Resolved
RESOLVED that the report be accepted and the progress made over the previous 12 months be noted (Option 1).
Executive Committee noted this item on Wednesday 21 July 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be accepted and the progress made over the previous 12 months be noted (Option 1).
1.1The purpose of the report is to update Members on progress made in delivery of Blaenau Gwent County Borough Council’s Flood Management Plan of 2016 up to April 2021.
2. Scope and Background
2.1The report provides the background to the Plan and summarises progress made on objectives and measures since its adoption, and approval by Welsh Government in 2016.
2.2The Plan highlights the hazards and risk of flooding and sets out how the Authority will work with other parties and local communities to manage the risks.
2.3The Plan sets out how over the six-year period, we will manage flooding so that the communities most at risk and the environment benefit the most.
2.4The objectives outlined in the Borough’s Flood Management Plan come under the headings: Social & Cultural, Economic, and Environmental
2.5The above objectives have been further classed into 3 categories: a. Prevention (11 Measures) b. Protection (15 Measures) c. Preparedness (8 Measures)
To achieve the objectives under the headings and categories, the Plan identifies measures designed to reduce flooding.
2.6Including the use of non-structural measures such as avoiding inappropriate development, and covering all aspects of flood risk management, including raising awareness of flooding and providing a better understanding of local flooding issues.
1 2.7 Section 19 Flood Investigation Report for Storm Water Flooding at Meadow Street and Railway Street, Llanhilleth: The Section 19 Flood Investigation Report for Storm Water Flooding at Meadow Street and Railway Street, Llanhilleth on 15th to 17th February 2020 is currently being finalised and will be presented to scrutiny in due course.
3. Options for Recommendation
3.1Options Appraisal
Option 1: Preferred option; That Members accept the Report and progress made over the previous 12 months.
Option 2: That Members do not accept the Report and recommend alternative actions going forward.
4. Evidence of how this topic supports the achievement of the Corporate Plan / Statutory Responsibilities / Blaenau Gwent Well-being Plan
The attached Appendix 2 is a table of the measures identified in the Plan. The table identifies the progress made since the Plan was adopted in December 2015, and also progress made since the last annual review in 2020. The measures evidenced in Appendix 2 demonstrates how the desired objectives of the Blaenau Gwent Well Being Goals, as well as the Wellbeing of Future Generations Act have been achieved
The findings of Appendix 2 can be summarised as follows:
4.1Prevention (BG01-04) Undertook a number of CCTV and Man Entry surveys of our culvert inlets to inspect their condition and to understand the flood risk and associated issues that could occur so that appropriate action can be taken at numerous locations including. i. Abertillery Old Ash Tip ii. Abertillery Bowls Club iii. HOV Culvert near Garnlydan. iv. Melbourne Rd, Abertillery
4.2Undertook significant schemes to alleviate flooding at the following locations. Ladies Row and King Street Tredegar. Culvert repairs at Victoria, Ebbw Vale. Remedial works at Cwmtillery Culvert. Remedial works to the embankment at Railway Terrace Aberbeeg.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
AppendixAppendix | 515 KB | Download |
PDF |
Flood Risk Management Plan (2016- 2022)Report | 482 KB | DownloadRead as text |
Follow Executive Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Oct 2022 | Conferences, Courses, Invitations and EventsRESOLVED that Councillor D. Bevan, Armed Forces Champion be approved to attend. Annual Briefing, HMS CAMBRIA – Thursd... | Approved | Open |
| 26 Oct 2022 | Executive CommitteeRESOLVED that the Decisions be accepted as a true record of proceedings. | Decided | Open |
| 26 Oct 2022 | Forward Work Programme – 7th December 2022RESOLVED that the report be accepted and the Forward Work Programme for the Meeting on 7 th December 2022 be approved... | Approved | Open |
| 26 Oct 2022 | Sickness Absence Performance 2021/22RESOLVED that the report be accepted and t he Cabinet agree the ongoing actions to support improvement in attendance.... | Agreed | Open |
| 26 Oct 2022 | Statutory Maintained Schools Partnership AgreementRESOLVED that the report be accepted and the information in the report and appendices be noted. (Option 1) | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.