Resolved
RESOLVED, subject to the foregoing, that the report be accepted and the Quarter 3 Performance Information contained therein be noted.
Planning, Regulatory & General Licensing Committee noted this item on Thursday 12 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED, subject to the foregoing, that the report be accepted and the Quarter 3 Performance Information contained therein be noted.
Report Date 26th Feb 2020 Report Author: Steve Smith
BLAENAU GWENT COUNTY BOROUGH COUNCIL
Report to Chair & Members of Planning Regulatory & General Licensing Committee
Quarterly Performance Information Report Subject Quarter 3 October - December 2019
Report Author Service Manager Development & Estates
Directorate Regeneration and Community Services
Date of Meeting 12th March 2020
Key Words Performance Management
Speed and quality of decision making
Welsh Government Monitoring
Quarter 3 Oct – Dec 2019
1.0Background 1.1 Every local planning authority (LPA) in Wales is required to collect performance information regarding the speed of decision making on all types of planning and related applications. This is submitted to Welsh Government on a quarterly basis. 1.2 This report considers the most recent data published by WG. The information relates to the third quarter of the current financial year i.e. October to December 2019. 1.3 It was published on the Welsh Government website on 5th Feb 2020 at
https://gov.wales/development-management-quarterly-surveys Report Date 26th Feb 2020 Report Author: Steve Smith
2.0Options for Consideration
2.1I have included 3 tables to illustrate current performance. 1. Fig 1 - ranks the 25 LPA’s in order of speed of determining all applications “on time”. This is defined as within the 8 week target period or longer time that may be agreed with the applicant. 2. Fig 2 – ranks the LPA’s in Wales and in respect of the average time (in days) taken to determine all applications. 3. Fig 3. – shows decisions taken by Planning Committee that are contrary to the recommendation of its officers.
3.0Performance Information 3.1 Fig 1: this Council decided 100% of all applications in time. This compares to a Welsh average of 86%.
3.2Fig 2: on average it takes 60 days from registration to decision for this Council to decide each planning application. The Wales average is 87 days. Fig 3: 38% of Planning Committee decisions were contrary to officer 3.3 recommendation. The Wales average is 10%.
4.0Conclusion 4.1 Performance remains consistent.
4.2When measured against the indicator of all applications determined “on time”, the returns for the last 5 quarters are 100%, 94%, 100%, 99% and now 100%.
4.3There is a similar picture when looking at the indicator that measures the average time (in days) it takes to decide applications. Our return fluctuates but again, we are consistently above the Wales average. We have shaved 10 days off the average time since the last quarter which is pleasing.
4.4The number of decisions where Planning Committee overturns the officer recommendation is again very high and unfortunately is significantly above the Wales average and shows no sign of improving.
5.0Recommendation 5.1 That the report be noted. Report Date 26th Feb 2020 Report Author: Steve Smith
Fig. 1
Welsh Government Quarterly DM Survey Percentage of Planning Applications Determined “On Time” (Ranked in Order of Performance)
Percentage Determined On Time Welsh Quarter 3 19-20 Local Planning Authority % in time (no. of decisions)
1 Blaenau Gwent 100 (78) 2 Swansea 99 (465) Merthyr Tydfil 99 (76) 4 Brecon Beacons NPA 98 (169) 5 Vale of Glamorgan 97 (298) 6 Neath Port Talbot 96 (167) 7 Conwy 94 (196) Rhondda Cynon Taff 94 (256) 9 Powys 93 (306) 10 Monmouthshire 91 (299) 11 Isle of Anglesey 89 (195) 12 Cardiff 86 (628) 13 Denbighshire 85 (189) 14 Caerphilly 83 (231) Pembrokeshire 83 (189) 16 Wrexham 82 (243) Newport 82 (201) 18 Torfaen 80 (89) 19 Bridgend 75 (195) Carmarthenshire 75 (387) 21 Snowdonia NPA 73 (124) 22 Pembrokeshire Coast NPA 72 (85) 23 Ceredigion 63 (262) 24 Flintshire 63 (229)
25 Gwynedd - - WALES AVERAGE 86% Report Date 26th Feb 2020 Report Author: Steve Smith
Fig. 2
Welsh Government Quarterly DM Survey Average Time to Decide Applications in Days (Ranked in Order of Performance)
Welsh Days Local Planning Authority
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Quarterly Performance Information Quarter 3 October: December 2019Report | 549 KB | DownloadRead as text |
Follow Planning, Regulatory & General Licensing Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jun 2022 | Planning Applications ReportRESOLVED that planning permission be REFUSED. Application No. C/2022/0047 7 Beaufort Terrace, Beaufort, Ebbw Vale, NP... | Refused | Open |
| 16 Jun 2022 | Appeals, Consultation and DNS Update - June 2022RESOLVED that the report be accepted and the information contained therein be noted. | Noted | Open |
| 16 Jun 2022 | List of Applications decided Under Delegated Powers Between 17th February, 2022 and 30th May, 2022RESOLVED that the report be accepted and the information contained therein be noted. | Noted | Open |
| 3 Mar 2022 | Planning Applications ReportRESOLVED that planning permission be APPROVED. The Chair did not take part in the vote. C/2021/0386 Land to Southern ... | Approved | Open |
| 3 Mar 2022 | Application: C/2021/0253 Premier Club, William Street, Cwm, Ebbw ValeRESOLVED that the report be accepted and the inclusion of the following conditions on the planning permission to be i... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.