BLACKPOOL COAST PROTECTION SCHEMES - USE OF ENVIRONMENT AGENCY FRAMEWORK FOR SELECTION OF CONTRACTORS AND DESIGNERS

Agreed Executive 2 papers

Executive agreed this item on Monday 5 September 2022. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The Executive agreed the recommendation as outlined above namely: To approve the use of the Environment Agency’s Collaborative Delivery Framework to select the Designers and Contractors for the Blackpool Coast Protection Schemes between 2022 and 2027 and deliver the Coast Protection schemes.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive, 6 pages

Report to: EXECUTIVE Relevant Officer: John Blackledge Director of Community and Environment

Relevant Cabinet Member Councillor Jane Hugo, Cabinet Member for Climate Change and Environment

Date of Meeting 5 September 2022

BLACKPOOL COAST PROTECTION SCHEMES – USE OF ENVIRONMENT AGENCY FRAMEWORK FOR SELECTION OF CONTRACTORS AND DESIGNERS 1.0 Purpose of the report:

1.1To provide the background information to enable the Executive to approve the recommendation to use the Environment Agency’s Collaborative Delivery Framework for the selection of the Designers and Contractors to deliver the Blackpool Coast Protection Schemes.

2.0Recommendation(s):

2.1To approve the use of the Environment Agency’s Collaborative Delivery Framework to select the Designers and Contractors for the Blackpool Coast Protection Schemes between 2022 and 2027 and deliver the Coast Protection schemes.

3.0Reasons for recommendation(s):

3.1The Environment Agency has been through a rigorous procurement process to select Designers and Contractors for their Collaborative Delivery Framework which also allows Local Authorities to utilise the framework for Coast protection and flood risk management schemes.

The Designers and Contractors are specialist in the delivery of Coast Protection Schemes.

The Environment Agency is funding the Coast Protection Schemes and has recommended the use of their frameworks due to the rigorous process of selection and the terms of engagement. The Council will benefit from early contractor engagement and negate the requirement of lengthy procurement process.

3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council?

3.3Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered:

4.1The Council could undertake its own procurement exercise although this would require a significant amount of time and resource.

To not proceed with the coast protection scheme putting in excess of 3600 properties at increased risk of flooding.

5.0Council priority:

5.1The relevant Council priority is both:  “The economy: Maximising growth and opportunity across Blackpool”  “Communities: Creating stronger communities and increasing resilience”

6.0Background information

6.1The Blackpool Coastal Strategy (the strategy) was approved by the Environment Agency in 2012 and details the strategic approach to managing flood and erosion, risk to people, property and other assets in the strategy area over the next 100 years.

The strategy area extends 11km from Kingsway in the North of Blackpool to Squires Gate in the South and is divided into 6 sub-units. In order to achieve the objectives of the strategy a long list of options are included in the strategy that determine which options are viable technically, economically and environmentally.

The strategy also provides an outline programme for implementation of the Capital works to provide the technical, economic and environmentally solutions which is detailed in sub units along the strategy area.

The defences are visually inspected on an annual basis and the maintenance required is determined, however consideration is also given to the condition and the ability for repairs to maintain the integrity of the coast protection.

In respect of Sub cell B1.2 Little Bispham to Bispham and sub cell 1.4, Gynn Square to Cocker Square significant deterioration in the coast protection was detected and Blackpool Council applied for funding to accelerate these Capital works outline and planned in the strategy.

Following the delivery of the Outline business case in line with the Strategy for sub cells B1.2 and B1.4, and in recognition of the urgent need to maintain the integrity of the coast protection Blackpool Council has been allocated £61m for the Coast Protection Schemes in these two sub-areas.

6.2The Council do not have the in- house resources to design and construct the works and therefore need to appoint suitable Designers and Contractors.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
BLACKPOOL COAST PROTECTION SCHEMES: USE OF ENVIRONMENT AGENCY FRAMEWORK FOR SELECTION OF CONTRACTORS AND DESIGNERSReport 6 pages DownloadRead as text
PDF
EX32 EA FrameworkReport 7 pages Download

At this meeting

Whole meeting

Who was there

8 of 10 attended
LB
Lennox BeattieSecretary, expected
NB
Councillor Neal BrookesCommittee Member, present
GC
Councillor Gillian CampbellCommittee Member, present
JF
Councillor Jo FarrellCommittee Member, present
JH
Councillor Jim HobsonCommittee Member, present
JH
Councillor Jane HugoCommittee Member, present
LH
Lorraine HurstSecretary, expected
MS
Councillor Mark SmithCommittee Member, present
IT
Councillor Ivan TaylorVice Chair, present
LW
Councillor Lynn WilliamsChair, present

On this subject at Blackpool

Search all
  1. BLACKPOOL COAST PROTECTION SCHEMES - USE OF ENVIRONMENT AGENCY FRAMEWORK FOR SELECTION OF CONTRACTORS AND DESIGNERSThis decision
  2. Blackpool coast protection schemes - use of environment agency framework for selection of contractors and designersAgreed
  3. Review of blackpool coastal housing management agreementAgreed
  4. Blackpool coastal housing limitedAgreed
  5. Blackpool coastal housing limitedAgreed

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies