blackpool Central No1) Compulsory Purchase Order 2021). This safe working space relates to the “Subject Land”.
iii) The engagement of these powers is considered to be proportionate and justified, notwithstanding the interference with the Rights of the leaseholders over the Subject Land which is owned by the Council.
iv) Appropriation for planning purposes of the Subject Land under section 227 of the Town and Country Planning Act 1990 (“TCPA 1990”) and any subsequent use of section 203 and section 204 powers pursuant to the Housing and Planning Act 2016 will enable the development to proceed without the risk of an injunction from adjoining leaseholders and convert the rights into compensation
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council?
3.3Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.