RESOLVED that the report be accepted and the Executive approve Option 2, namely to utilise the BGCBC Capital Programme Big Arch allocation (£1,000K) - An application to CADW for consent to undertake remedial works has been delayed and works can’t progress until consent is awarded resulting in actual works on site delayed until July 2021/22 at the earliest – the funding will be reviewed / reinstated prior to CADW approval and works on site. If Welsh Government subsequently agree the flood funding for the scheme then the £405k can then be ‘repaid’ to this capital allocation.
Word for word from the decision Blaenau Gwent published for this meeting.Source: democracy.blaenau-gwent.gov.uk
1.1The purpose of the report is to provide options for funding repairs to Aberbeeg Road.
2. Scope and Background
2.1Outlines possible method of funding for the remedial works for Aberbeeg Road.
3. Options for Recommendation
3.1Option 2: Utilise the BGCBC Capital Programme Big Arch allocation (£1,000K) - An application to Cadw for consent to undertake remedial works has been delayed and works can’t progress until consent is awarded resulting in actual works on site delayed until July 2021/22 at the earliest – the funding will be reviewed / reinstated prior to Cadw approval and works on site. If WG subsequently agree the flood funding for the scheme then the £405K can then be ‘repaid’ to this capital allocation.
4. Evidence of how does this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan
4.1To undertake remedial works to a damaged section of the A4046 following storm Dennis.
4.2Longitudinal cracking was reported to the Authority and following an inspection by the Borough’s Engineers the road was closed to vehicular traffic on public safety grounds while a site investigation was undertaken to determine the cause of the failure.
4.3The site investigation report has identified the remedial works required and also a recommendation to continue to close the northern lane of the carriage.
4.4The highway is currently restricted by means of traffic lights to one lane of traffic and assigned a 7.5tons weight limit.
4.5The A4046 is a strategic highway for vehicles and provide a southerly access to and from Ebbw Vale to Newport and the M4 - the restriction has resulted in a lengthy detour for vehicles over 7.5T via the A467 to Brynmawr. 4.6 Following a meeting with the Heads of the Valley Road contractor we were informed they probably intend to undertake a significant temporary traffic switch at Brynmawr in August, as part of their ongoing works. The current proposed traffic switch requires significant diversionary routes – including the A4046. The potential unavailability of the A4046 as a diversionary route for the proposed Heads of the Valleys works will result in additional traffic movements being displaced onto local roads and the potential for increased traffic disruption at Brynmawr. 4.7 A provisional programme for the proposed traffic switch works at Brynmawr – it is the weekend of 15/16th of August for an estimated duration of 12 weeks (completion mid-November). The Aberbeeg works is programmed to take 12 weeks and will initially overlap the HOV works at the initial stages of their contact. 4.8 Although we have a 7.5T weight restriction on the road HGV’s are still using this section of the highway as a short cut to and from Ebbw Vale - If we wait for HOV to complete their works we run the risk of not only working during the winter months but increase HGV traffic that may result in further damage/slippage to Aberbeeg Road and lead to a full closure.
4.9Progress/Timescale to date:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Sickness Absence Performance 2021/22RESOLVED that the report be accepted and t he Cabinet agree the ongoing actions to support improvement in attendance....
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.