Resolved
RESOLVED that the report be accepted along with the progress made as presented (Option 1).
Executive Committee decided this item on Wednesday 22 September 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be accepted along with the progress made as presented (Option 1).
1.1To outline progress made since the adoption of the Council’s Decarbonisation Plan and the declaration of a Climate Emergency on 24 September 2020.
2. Scope and Background
2.1The Decarbonisation Plan set out how we would deliver our commitment to the ambition of the Welsh Public Sector to achieve net Zero by 2030. It outlined how we could reduce our organisational emissions across nine transitions, see Appendices A and B.
2.2Since the plan was adopted a Decarbonisation Board (the Board hereafter) has been established chaired by the Managing Director consisting of a range of experienced officers from across the Council, for Terms of Reference, see Appendix C.
2.3The Board agreed to carry out readiness assessments for each of the nine transitions to understand what was already being done, and to identify the key actions we need to take to progress. This process is being based on good practice from the Place-based Climate Action Network (PCAN) at Leeds University. The transition areas are: Transport Direct Transport Commissioned Sequestration Procurement Goods Procurement Services Procurement Works Electricity Heat Waste 2.4 Making Good Progress The Board agreed that the first readiness assessment to be examined would be ‘Transport Direct’ making up 8% of our gross carbon emissions. Key stakeholders from a range of service areas were involved in the process held in May and June 2021 via online workshops, bringing valuable knowledge on progress and insight on how challenges can be overcome. It is of note that staff energy and engagement in giving time to the readiness assessment was high. The initial approach has provided a very good start and something that can be used to build on developing and shaping the process using feedback and learning as we move forward.
2.5The products from these workshops have been carefully considered by the Board and CLT in July 2021 with a number of high level actions agreed. These are outlined below with organisational leads identified:
2.5.1 Fleet Develop a fleet plan and resource its implementation by building costs into Corporate Medium Term Financial Plan. (Lead: Community Services) Develop and resource a low carbon depot. (Lead: Community Services) Ensure procurement arrangements are in place to support the plan. This needs to recognise the inter-dependant work on the new depot and collaborative opportunities at a regional and national level. (Lead: Commercial Services) Replace small fleet ULEV in phased way in line with available space, grid capacity and infrastructure. (Lead: Community Services)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 365 KB | Download |
PDF |
Appendix BAppendix B | 53 KB | Download |
PDF |
Appendix CAppendix C | 121 KB | Download |
PDF |
Appendix DAppendix D | 1.2 MB | Download |
PDF |
Appendix EAppendix E | 9.1 MB | Download |
PDF |
Progress update on Decarbonisation PlanReport | 606 KB | DownloadRead as text |
Follow Executive Committee at Blaenau Gwent and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Oct 2022 | Conferences, Courses, Invitations and EventsRESOLVED that Councillor D. Bevan, Armed Forces Champion be approved to attend. Annual Briefing, HMS CAMBRIA – Thursd... | Approved | Open |
| 26 Oct 2022 | Executive CommitteeRESOLVED that the Decisions be accepted as a true record of proceedings. | Decided | Open |
| 26 Oct 2022 | Forward Work Programme – 7th December 2022RESOLVED that the report be accepted and the Forward Work Programme for the Meeting on 7 th December 2022 be approved... | Approved | Open |
| 26 Oct 2022 | Sickness Absence Performance 2021/22RESOLVED that the report be accepted and t he Cabinet agree the ongoing actions to support improvement in attendance.... | Agreed | Open |
| 26 Oct 2022 | Statutory Maintained Schools Partnership AgreementRESOLVED that the report be accepted and the information in the report and appendices be noted. (Option 1) | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.