BLACKPOOL CENTRAL - NEXT STEPS ON PROCUREMENT

Agreed Executive 6 papers

AI summaryBlackpool Council Executive approved procurement for the Blackpool Central town centre site using a public sector framework, and extended the Newmark HDH marketing consultant commission.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedUse an established public sector framework to find an Investor/Developer
MoneyCosts from Town Deal programmeMarketing consultant extension funded from existing Town Deal
What happens nextRun framework procurementIf no suitable framework, design own tender process
Who it affectsBlackpool Central site, town centreAround 10 acre cleared site, central to visitor economy

What was decided

The Council will run a procurement exercise for the Blackpool Central site using an established public sector framework agreement, with the Chief Executive, after consulting the Leader, delegated to appoint the preferred Investor/Developer. Report 2.1, 2.3

The existing commission with marketing consultants Newmark HDH will be extended to support the procurement, and the Head of Legal Services is authorised to sign all related legal agreements. Report 2.2, 2.4

Why

The site is strategic, lies at the heart of the town centre, and its regeneration is central to the Council's local and visitor economy ambitions. Report 3.1, 5.1

Market feedback indicated a full open market process would deter investors due to high cost, time and resource demands, while a framework offers speed and a pre-vetted list of parties. Report 7.1, 7.2

The Council has cleared the site, secured planning consent (Ref 21/0517), and engaged with the Department for Digital, Culture, Media and Sport; further delay risks the site staying vacant. Report 6.2, 6.4, 11.1

What happens next

Marketing consultants will support the procurement through to its completion, and equalities and climate considerations will be addressed at any future planning application stage. Report 2.2, 12.1, 13.1

The Head of Legal Services will execute legal agreements needed to progress the site, including disposal of land and appointment of the preferred Investor/Developer. Report 2.4, 10.2

The money

  • exceed £300m Estimated cost to deliver development of the whole site (alternative option considered and rejected) Report 4.2

Options considered

  • Chosen: Use an established public sector framework for procurement. Faster, pre-vetted suppliers; aligns with developer preferences for streamlined process; used previously on DWP Fylde View, MOD building and Multiversity Report 2.1, 7.1, 7.2
  • Rejected: Run a full open market procurement exercise. Unlikely to attract desired interest; high upfront tendering costs and protracted timescales could deter bidders Report 4.1
  • Rejected: Council funds and develops the site itself. Cost likely to exceed £300m; Council cannot raise the capital; site is seen as ideal for private sector investment Report 4.2
  • Rejected: Do nothing, no further promotion or procurement. Contrary to long-standing ambition and existing planning strategy; area likely to see further economic and environmental decline Report 4.3

Implications

  • Legal: Procurement will be governed by the Procurement Act 2023 and the Procurement Regulations 2024, which came into force on February 24, 2025. Report 10.1
  • Financial: Only immediate cost is extending the Newmark HDH commission, expected to be met from the existing Town Deal programme; any further Council funding will be a separate item. Report 9.1, 9.2
  • Risk: Without continued momentum, the site risks remaining vacant for a further prolonged period; planning consent Ref 21/0517 is already in place. Report 11.1
  • Other: Equalities and climate change considerations are not applicable at this stage but will be addressed in any future planning application. Report 12.1, 13.1

Who and where

  • Blackpool Council, as landowner and procuring authority Report 2.1, 10.2
  • Potential Investors and Developers approached via the framework Report 2.3, 7.1
  • Newmark HDH with the leisureway, retained as marketing consultants Report 2.2, 6.3
  • Blackpool town centre businesses, residents and visitor economy Report 3.1, 4.3
  • Department for Digital, Culture, Media and Sport and other Government Departments in supporting discussions Report 6.4

Timeline

  • February 24, 2025: Procurement Regulations 2024 came into force Report 10.1
  • October 2025: Final phase of demolition of the courts concluded, leaving a circa 10-acre site predominantly cleared Report 6.2
  • 4 September 2026: Scrutiny Committee Chair informed of the decision Report P52
  • 2026-09-14: Executive meeting date when the decision was made

Plain English for the jargon

  • Blackpool Central site: A strategic circa 10-acre site in the heart of Blackpool town centre, previously subject to land sale agreements with Nikal, now cleared and marketed for redevelopment
  • Public sector framework agreement: An pre-arranged list of suppliers, such as Pagabo, Constellia or Crown Commercial Services, that public bodies can call on to run a faster, more limited procurement
  • Town Deal programme: Existing funding stream from which the cost of extending the Newmark HDH marketing commission is expected to be met
  • MIPIM and UKReIIF: International and UK property investment events at which the Council and Newmark HDH have promoted the site
  • Planning consent Ref 21/0517: Existing planning permission that has established the basis for future development on the Blackpool Central site
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

The Executive agreed the recommendations as outlined above namely: 1. To agree that the Council proceeds with the procurement exercise relating to the development of the Blackpool Central site, with the proposed route to market being the use of an established public sector framework agreement. 2. To agree any necessary extensions to the existing commission with the marketing consultants (Newmark HDH) for the provision of support up to and through the procurement exercise. In the event that a suitable framework can not be found, then the Council will look to design and conduct its own tender process. 3. To delegate the responsibility to the Chief Executive, after consultation with the Leader of the Council, to approve the appointment of a preferred Investor/Developer following completion of the procurement exercise and to approve the terms of any associated legal, contractual, property or land arrangements necessary to progress the development of the Blackpool Central site 4. To authorise the Head of Legal Services to enter into, execute and complete all legal agreements and ancillary documents necessary to give effect to the above decisions.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Executive

Recommendation

2.1To agree that the Council proceeds with the procurement exercise relating to the development of the Blackpool Central site, with the proposed route to market being the use of an established public sector framework agreement.

2.2To agree any necessary extensions to the existing commission with the marketing consultants (Newmark HDH) for the provision of support up to and through the procurement exercise. In the event that a suitable framework can not be found, then the Council will look to design and conduct its own tender process.

2.3To delegate the responsibility to the Chief Executive, after consultation with the Leader of the Council, to approve the appointment of a preferred Investor/Developer following completion of the procurement exercise and to approve the terms of any associated legal, contractual, property or land arrangements necessary to progress the development of the Blackpool Central site

2.4To authorise the Head of Legal Services to enter into, execute and complete all legal agreements and ancillary documents necessary to give effect to the above decisions.

Reasons for recommendation

3.1The Blackpool Central site is a strategic site that lies within the heart of the town centre. The regeneration of the site is pivotal to the town’s regeneration programme and the Council ambitions to support both the local and visitor economy.

3.2The recommendations support the Council’s approach to seeking development of the site and follows the recent work undertaken by marketing consultants Newmark HDH with the leisureway, who have been working with the Council to promote the development potential that exists on the site and within the resort.

3.3Is the recommendation contrary to a plan or strategy adopted or approved by No the Council?

3.4Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered:

4.1The Council could choose to undertake a full open market exercise offering the site to the external market. This is unlikely to attract the type of interest that the Council are looking for on the site and could potentially put desirable bidders off from engaging with the Council, due to upfront costs for tendering, and the protracted timescales for an open market process to be undertaken.

4.2The Council could seek to obtain and fund development of the site itself. The level of funding required to deliver development of the whole site is likely to exceed £300m and it is highly unlikely to be able to raise capital to deliver the scheme. Notwithstanding this, the council’s vision and aspiration for the site remain, that this is an ideal site for the private sector to invest in and bring exciting, innovative new attractions to the resort taking advantage of the commercial opportunity that exists, whist helping to support the long-term regeneration of the town and supporting the strategic objective of growing a year-round tourism economy acting as a catalyst for wider private sector investment.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Blackpool Central Site Development Brochure 2026Appendix 5a 13 MB Download
PDF
Blackpool Central Site Development Brochure 2026Appendix 5a 13 MB Download
PDF
BLACKPOOL CENTRAL: NEXT STEPS ON PROCUREMENTReport 544 KB DownloadRead as text
PDF
BLACKPOOL CENTRAL: NEXT STEPS ON PROCUREMENTReport 544 KB Download
PDF
EX34 Blackpool CentralReport 220 KB Download
PDF
EX34 Blackpool CentralReport 220 KB Download

At this meeting

Whole meeting

Who was there

12 of 30 attended
LB
Lennox BeattieSecretary, expected
KB
Councillor Kath BensonCommittee Member, present
NB
Councillor Neal BrookesVice Chair, present
PB
Councillor Paula BurdessCommittee Member, present
SB
Scott ButterfieldOfficer, expected
SC
Sarah ChadwickSecretary, expected
DF
Councillor Dave FlanaganCommittee Member, absent
JH
Councillor Jim HobsonCommittee Member, absent
JH
Councillor Jane HugoVice Chair, present
LH
Lorraine HurstCommittee Member, expected
NJ
Neil JackCommittee Member, expected
ML
Martin LawtonOfficer, expected

All 30 on the meeting page

On this subject at Blackpool

Search all
  1. BLACKPOOL CENTRAL - NEXT STEPS ON PROCUREMENTThis decision
  2. Blackpool central - next stepsAgreed
  3. Blackpool central : next stepsAgreed
  4. Blackpool central multi-storey car park: tenant fit out worksAgreed
  5. Planning application 21/0527: former king edward vii picture house, central drive, blackpool, fy1 5qeApproved
  6. Proposed appropriation and disposal of land at blackpool centralAgreed

More from Blackpool Executive

All decisions
MeetingDecisionOutcome
12 Oct 2026 Adoption of the lancashire waste strategy 2026-2036The Executive agreed the recommendations as outlined above namely: 1. To approve the adoption of the final post-consu... Agreed Open
12 Oct 2026 Rent setting policyThe Executive agreed the recommendation as outlined above namely: To approve the Rent Setting Policy , attached at Ap... Agreed Open
12 Oct 2026 Adoption of the blackpool heritage investment strategy 2026-2031The Executive agreed the recommendations as outlined above namely: 1. To note the consultation findings and amendment... Agreed Open
12 Oct 2026 Establishment of a special educational needs and disabilities (send) specialist base at st mary's catholic academyThe Executive agreed the recommendations as outlined above namely: 1. To approve the establishment of a 20-place SEND... Agreed Open
12 Oct 2026 Blackpool childrens social care sufficiency strategy 2026-28The Executive agreed the recommendation outlined above namely: To approve the Blackpool Children’s Social Care Suffic... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies