Blackpool Borough Council
Audit Committee, Thursday 24 September 2026 at 6.00pm

INTERNAL AUDIT FOLLOW UP - CREDITOR PAYMENT FINANCIAL CONTROL ASSURANCE TESTING

Noted Finance 4 papers

AI summaryBlackpool's Audit Committee noted an internal audit follow-up on creditor payment controls. The follow-up found reasonable assurance overall, but identified a high risk user delegation gap and limited assurance over fostering payment controls in the Adults and Children's Finance Team.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedInternal audit follow-up on creditor payment controls
MoneyNot stated
What happens nextRecommendations in progressActions being implemented within current budget
Who it affectsCouncil departmentsThose using the TechOne creditors system

What was decided

The committee noted the progress report on the creditor payments internal audit follow-up. Report 1.1

Why

To let the committee consider an update on the audit recommendations and the actions being implemented to address them. Report 2.1, 3.1

What happens next

Council departments will continue implementing agreed actions on creditor controls within current budget constraints. Report 7.1, 8.1

Structured reconciliation procedures, clear recovery protocols and better information sharing are recommended to strengthen fostering payment controls. Report P21

Options considered

  • Rejected: No alternative options considered. Not applicable Report 4.1

Implications

  • Risk: A high risk recommendation was made on the user delegation function, which in its current form could let the same person raise and approve an order, raising fraud risk. Report P20
  • Risk: Significant evidence of retrospective purchase orders being raised, which is not aligned with procedures and could create budget monitoring and forecasting issues. Report P20
  • Risk: Limited assurance over governance, risk management and control within the Adults and Children's Finance Team for fostering payments, with gaps in preventing, detecting and recovering overpayments. Report P21
  • Financial: Controls will be implemented within current budget constraints. Report 8.1
  • Legal: Risks need to be effectively managed to comply with relevant legislation. Report 9.1

Who and where

  • Adults and Children's Finance Team (fostering payments) Report P21
  • Exchequer Services Team Report 6.1, P19
  • TechOne Systems Team Report 6.1
  • Council departments using TechOne for creditor payments Report 6.1, P19

Timeline

  • 12 December 2025: Original internal audit report on creditor payments issued Report 1.1
  • 2026-09-24: Audit Committee considered progress report on audit recommendations

Plain English for the jargon

  • TechOne: Council system used for purchase orders, payment approvals and supplier records
  • Exchequer Services Team: Council team that supports creditor management
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item5

Resolved

To note the Internal Audit Follow Up - Creditor Payment Financial Control Assurance Testing.
Word for word from the decision Blackpool published for this meeting. Source: democracy.blackpool.gov.uk

Follow this further

Built from Blackpool's papers

What the report saysPro

Report to Audit Committee

Purpose of the report

1.1To consider a progress report on the recommendations made in the internal audit report relating to creditor payments issued on 12 December 2025.

2.0Recommendation(s):

2.1To consider the actions being implemented to address the audit recommendations relating to creditor payments.

3.0Reasons for recommendation(s):

3.1To enable Audit Committee to consider an update and progress report on the audit recommendations.

3.2Is the recommendation contrary to a plan or strategy adopted or approved by the Council? No

3.3Is the recommendation in accordance with the Council’s approved budget? Yes

4.0Other alternative options to be considered:

4.1N/a

5.0Council priority:

5.1The relevant Council Priority is: Communities: Creating stronger communities and increasing resilience

6.0Background information

6.1The TechOne system is used for raising purchase orders, approving payments, and managing supplier records. The system includes built-in approval hierarchies and access restrictions designed to ensure financial governance and mitigate risks associated with unauthorised transactions. TechOne User access is overseen by the TechOne Systems Team, and access is reviewed monthly. User accounts are linked to the Council’s active directory, meaning that when IT disables a user’s network account, access to TechOne is automatically revoked. This integration reduces the likelihood of unauthorised users retaining system access. A quarterly TechOne User Access Audit randomly selects a sample of users to ensure access remains appropriate. Users verify the system functions and access levels they require, including Purchasing, General Ledger, Accounts Payable, Debtors, and Budgeting.

6.2The scope and assurance statement of the audit was as follows:

Scope

The scope of the audit was to ensure that key controls are operating in as part of the creditors payment process. This was part of cyclical financial control assurance testing carried out by internal audit on key financial systems.

Assurance Statement

We provide reasonable assurance that there is generally sound system of governance, risk management, and control in place within the Creditors systems and processes. Our testing broadly revealed a satisfactory level of compliance with existing controls.

The TechOne system and the Exchequer Services Team provide effective foundations for robust creditor management. Opportunities to further strengthen the control environment have been identified and recommendations have been made to promote greater consistency and alignment across Council departments.

We have however made a high-risk recommendation in respect of the user delegation function which is its current form could enable the same person to raise and approve an order. This increases fraud risk and therefore assurance in relation to this function is limited. Likewise, there is significant evidence of retrospective purchase orders being raised which is not align with procedures and could create budget monitoring / forecasting issues.

Our testing revealed significant weaknesses, providing limited assurance over the system of governance, risk management, and control within the Adults and Children’s Finance Team for fostering payments. Key gaps and instances of non-compliance were identified, including lapses in controls to prevent, detect, and recover overpayments. Implementation of structured reconciliation procedures, clear recovery protocols, and improved information-sharing processes is recommended to strengthen controls, mitigate risk, and enhance accountability and compliance.

6.3Does the information submitted include any exempt information? No

7.0List of Appendices:

7.1Appendix 5(a): Internal Audit Recommendations and Agreed Actions.

8.0Financial considerations:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(a) Audit Report and Agreed ActionsAppendix 5 312 KB Download
PDF
(a) Audit Report and Agreed ActionsAppendix 5 312 KB Download
PDF
INTERNAL AUDIT FOLLOW UP: CREDITOR PAYMENT FINANCIAL CONTROL ASSURANCE TESTINGReport 305 KB DownloadRead as text
PDF
INTERNAL AUDIT FOLLOW UP: CREDITOR PAYMENT FINANCIAL CONTROL ASSURANCE TESTINGReport 305 KB Download

At this meeting

Whole meeting

Who was there

0 of 15 attended
SB
Councillor Shaun BrookesCommittee Member, expected
SC
Councillor Simon CartmellCommittee Member, expected
SD
Sharon DavisSecretary, expected
JF
Councillor Jo FarrellCommittee Member, expected
MF
Councillor Mel FenlonCommittee Member, expected
TG
Tracy GreenhalghOfficer, expected
AH
Councillor Alistair HumphreysVice Chair, expected
LH
Lorraine HurstSecretary, expected
NJ
Neil JackOfficer, expected
AL
Arthur LoganSecretary, expected
BM
Councillor Bradley MitchellChair, expected
JM
Councillor Jon MorganCommittee Member, expected

All 15 on the meeting page

On this subject at Blackpool

Search all
  1. INTERNAL AUDIT FOLLOW UP - CREDITOR PAYMENT FINANCIAL CONTROL ASSURANCE TESTINGThis decision
  2. Internal audit follow up - illuminations serviceNoted
  3. Global internal audit standards self assessmentNoted
  4. Internal audit follow-up - operational function of securityNoted
  5. Internal audit plan 2026/27Approved
  6. Internal audit charter and mandate 2026/27Approved

More from Blackpool Audit Committee

All decisions
MeetingDecisionOutcome
24 Sep 2026 Minutes of the last meeting held on 11 june 2026That the minutes of the meeting held on 11 June 2026 be approved as a true and correct record. Approved Open
24 Sep 2026 Strategic risk register deep dive - commercialTo note the Strategic Risk Register Deep Diver regarding Commercial risk. To receive an overview of the different typ... Noted Open
24 Sep 2026 Internal audit follow up - illuminations serviceTo note the Internal Audit Follow Up – Illuminations Service. Noted Open
24 Sep 2026 Updated external audit plan and strategy for the year ending 31 march 2026To note the updated External Audit Plan and Strategy for the Year Ending 31 March 2026. Noted Open
24 Sep 2026 Audit and risk services quarter one reportTo note the Audit and Risk Services Quarter One Report. Noted Open