The Executive agreed the recommendations as outlined above namely: To approve the redevelopment of the former Blackpool Coastal Housing neighbourhood office site on Sidford Court providing two new two-bedroom bungalows That the Council bids to Homes England for capital grant to help fund the construction of the proposed two units. That the existing principal contractor, Tyson Construction, is formally instructed to build the additional units under the existing JCT Design and Build contract dated 09 November 2021. 4. To approve the additional expenditure to develop the additional bungalows and note the revised scheme costs outlined in Appendix 6b, to the Executive report, financial considerations
Word for word from the decision Blackpool published for this meeting.Source: democracy.blackpool.gov.uk
Report to: EXECUTIVE Relevant Officer: Antony Lockley, Director of Strategy and Assistant Chief Executive
Relevant Cabinet Member Councillor Mark Smith, Cabinet Member for Levelling Up - Place
Date of Meeting: 11 December 2023
CONSTRUCTION OF TWO ADDITIONAL COUNCIL HOMES AT GRANGE PARK (PHASE 2 HOUSING SITE), BLACKPOOL. 1.0 Purpose of the report:
1.1This report outlines the proposal and level of investment required to deliver two additional two-bedroom bungalows at Grange Park scheme (Phase Two site). These additional units will replace the existing Blackpool Coastal Housing neighbourhood office on Sidford Court, Grange Park. The report seeks formal approval for the units to be delivered as an addition to the existing build programme (EX34/2021). The report also updates Executive on the additional costs incurred by the scheme.
2.0Recommendation(s):
2.1To approve the redevelopment of the former Blackpool Coastal Housing neighbourhood office site on Sidford Court providing two new two-bedroom bungalows
2.2That the Council bids to Homes England for capital grant to help fund the construction of the proposed two units.
2.3That the existing principal contractor, Tyson Construction, is formally instructed to build the additional units under the existing JCT Design and Build contract dated 09 November 2021.
2.4To approve the additional expenditure to develop the additional bungalows and note the revised scheme costs outlined in Appendix 6b financial considerations.
3.0Reasons for recommendation(s):
3.1The site identified for the two additional units is currently occupied by a former Blackpool Coastal Housing neighbourhood office. The office building is currently being utilised by Tyson Construction as a temporary site office and the building will be demolished at the end of the scheme development which would leave a relatively small area of land for alternative use. It is not deemed suitable for use as open space due to its small size and location (adjacent to housing and Family Hub) making it difficult to maintain, of limited functional use and the potential to attract anti-social behaviour. New high-quality open space is incorporated into the existing designs for both the Phase 1 and 2 new Grange Park housing.
Demand for bungalows has been clearly demonstrated following the development of the Grange Park Phase 1 site. The bungalows on this site highlighted significant interest from the waiting list. Blackpool Coastal Housing lettings department have shared their support for the additional units. Both units tenure will be affordable rent, ensuring consistency across the scheme. The unit type will fully replicate that as provided on Phase 1 being wheelchair accessible and adaptable together with inclusion of private garden space and in curtilage car parking.
To ensure value for money, it is recommended that the additional units are built as part of the existing construction contract. This provides value for money in respect of site mobilisation and set up enabling the additional two units to be completed within the existing scheme delivery timeframe (to complete summer 2024). Development of the site as a standalone project would encounter viability and practical delivery issues due to the small size of the site.
To acknowledge the existing scheme cost was approved (EX34) based on the pre-construction tender estimate. The revised scheme cost reflects the tender return price (which in turn is in- line with the current construction market trends) a further uplift for inflation and minor design changes, agreed as a variation within delegated limits. It also covers the BCIS contractor uplift as a result of bringing forward the start on site of the Phase 2 site. Additional costs to-date are within allowable delegated tolerance.
3.2Is the recommendation contrary to a plan or strategy adopted or approved by the No Council?
3.3Is the recommendation in accordance with the Council’s approved budget? Yes
4.0Other alternative options to be considered:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.