Resolved
RESOLVED that the report be accepted and that the Executive considered and approved the report and provided appropriate challenge to the financial outcomes in the report. (Option 1)
Executive Committee approved this item on Wednesday 24 June 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be accepted and that the Executive considered and approved the report and provided appropriate challenge to the financial outcomes in the report. (Option 1)
1.1The purpose of the report is to update members on the provisional outturn against revenue budget for the financial year 2019/2020 across all portfolios.
2. Scope and Background 2.1 This report provides details on the following:
Provisional outturn position at the end of 2019/2020 Details of significant adverse variances Provisional outturn for Fees & Charges Progress on the achievement of the Financial Efficiency Projects for 2019/2020
2.2This report forms part of the quarterly financial reporting framework to Members.
3. Options for Recommendation
3.1Option 1 (Recommended Option)
Members of the Executive Committee consider and approve the report and provide appropriate challenge to the financial outcomes in the report.
3.2Option 2 Members of the Executive Committee do not accept the report.
4. Evidence of how does this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan
4.1This report supports the Council Priority, “Efficient Council”, as it is part of the financial planning and reporting arrangements which support the Council’s financial resilience. 5. Implications Against Each Option
5.1Impact on Budget
5.1.1 The overall financial position across all portfolios at 31 March 2020, is a favourable variance of £0.48m (0.33%), against a total revenue budget of £147m. The figures are provisional and subject to external audit.
5.1.2 The outturn is an improvement on the forecast financial position at the end of December 2019, at which time the forecast was an adverse variance of £0.064m, as shown in the table below.
5.1.3 Across all Portfolios, the overall position is shown below: -
Portfolio/ 2019/2020 2019/20 Favourable/ Favourable/ Append Committee Revised Provisional (Adverse) (Adverse) ref: Revenue Outturn @ March Dec Budget 31 March 2020 2019 2020 £m £m £m £m
Underspending Portfolios
Corporate Services & Financial 14.725 14.709 0.016 0.007 2a Management & Strategy
Social Services 44.915 44.526 2b 0.389 0.074
Education 55.477 55.348 0.129 0.022 2c
Planning 1.056 1.024 0.032 (0.005) 2f
116.173 115.607 0.566 0.098 Sub Total (1)
Overspending Portfolios
Environment 29.523 29.534 (0.011) (0.20) 2e
Economy 1.516 1.516 0.000 0.049 2d
Licensing 0.065 0.074 (0.009) (0.011) 2f Sub Total (2) 31.104 31.185 (0.02) (0.162)
February (0.064) 0.064 Floods
Total 147.277 146.795 0.482 (0.064)
5.1.4 The table indicates that the provisional outturn is lower than the budget by £0.48m (across all services). This is after the application of £1m net drawings from specific reserves to address “one-off” in year planned expenditure, the most significant use of reserves being:
Downsizing & Redundancy Reserves - £332,000 (including Leisure Trust) ISB Reserve - £159,000 ICT Reserve - £91,000 Strategic Business Reviews - £169,000 (Leisure Trust, Silent Valley & Third Party Expenditure Review) Technology Park - £80,000
5.1.5 The full impact the provisional outturn has had on reserves and balances for 2019/2020 will be shown in the draft Statement of Accounts, at a later date.
5.1.6 The provisional outturn of £0.48m favourable variance is a significantly improved position to the forecast at December 2019 of £0.064m adverse variance. The major movements from that position are a result of:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix 1Appendix 1 | 163 KB | Download |
PDF |
Appendix 2Appendix 2 | 240 KB | Download |
PDF |
Appendix 3Appendix 3 | 71 KB | Download |
PDF |
Appendix 4Appendix 4 | 185 KB | Download |
PDF |
Revenue Budget Monitoring: 2019/2020 Provisional OutturnReport | 721 KB | DownloadRead as text |
Follow Executive Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Oct 2022 | Conferences, Courses, Invitations and EventsRESOLVED that Councillor D. Bevan, Armed Forces Champion be approved to attend. Annual Briefing, HMS CAMBRIA – Thursd... | Approved | Open |
| 26 Oct 2022 | Executive CommitteeRESOLVED that the Decisions be accepted as a true record of proceedings. | Decided | Open |
| 26 Oct 2022 | Forward Work Programme – 7th December 2022RESOLVED that the report be accepted and the Forward Work Programme for the Meeting on 7 th December 2022 be approved... | Approved | Open |
| 26 Oct 2022 | Sickness Absence Performance 2021/22RESOLVED that the report be accepted and t he Cabinet agree the ongoing actions to support improvement in attendance.... | Agreed | Open |
| 26 Oct 2022 | Statutory Maintained Schools Partnership AgreementRESOLVED that the report be accepted and the information in the report and appendices be noted. (Option 1) | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.