CENTRAL HOUSING REGENERATION: PROJECT UPDATE AND INCLUSION OF COUNCIL HOUSING ASSETS IN PHASE 1

Agreed Executive 3 papers

Executive agreed this item on Monday 13 October 2025. Below is the council's own wording, with the papers it was decided on.

Item5

Resolved

The Executive agreed the recommendations as outlined above namely: 1. To note the progress on the delivery of Central Housing Regeneration programme. 2. To suspend the usual re-letting of these units to enable full vacancy to be achieved. 3. To resolve to commence activity to identify alternative provision for the use of the building at the corner of Central Drive and Rigby Road and to seek a formal decision once a relocation plan has been outlined. 4. To note that CPO Guidance Home Loss Payments (Prescribed Amounts) (England) Regulations 2023 will be followed in supporting those residents being required to relocate, providing Homes Loss and Disturbance payments, where applicable. 5. To allow that once full vacancy has been achieved, and subject to the relevant planning approvals, to demolish the existing two blocks totalling 12 flats to enable Central Housing Regeneration Phase 1 redevelopment.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive, 11 pages

Report to: EXECUTIVE

Relevant Officer: Alan Cavill, Director of Place Relevant Cabinet Member: Councillor Mark Smith, Cabinet Member for Economy and Built Environment Date of Meeting: 13 October 2025

CENTRAL HOUSING REGENERATION: PROJECT UPDATE AND INCLUSION OF COUNCIL HOUSING ASSETS IN PHASE 1 1.0 Purpose of the report

1.1To seek approval for the inclusion of the Council’s residential properties at Salthouse Avenue and Kent Road and the building located at the corner of Central Drive and Rigby Road within the Central Housing Regeneration Area Phase 1 scheme boundary in order to provide for comprehensive redevelopment of this area. To agree the approach to consulting those residents within the blocks to assist in their relocation. To seek delegation to enable a decision in respect of the subsequent appropriation for planning at the point planning permission is in place.

2.0Recommendation(s)

2.1To note the progress on the delivery of Central Housing Regeneration programme;

2.2To suspend the usual re-letting of these units to enable full vacancy to be achieved;

2.3To resolve to commence activity to identify alternative provision for the use of the building at the corner of Central Drive and Rigby Road and to seek a formal decision once a relocation plan has been outlined;

2.4To note that CPO Guidance Home Loss Payments (Prescribed Amounts) (England) Regulations 2023 will be followed in supporting those residents being required to relocate, providing Homes Loss and Disturbance payments, where applicable;

2.5To allow that once full vacancy has been achieved, and subject to the relevant planning approvals, to demolish the existing two blocks totalling 12 flats to enable Central Housing Regeneration Phase 1 redevelopment;

2.6To delegate authority to Director of Place, to appropriate for planning purposes the Subject Land under section 122 of the Local Government Act1972 and conditional on the grant of Planning Permission subsequently invoke section 203 and section 204 of the Housing and Planning Act 2016.

3.0Reason for recommendation(s)

3.1To enable meaningful and comprehensive Phase 1 redevelopment, providing impactful change in kick-starting the regeneration of the central area.

3.2Is the recommendation contrary to a plan or strategy approved by the Council? No

3.3Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered

4.1Not including the identified properties within the Phase 1 redevelopment area was considered as alternative option.

5.0Council priority

5.1The relevant Council priority is:  ‘Communities: Creating stronger communities and increasing resilience’

6.0Background and key information

Central Housing Regeneration – The Need

6.1In March 2022, Blackpool was confirmed as one of three Levelling-Up Pilot Areas. The pilot status reflects the determination of both Local and Central Government to support intervention that will bring about positive transformation of the town, in a systematic and wholesale manner. The overarching ambition, and underlying goal is improvement of life chances for our residents in the Inner Area through the provision of improved quality housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 5aAppendix 5a 1 pages Download
PDF
CENTRAL HOUSING REGENERATION: PROJECT UPDATE AND INCLUSION OF COUNCIL HOUSING ASSETS IN PHASE 1Report 11 pages DownloadRead as text
PDF
EX32 HRA PropertiesReport 12 pages Download

At this meeting

Whole meeting

Who was there

0 of 11 attended
LB
Lennox BeattieSecretary, expected
KB
Councillor Kath BensonCommittee Member, expected
NB
Councillor Neal BrookesVice Chair, expected
PB
Councillor Paula BurdessCommittee Member, expected
SC
Sarah ChadwickSecretary, expected
JF
Councillor Jo FarrellCommittee Member, expected
JH
Councillor Jim HobsonCommittee Member, expected
JH
Councillor Jane HugoVice Chair, expected
MS
Councillor Mark SmithCommittee Member, expected
IT
Councillor Ivan TaylorCommittee Member, expected
LW
Councillor Lynn Williams MBEChair, expected

On this subject at Blackpool

Search all
  1. CENTRAL HOUSING REGENERATION: PROJECT UPDATE AND INCLUSION OF COUNCIL HOUSING ASSETS IN PHASE 1This decision
  2. Central housing regeneration project area: delivery progress and relocation supportNoted
  3. Central housing regeneration area phase 1: progress update and prepare for compulsory purchase orderAgreed
  4. Central Housing Regeneration – Project update and acquisition of landAgreed

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies